Warren Bros. Co. v. Metropolitan Government of Nashville & Davidson County

540 S.W.2d 243, 1976 Tenn. App. LEXIS 238
CourtCourt of Appeals of Tennessee
DecidedFebruary 6, 1976
StatusPublished
Cited by10 cases

This text of 540 S.W.2d 243 (Warren Bros. Co. v. Metropolitan Government of Nashville & Davidson County) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Warren Bros. Co. v. Metropolitan Government of Nashville & Davidson County, 540 S.W.2d 243, 1976 Tenn. App. LEXIS 238 (Tenn. Ct. App. 1976).

Opinion

NEARN, Judge.

This is a dispute over the terms of a contract.

Metro desired that certain improvements be made to a portion of Charlotte Avenue in Nashville. Under circumstances later set out, Warren Brothers agreed to do the work. A part of the work consisted of laying storm and sanitary sewers. Trenches had to be excavated in order to lay the storm and sanitary sewer lines. Rock had to be excavated in order to dig the trenches. Warren Brothers sought separate payment under the “rock excavation” provision of the contract. Metro refused payment claiming that the rock excavation provision was inapplicable when excavating for storm and sewer lines. It was the position of Metro that the bid price of Warren Brothers included work for all excavation of either rock or common dirt when excavating for sewer and storm lines, that the bid on the sewer items included what rock excavation was entailed in that work.

Suit was filed by Warren Brothers seeking the additional payment under the contract for rock excavation, as well as payment for the cost of some cast iron fittings.

The Chancellor awarded judgment against Metro for the cast iron fittings in the amount of $82,706.00. Metro makes no complaint about the judgment for the cast iron fittings and such forms no part of this appeal. However, the Chancellor refused to award judgment in favor of Warren Brothers for rock excavation and Warren Brothers appeals from that portion of the judgment. It is stipulated that the rock excavation dispute involved $119,754.30.

Warren Brothers has filed five Assignments of Error with this Court. They raise but two issues for determination. The first is: Was the Chancellor correct in holding that under the contract Warren Brothers was not entitled to rock excavation payment? The second issue is: If the Chancellor was correct in the first instance, did he err in failing to give Warren Brothers relief under the theory of quantum meruit ?

[245]*245The bid contract document in Item I, “Unclassified Excavation”, under section 1.01 “Scope”, states that the work to be performed “shall consist of clearing and grubbing, loosening, loading, removing and disposing, in the specified manner, of all wet and dry materials (including rock) which are necessary to be removed for construction purposes; —.” Section “1.04 Rocks and Boulders” provides “(a) Rock shall be excavated over the horizontal limits of excavation and to a depth of not less than 6 inches below the bottom of pipe sewers — (b) Drilling and blasting operations shall be conducted with due regard for the safety of persons and property — .” Section “1.06 Excavation for Trenches, Manholes and Structures” provides “(a) Common excavation for sewer lines shall consist of the excavation necessary for the construction of sewer and other pipe lines and all appurtenant facilities therefor, — ”.

Section “1.15 Measurement and Payment” provides “(a) Trench excavation, backfill, except crushed stone backfill, and bedding will be considered an integral part of the work of sanitary or storm sewers and no separate payment therefor will be allowed — ”.

In Item II headed rock excavation under section “2.01 Scope” the following is found:

“Rock excavation shall cover the removal of all rock materials as hereinafter defined which shall require removal from their original beds within the limits hereinafter defined, for the purpose of construction as shown on the plans or set forth in these specifications. It shall include all drilling, blasting and all other items incidental to such removal, and also the necessary disposal of excavated materials as specified for Item I, Common Excavation.”

Section “2.05 Payment” provides “Payment for rock excavation performed under these specifications shall be made for the quantities determined in the manner specified above at the contract unit price per cubic yard as listed under Item II of the Contract Pay Items — ”.

Item II of the Contract Pay Items provided for payment of rock excavation at $30.00 per cubic yard.

By separate addendum to the contract, Warren Brothers also agreed to install street light bases at $178.34 each and pull boxes at $155.00 each. The addendum also explicitly provided that any rock excavation necessary in the installation of bases and boxes would be in compliance with “Item II, Rock Excavation and shall be paid for at the Contract Unit Price per cubic yard”.

As to Item II rock excavation the addendum then provided:

“This Item shall pertain to rock removed for Street Light Bases, Pull Boxes, Retaining Walls and other Structure Excavation, but shall not pertain to the installation of Storm Sewers, Sanitary Sewers, Manholes, Inlets or Water Mains and their Appurtenances.” (The emphasis is not supplied by the Court. The word “not” was underlined by typewriter in the original document.)

The Chancellor found the following to be the events and their sequence:

“1. During the year 1972 Metro advertised for contractors to bid on construction of certain improvements to be made for the widening and improving of Charlotte Avenue between Fourteenth Avenue North and Twenty-Fourth Avenue North in Nashville.
“2. Warren obtained from Metro copies of the proposals, contract documents, plans and specifications. Following receipt of the above documents Addendum No. 1 was mailed to Warren and received on January .5, 1973.
“3. Warren submitted a sealed bid on the forms provided by Metro and the bids were opened on January 11, 1973, and Warren was low bidder.
“4. By letter of January 12, 1973, Warren agreed to accept the provisions of Addendum No. 1 with the understanding that a contract supplement would be prepared.
“5. On March 8, 1973, the parties signed a contract, drawn and prepared by [246]*246Metro, covering the work to be done on the project.
“6. On March 12, 1973, contract supplement No. 1 was signed by the parties.
“7. On April 16, 1973, at a pre-con-struction conference the question arose as to whether rock excavation encountered in storm sewer construction would be paid for as a separate item.
“8. On April 17, 1973, Metro by letter notified Warren that “there shall be no extra payment for rock excavation encountered in the storm sewer construction.”

The evidence does not preponderate against the Chancellor’s findings.

It is the position of Warren Brothers that section “1.01 Scope” simply states in general terms the work to be done, and that Warren Brothers did perform that work. That section 1.04 specifically provides for rock excavation work; that section 1.06 specifically provides for common excavation work; and that the term “Trench Excavation” as used in section 1.15 governing payment applies only to common excavation work. Therefore, Warren Brothers argues, it is entitled to separate payment for the rock excavated in digging the trenches at $30.00 per cubic yard as provided in section 2.05 of the rock excavation item. Warren Brothers argues that if that is not what the contract provides, it certainly is not clear on the point and should be most strongly construed against the drafter, Metro, and in favor of Warren Brothers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Victor Cole v. Joe Caruso
Court of Appeals of Tennessee, 2018
Forrest Construction Co. v. Laughlin
337 S.W.3d 211 (Court of Appeals of Tennessee, 2009)
Amprite Electric v. Tennessee Stadium Group
Court of Appeals of Tennessee, 2003
First American v. Fitzgerald
Court of Appeals of Tennessee, 1997
Castelli v. Lien
910 S.W.2d 420 (Court of Appeals of Tennessee, 1995)
WF Holt Co. v. a & E Elec. Co., Inc.
665 S.W.2d 722 (Court of Appeals of Tennessee, 1983)
Tennessee Asphalt Co. v. Purcell Enterprises, Inc.
631 S.W.2d 439 (Court of Appeals of Tennessee, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
540 S.W.2d 243, 1976 Tenn. App. LEXIS 238, Counsel Stack Legal Research, https://law.counselstack.com/opinion/warren-bros-co-v-metropolitan-government-of-nashville-davidson-county-tennctapp-1976.