Warm Springs Dam Task Force v. Gribble

417 U.S. 1301, 94 S. Ct. 2542, 41 L. Ed. 2d 654, 4 Envtl. L. Rep. (Envtl. Law Inst.) 20666, 6 ERC (BNA) 1745, 1974 U.S. LEXIS 3947
CourtSupreme Court of the United States
DecidedJune 17, 1974
DocketNo. A-1146
StatusPublished
Cited by13 cases

This text of 417 U.S. 1301 (Warm Springs Dam Task Force v. Gribble) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Warm Springs Dam Task Force v. Gribble, 417 U.S. 1301, 94 S. Ct. 2542, 41 L. Ed. 2d 654, 4 Envtl. L. Rep. (Envtl. Law Inst.) 20666, 6 ERC (BNA) 1745, 1974 U.S. LEXIS 3947 (1974).

Opinion

Mr. Justice Douglas, Circuit Justice.

Applicants brought an action on March 22, 1974, in the United States District Court for the Northern District of California and sought a preliminary injunction to halt further construction in connection with the Warm Springs Dam-Lake Sonoma Project on Dry and Warm Springs Creeks in the Russian River Basin, Sonoma County, California. The applicants alleged, inter alia, that the Environmental Impact Statement filed by the Army Corps of Engineers concerning the project did not comply with the requirements of the National Environmental Policy Act of 1969,42 U. S. C. § 4321 et seg,

A hearing was held in the District Court on the motion for a preliminary injunction. On May 23, 1974, the Dis[1302]*1302trict Court rendered an oral ruling denying applicants’ motion for the injunction.1 A written opinion was filed thereafter. Applicants filed an application in the Court of Appeals for the Ninth Circuit for an injunction pending appeal, which was denied on May 24, 1974.

Application was then made to me as Circuit Justice for the Ninth Circuit seeking a stay of the order of the District Court as well as a stay restraining further construction work on the Warm Springs Dam Project. Because of the seriousness of the claims made by the applicants, I issued an order, on May 30, 1974, staying further disturbance of the soil in connection with the dam (other than research, investigation, planning and design activity) “pending reconsideration of the application when the memoranda of the Solicitor General and the Environmental Protection Agency are received.”

A response has been filed, along with further materials submitted by the applicants supporting their request for a stay. After consideration of these submissions, I have entered an order continuing my earlier stay order pending disposition of the appeal in this case by the Court of Appeals for the Ninth Circuit.

The Warm Springs Dam will be an earth-fill dam, holding back a reservoir of water, across Dry Creek, a major tributary of the Russian River in Sonoma County. The dam was first authorized, in smaller form than is now contemplated, in the Flood Control Act of 1962, Pub. L. 87-874, 76 Stat. 1173, 1192. On January 1, 1970, the National Environmental Policy Act, which requires the filing of an Environmental Impact Statement (EIS) for major federal actions significantly affecting the quality of the human environment, 42 U. S. C. §4332 (2)(C), [1303]*1303became law. A draft EIS was not distributed until June 1973, and the final EIS was not filed with the Council on Environmental Quality until December 4, 1973. I am informed that approximately $35 million has been expended on the project already, and that another $7 million will be expended before this case will be heard and determined by the Court of Appeals.

The applicants for this stay focus on two extremely serious challenges to the adequacy of the EIS.

First, they note that the dam will sit atop a geologic fault running along Dry Creek. There are other faults nearby. A town of 5,000 people is nestled below the dam and the wall of water it will restrain. At the District Court hearing on applicants’ motion for a preliminary injunction, substantial questions were raised about the integrity of the dam should an earthquake occur. There seems to be a recognized “credibility gap” as to the safety of the project; recommendations were received by the Corps from its own staff for further study; and reservations about the safety factor were expressed by the State of California. A contract has been made for further dynamic analysis of the safety of the dam. Should that analysis indicate that the dam is potentially risky, the Corps would have “no choice” but to consider abandoning the entire project. Tr. 1828-1829,1832.

Second, challenges were made at the hearing to the adequacy of the EIS regarding expected poisoning of water in the reservoir behind the dam. The water will be used by consumers in the surrounding county. There were allegations at the hearing that the waters will be poisoned by mercury carried from an abandoned mercury mine which will be inundated when the dam is built, and that asbestos, fluoride, and boron particles will also leach into the waters. It is contended that the EIS is deficient in its treatment of these significant environmental effects.

[1304]*1304The District Court rejected these contentions, finding that the Corps adequately dealt with the seismic problem and the water-poisoning problem. It found the EIS adequate. The Solicitor General argues that the District Court’s findings are not “clearly erroneous” and will be upheld by the Court of Appeals, and that therefore I should deny the requested stay.

Here, however, the views of the two federal agencies most intimately familiar with environmental issues and the requirements of the National Environmental Policy Act have been filed with the Court. They undermine the determination of the District Court.

The Environmental Protection Agency (EPA) has written to the Solicitor General expressing some doubt about the treatment of the water-poisoning issues in the final EIS.2 The EPA goes on to say, however, that:

“We wish to emphasize that the CEQ [Council on [1305]*1305Environmental Quality] is the Executive Office charged with NEPA administration and ultimately with evaluating the performance of Federal agencies in complying with the Act. We understand that the Council has expressed concern over the adequacy of the final environmental statement on the Warm Springs project and the issues raised by the Council clearly fall under its administrative responsibilities relative to NEPA.” Letter of June 4, 1974, from Alan G. Kirk II, Assistant Administrator for Enforcement and General Counsel, Environmental Protection Agency, to Robert H. Bork, Solicitor General.

The applicants have filed with this Court a letter from the General Counsel of the CEQ to the Solicitor General expressing the views of the Council on the adequacy of the Warm Springs Dam final EIS. Letter of June 11, 1974, from Gary Widman, General Counsel, Council on Environmental Quality, to Robert H. Bork, Solicitor General. In that letter, the Council expresses the view that the plaintiffs and the public are likely to be irreparably harmed if an injunction pending appeal is denied. The Council continues:

“It is the Council’s position that the best interests of the Government would be served by halting construction work (excluding environment study and testing) until the appeal is decided on the merits.
“In its letter of February 14, 1974, the Council advised the Corps that its Environmental Impact Statement (‘EIS’) was not adequate in several respects. The Council asked for further study and consideration of the earthquake hazard, the problems of stimulating population growth in the area, [1306]*1306the calculation of benefits and costs, and further asked consideration of an alternative project (enlargement of the existing Coyote Dam) that would not raise similar environmental problems.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Crosby v. Young
512 F. Supp. 1363 (E.D. Michigan, 1981)
Andrus v. Sierra Club
442 U.S. 347 (Supreme Court, 1979)
State of Alaska v. Carter
462 F. Supp. 1155 (D. Alaska, 1978)
WARM SPRINGS DAM TASK FORCE Et Al. v. GRIBBLE Et Al.
439 U.S. 1392 (Supreme Court, 1978)
Warm Springs Dam Task Force v. Gribble
431 F. Supp. 320 (N.D. California, 1977)
Mobil Oil Corp. v. Federal Trade Commission
430 F. Supp. 855 (S.D. New York, 1977)
Carolina Action v. Simon
389 F. Supp. 1244 (M.D. North Carolina, 1975)
Secretary of Environmental Affairs v. Massachusetts Port Authority
323 N.E.2d 329 (Massachusetts Supreme Judicial Court, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
417 U.S. 1301, 94 S. Ct. 2542, 41 L. Ed. 2d 654, 4 Envtl. L. Rep. (Envtl. Law Inst.) 20666, 6 ERC (BNA) 1745, 1974 U.S. LEXIS 3947, Counsel Stack Legal Research, https://law.counselstack.com/opinion/warm-springs-dam-task-force-v-gribble-scotus-1974.