Warner v. City of New Orleans

87 F. 829, 31 C.C.A. 238, 1898 U.S. App. LEXIS 2035
CourtCourt of Appeals for the Fifth Circuit
DecidedMay 17, 1898
DocketNo. 691
StatusPublished
Cited by4 cases

This text of 87 F. 829 (Warner v. City of New Orleans) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Warner v. City of New Orleans, 87 F. 829, 31 C.C.A. 238, 1898 U.S. App. LEXIS 2035 (5th Cir. 1898).

Opinion

SWAYNE, District Judge

(after stating the facts as abové). As to nearly all of these defenses, we might well rest our decision in this east' on the opinion of the supreme court expressed in answer to the certified question. All the facts averred in the bill have either been admitted by the answer, or abundantly established by evidence. Indeed, the only fact in dispute between the parlies is the question of responsibility for the alleged defects in the drainage plan. So far, however, as the answer attempts to fasten this responsibility on the canal company and Van Norden, its transferee, as a defense to this action, it is entirely unsupported by the evidence, as the counsel for the city very frankly admitted in their argumen t at the bearing. The general plan under which the work was undertaken by the contractor was prescribed by the legislature in the act of 1871, which directed the canal company to dig canals above, below, and in the rear of the city, and with the earth removed therefrom to build levees to protect the city from overflow, and to dig such interior canals as might be necessary for the drainage of tin; city and the lands in the rear; but the rigid: to prescribe the location and number of all the canals was expressly vested in the city. As a matter of fact, the city, through its ordinances, based on the recommendation of the city engineer, located each of the canals that were excavated, and exercised direct supervision over the work, which the assistant engineer having charge of the work says was done strictly in accordance with the specifications furnished by the contractor, and well done. The principal objections made to the plan by some of the eminent, engineers who have testified are that it was not sufficiently extensive to meet the future requirements of a growing city like Yew Orleans, that it did not provide; the number of interior canals necessary to bold and carry off the excessive rainfall, and that the method of discharging the drainage water by means of pumps into the lake was too expensive, and was wrong from a sanitary point of view. Testifying by the light, of experience and investigation made by them since 1871, they give it. as their opinion that a greater number of canals should be excavated than called for by the plan, and that the drainage ought to be discharged into Bayou Bienvenue, some distance below the city proper, through the main canal, by means of a series of pumping stations. Oilier engineers of equal reputation — notably, Mr. Bell, who, as engineer of the city in 1871, devised the plan now condemned, and the present city engineer, and others — testify that the plan was a good one, and. if carried out, would have accomplished the drainage of the city. The cost of completing the work after the city purchased the drainage plant, as testified to by some of the witnesses for the defendant, would have been about Spoilt),000, if’paid for in cash, and not in warrant's. But it now appears that a new plan of drainage; has recently been adopted, which, incorporating and using all the old works, is estimated to cost, about 88,000,000. Without commenting further on the evidence on this part of the defense», our conclusion is that the plan under which the work was done by the canal company and its [834]*834transferee would, if carried out as contemplated, have sufficiently accomplished the drainage of the lands within the several districts to render the assessments available, if the city had kept the work in serviceable condition after its completion, as the law required. It is a singular fact that, while the answer in this case charges the failure of the drainage to the alleged defective plan and the work of the contractor, the principal ground of the decision in Davidson v. City of New Orleans, 34 La. Ann. 170, for annulling the judgment for one of these assessments, is that the city had abandoned the work, without any probability of renewing it, so that the work, in its incomplete state, was a detriment, rather than a benefit, to the lands. The failure of consideration which worked the destruction of the drainage fund was therefore, as adjudged by the supreme court of the state, caused directly by the fault of the city. Its conduct in this and other respects was a violation of its duty as a trustee, and was a breach of the covenant contained in the act of purchase, “not to obstruct or impede, but on the contrary to facilitate by all lawful means, the collection of the drainage assessments.” Treating the city, therefore, as a trustee, under an express duty to do whatever was reasonably required to make the drainage fund available for the purpose of paying the purchase warrants, a court of equity will apply the maxim “that equity looks upon that as done which ought to have been done.” “The true meaning of this maxim is that equity will treat the subject-matter, as to all collateral consequences and incidents, in the same manner as if the acts contemplated by the parties had been executed exactly as they ought to have been. * * * They are also deemed to have the same consequence attached to them, so that one party, or his privies, shall not derive benefit by his laches or neglect, and the other party, for whose profit the contract was designed, shall not suffer thereby.” 1 Story, Eq. Jur. § 64g. The city must therefore be treated as having done whatever was necessary to render the assessments available, and should be held to account for the drainage fund, as if collected and in hand.

It is claimed, however, that the city is not bound to account for the assessments and judgments against itself, as the quasi owner of the streets and other public places, on the ground that such assessments and judgments should be considered void ab initio, for the reason that public property is exempt from taxation. But we think the city, by drawing these warrants against the drainage fund, composed largely of these very assessments and judgments, is, under the principles laid down by the supreme court in the present case, estopped to deny their existence and validity, to the same extent that it is (‘stopped from setting up the issue of bonds under the act of 1872 as a discharge of its general liability as trustee with reference to the fund. As an original question, however, the authorities seem to affirm the liability of a municipal corporation for its proportion of the cost of local improvements, independently of the existence of any estoppel. In Re New Orleans Drainage Co., 11 La. Ann. 338, the supreme court of Louisiana held the city of New Orleans liable for assessments made on the area of the streets under the act of 1835, which is similar in all respects to the acts involved here, except that the assessments in [835]*835that case had not been ratified by the legislature, as was done in this instance by the act of 1871. This case has since been commented upon and affirmed in Marquez v. City of New Orleans, 13 La. Ann. 319, and Correjolles v. Succession of Foucher, 26 La. Ann. 362, and in Paving Co. v. Gogreve, 41 La. Ann. 259, 5 South. 848. The matter of local assessments has been the subject of judicial inquiry in other states, notably by the supreme court of Illinois in the case of County of McLean v. City of Bloomington, 106 Ill. 209, where all the objections raised in this case have been elaborately considered, and decided in harmony with the case above quoted. Says the court in that ease:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Scott County v. Advance-Rumley Thresher Co.
288 F. 739 (Eighth Circuit, 1923)
United States ex rel. Palmer v. Lapp
244 F. 377 (Sixth Circuit, 1917)
Bidwell v. City of Tacoma
67 P. 259 (Washington Supreme Court, 1901)
City of New Orleans v. Warner
101 F. 1005 (Fifth Circuit, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
87 F. 829, 31 C.C.A. 238, 1898 U.S. App. LEXIS 2035, Counsel Stack Legal Research, https://law.counselstack.com/opinion/warner-v-city-of-new-orleans-ca5-1898.