This text of 630 N.E.2d 1171 (Wartenberg v. Dubin, Dubin & Moutoussamy) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wartenberg v. Dubin, Dubin & Moutoussamy, 630 N.E.2d 1171, 259 Ill. App. 3d 89, 197 Ill. Dec. 47, 1994 Ill. App. LEXIS 246 (Ill. Ct. App. 1994).

Opinion

JUSTICE JOHNSON

delivered the opinion of the court:

Plaintiff, Thomas H. Wartenberg (hereinafter Wartenberg), brought an action under the Structural Work Act (111. Rev. Stat. 1991, ch. 48, par. 69) in the circuit court of Cook County against defendant, the architectural firm of Dubin, Dubin and Moutoussamy (hereinafter Dubin), to recover damages for injuries he sustained while working on the Merchandise Mart "el” platform in Chicago.

Dubin filed a motion for summary judgment asserting that it was not in charge of the work and that it did not owe Wartenberg a duty of care. The trial court granted the motion, finding that Dubin was not in charge of the work and that neither a duty nor proximate cause existed.

On appeal, Wartenberg opines that the trial court erroneously granted Dubin’s motion for summary judgment.

We affirm.

The record reveals the following pertinent facts. In 1982, construction commenced on a project called the Wells Street Viaduct and CTA Station Improvements (hereinafter the project). The Chicago Transit Authority (CTA) employed Envirodyne Engineers (hereinafter Envirodyne) as a design consultant to provide structural, civil, mechanical and electrical engineering services on the project.

In March 1983, at Envirodyne’s request, Dubin submitted a proposal for architectural design services including a preliminary architectural design fee and a construction document consultation fee for "Phase II” of the project. The proposal did not include the preparation of construction documents.

In January 1985, Dubin submitted another proposal for the completion of the "Phase II” architectural services enumerating the maximum architectural cost estimates. In November 1985, Envirodyne authorized Dubin to commence the services required to complete the work.

In 1988, Dubin’s field worker and staff architect, Richard Rucks, began visiting the construction site approximately once a week to "see how the work [Dubin] designed was going in place.” Rucks made observations and submitted reports of any potential design problems to Envirodyne.

In November 1987, the general contractor employed by the CTA, Cameron-Meccor Joint Venture and/or Cameron Construction Company, subcontracted with Wartenberg’s employer, Reliable Welding Company, to perform metal work on the project. In March 1989, Wartenberg injured his back while lifting a steel beam by rope from the street level to the "el” platform above.

Consequently, Wartenberg filed an action under the Structural Work Act against Dubin and other defendants, alleging that they were "in charge” of the work being performed at the work site and that they had a duty to provide proper equipment. Dubin moved for summary judgment. The trial court granted the motion on both counts, finding that Dubin did not control the work and was not involved in the actual construction of the project. The trial court also found that an architect’s presence at a construction site does not, in itself, create an "in charge of” situation as contemplated by the Structural Work Act. Wartenberg appeals.

The sole issue of contention on review is whether the trial court’s award of summary judgment in favor of Dubin was proper.

Wartenberg predicated recovery for his injuries on the Structural Work Act (hereinafter the Act) whose actionable language provides:

"Any owner, contractor, sub-contractor, foreman or other person having charge of the erection, construction, repairing, alteration, removal or painting of any building, bridge, viaduct or other structure within the provisions of this Act, shall comply with all the terms thereof ***.
* * *
For any injury to person or property, occasioned by any wilful violations of this Act, or wilful failure to comply with any of its provisions, a right of action shall accrue to the party injured, for any direct damages sustained thereby ***.” (Ill. Rev. Stat. 1991, ch. 48, par. 69.)

A statutory duty, therefore, is only imposed if Dubin "ha[d] charge of” the construction work.

Factors often used to establish the requisite "having charge” element of the Act are whether a defendant (1) actually supervised or controlled the work; (2) retained the right to supervise or control the work; (3) took part in activities at the work site; (4) supervised subcontractors; (5) was responsible for on-site safety; (6) was authorized to issue orders; and (7) had the authority to stop work. (Mahoney v. 223 Associates (1993), 245 Ill. App. 3d 562, 565.) Supplemental to these considerations are whether the party owned the jobsite equipment, was familiar with construction customs and practices, and whether the party was situated so as to assure worker safety or to alleviate equipment deficiencies or improper work habits. Mahoney, 245 Ill. App. 3d at 565; see Chance v. City of Collinsville (1983), 112 Ill. App. 3d 6.

The record in this case patently evinces that none of these considerations characterizes the role of Dubin. Dubin’s involvement in the project arose out of a series of letters exchanged between it and Envirodyne rather than a formal contract. It is necessary to examine the substance of these letters in order to ascertain the relationship between the parties and, more specifically, Dubin’s relationship to the construction site.

In his deposition, John W. Moutoussamy, managing partner of Dubin, stated that he wrote a letter to Envirodyne proposing "preliminary design development drawings for an agreed on amount of money” for the project. Such documents form the basis for construction contracts. Dubin created the drawings and Envirodyne approved them.

Additional letters were exchanged between the parties which discussed architectural services, specifications and cost estimates. Du-bin never agreed to participate in any phase of the actual construction or to supervise the jobsite direction of activities.

After construction began, Moutoussamy stated that Envirodyne asked Dubin to provide it with a "casual observation” service requiring an architect from Dubin to visit the site and "observe the construction for the purpose of determining [that] what is [on site] is generally in agreement with the documents.” Dubin provided this service and Richard Rucks was assigned to visit the site. Through Rucks, Dubin advised Envirodyne if anything on site did not conform with the documents Dubin had prepared. The on-site contractors were never routinely advised by Dubin.

Moutoussamy also indicated that Dubin did not hire any personnel to work on the site. Further, Dubin neither had the authority to effect needed changes, nor did it have the authority to halt construction on the project if something was not in accordance with the requisite specifications.

Both Richard Rucks’ deposition testimony and affidavit are substantially similar to the facts provided by Moutoussamy. However, Rucks additionally stated that he visited the construction site initially on a weekly basis for about 10 months and then on a monthly basis for the last four months at the end of the project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Katonah v. USAir, Inc.
876 F. Supp. 984 (N.D. Illinois, 1995)
Skyview Film & Video, Inc. v. Safeco Life Insurance
864 F. Supp. 755 (N.D. Illinois, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
630 N.E.2d 1171, 259 Ill. App. 3d 89, 197 Ill. Dec. 47, 1994 Ill. App. LEXIS 246, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wartenberg-v-dubin-dubin-moutoussamy-illappct-1994.