Amprite Electric v. Tennessee Stadium Group

CourtCourt of Appeals of Tennessee
DecidedJuly 10, 2003
DocketM2002-00892-COA-R3-CV
StatusPublished

This text of Amprite Electric v. Tennessee Stadium Group (Amprite Electric v. Tennessee Stadium Group) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Amprite Electric v. Tennessee Stadium Group, (Tenn. Ct. App. 2003).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE July 10, 2003 Session

AMPRITE ELECTRIC COMPANY v. TENNESSEE STADIUM GROUP, LLP

Appeal from the Chancery Court for Davidson County No. 99-2847-III Ellen Hobbs Lyle, Chancellor

No. M2002-00892-COA-R3-CV - Filed September 22, 2003

The electrical subcontractor on the Adelphia Stadium job was required by the contractor, on 212 occasions, to perform extra work. Although the subcontract provided that written change orders must precede and authorize extra work, this requirement was soon mutually abandoned because the contractor, encouraged by the owner, was concerned about a timely completion. The principal issue concerns the dollar amount of compensation for the extra work. Amprite priced its extra work according to manuals used in the construction industry, as contrasted to its actual costs plus 10 percent, as the subcontract provides. Amprite concedes that although its actual costs plus 10 percent were substantially less than the amounts claimed, the contractor was estopped to deny the greater compensation. The trial court held that the contract was abandoned and that, in lieu, a different contract would be implied. Amprite was accordingly awarded compensation for “8686 hours never worked, $90,245.00 for materials never purchased and $6,877.00 for taxes never paid,”for a total recovery of $1,131,311.66. Contractor appeals insisting that the contract was not abandoned and that its provisions control. We hold that the requirement of written change orders was waived by mutual agreement but that the remainder of the contract was enforceable. The judgment is modified to allow a recovery of $170,084.00.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court as Modified is Affirmed

WILLIAM H. INMAN , SR. J., delivered the opinion of the court, in which DAVID R. FARMER and HOLLY M. KIRBY, J.J., joined.

Phillip Byron Jones, Nashville, Tennessee, attorney for appellant, Amprite Electric Company.

Craig V. Gabbert, Jr., Nashville, Tennessee, and F. Barry McCabe, Atlanta, Georgia, for the appellee,, Tennessee Stadium Group, LLP. Todd E. Panther, Nashville, Tennessee, for the Amicus Curiae, The American Subcontractors Association, American Subcontractors Association of Middle Tennessee, and American Subcontractors Association of Western Tennessee.

OPINION

This litigation arises out of the construction of the NFL Stadium (“the Project”) for the Tennessee Titans. Amprite Electric Company (“Amprite”, “the Plaintiff” or “the Subcontractor”) was awarded a subcontract for the electrical work (“the Subcontract”) and was ultimately paid $10,890,000.00 in accordance with the Subcontract by Tennessee Stadium Group, L.L.P. ( “the Contractor” or “the Defendant”), a limited liability partnership of two foreign corporations experienced in the construction of large projects. During the construction, changes in the various drawings were required to be made, for which the Plaintiff seeks compensation attributable to the extra work occasioned by such changes.

As pertinent here, the Subcontract provides:

CHANGE ORDERS. Owner has reserved the right under the Contract documents to require Contractor to make changes in the work, including additions thereto and deletions therefrom. Without notice to any surety and without invaliding this Subcontract, Contractor may from time to time, by written order (“Change Order”) to Subcontractor, make changes in the work to the same extent and in the same manner as may be required of Contractor by Owner under the Contract documents. Subcontractor shall thereupon perform the changed work in accordance with the terms of this Subcontract and the Change Order.

Upon request of Contractor, and in time and manner sufficient to permit Contractor to comply with its obligations under the Contract documents, Subcontractor shall submit a written proposal for any applicable price and time adjustment attributable to the changed work, detailed as Contractor or Owner may require, supported and conforming to the requirements of the Contract documents.

Where a Change Order is issued pursuant to a change required by the Owner, the price shall be adjusted by the net amount of any direct savings and direct costs plus profit percentage attributable to the Change Order and the time for performance of the work may be adjusted according to the Contract documents . . .

-2- As used in this Subcontract, Subcontractor’s direct savings and direct costs shall mean and be limited to the actual amount of the following: cost of materials, including sales tax and cost of delivery; cost of labor, including social security, old age and unemployment insurance, and fringe benefits required by agreement or custom; worker’s compensation insurance; bond premiums if and to the extent actually increased; and actual rent not greater than the rent charged in the locale, or reasonable value of Subcontractor-owned equipment and machinery.

If the parties are able to agree upon the amount of the price adjustment and the extent of any time adjustment, such adjustments shall be set-forth in the Change Order which shall be accepted by Subcontractor. If the parties are unable to agree upon such adjustment, Contractor may elect to issue the Change Order to Subcontractor directly such work to be performed by Subcontractor and any adjustments to price or time shall be subject to ultimate determination in accordance with this changed work . . . in no event shall Subcontractor proceed with changed work without a Change Order issued pursuant to this paragraph 8 and Contractor shall not be liable for any additional costs incurred or delays encountered in the performance of such changed work without such a written Change Order.

From the beginning all parties understood that the construction of the stadium was to be aggressively performed. The Construction Management Agreement (“Contract”) between the Contractor and the Metropolitan Government of Nashville for Davidson County, Metropolitan Development and Housing Agency (“the Owner” or “ MDHA”), included a $10 million contingency fund to be used by the Contractor, in it discretion, to resolve problems arising from additional work in order to keep the Project on schedule. If this fund was not depleted the Contractor retained it as extra profit.

To the Subcontract was attached a document identified as Schedule H, which was to be utilized as a uniform method to track the nature and cost of extra work. It provided an agreed upon hourly rate for labor of $27.97 for extra work, and a flat percentage rate for small tool and other expenses. It was also agreed that the hours necessary to perform certain tasks would be those estimated by the National Electrical Contractors Association (“NECA”), and that the pricing of materials for extra work would be as prescribed by the Trade Service Corporation’s publication. While the basic Contract provided that Amprite would be paid ‘direct costs’ for extra work, Schedule H provided that, in calculating these costs, fixed or set rates and prescribed units would be used.

It was agreed that if Amprite was asked to make changes, it would provide Contractor with a Change Order Proposal, commonly referred to as a “COP.” Each COP would have attached a

-3- Schedule H in the format provided for in the Subcontract. Pricing would be consistent with NECA and the Trade Service Corporation. The COP would then be approved and thereafter, a change order would be issued, and the additional work would commence consistent with the Subcontract that provided that in no event was Amprite to perform extra work unless a change order was issued.

Schedule H was a creation of the Contractor’s Project Manager, which had used a similar method in construction of the Olympic Stadium in Atlanta, Georgia.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Win Myint and wife Patti KI. Myint v. Allstate Insurance Company
970 S.W.2d 920 (Tennessee Supreme Court, 1998)
Galleria Associates, L.P. v. Mogk
34 S.W.3d 874 (Court of Appeals of Tennessee, 2000)
Realty Shop, Inc. v. RR Westminster Holding, Inc.
7 S.W.3d 581 (Court of Appeals of Tennessee, 1999)
Gredig v. Tennessee Farmers Mutual Insurance Co.
891 S.W.2d 909 (Court of Appeals of Tennessee, 1994)
Adams v. Dean Roofing Co., Inc.
715 S.W.2d 341 (Court of Appeals of Tennessee, 1986)
Petty v. Sloan
277 S.W.2d 355 (Tennessee Supreme Court, 1955)
Werne v. Sanderson
954 S.W.2d 742 (Court of Appeals of Tennessee, 1997)
Whaley v. Underwood
922 S.W.2d 110 (Court of Appeals of Tennessee, 1995)
Commerce Street Co. v. Goodyear Tire & Rubber Co.
215 S.W.2d 4 (Court of Appeals of Tennessee, 1948)
Warren Bros. Co. v. Metropolitan Government of Nashville & Davidson County
540 S.W.2d 243 (Court of Appeals of Tennessee, 1976)
Hall v. Jeffers
767 S.W.2d 654 (Court of Appeals of Tennessee, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
Amprite Electric v. Tennessee Stadium Group, Counsel Stack Legal Research, https://law.counselstack.com/opinion/amprite-electric-v-tennessee-stadium-group-tennctapp-2003.