Wark & Co. v. Twelfth & Sansom Corp.

107 A.2d 856, 378 Pa. 578
CourtSupreme Court of Pennsylvania
DecidedSeptember 27, 1954
DocketAppeal, 201
StatusPublished
Cited by26 cases

This text of 107 A.2d 856 (Wark & Co. v. Twelfth & Sansom Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wark & Co. v. Twelfth & Sansom Corp., 107 A.2d 856, 378 Pa. 578 (Pa. 1954).

Opinion

Opinion by

Mr. Justice Jones,

This litigation involves a dispute over the performance of a building contract and derives directly from a common law arbitration award in favor of the plaintiff contractor. The defendant answered and, by way of new matter, averred that the award was a nullity because the arbitrators, allegedly, had not properly discharged their function. The plaintiff’s reply to the new matter denied that there had been any improper activity on the part of the arbitrators. Thereafter, the plaintiff moved for judgment on the pleadings. The *580 court below refused the motion and this appeal followed.

The refusal of the plaintiff’s motion, under Rule 1034 of our Rules of Civil Procedure, for judgment on the pleadings is appealable by virtue of the Act of April 18, 1874, P. L. 64, 12 PS § 1097, which made appealable the refusal of the analogous motion, under prior practice, of judgment for want of a sufficient affidavit of defense: Rohm & Haas Co. v. Lessner, 168 Pa. Superior Ct. 242, 244-245, 77 A. 2d 675. Cf. also Epstein v. Kramer, 374 Pa. 112, 120, 96 A. 2d 912. It follows that, on such a motion, the allegations of the defendant’s answer are to be taken as true. The plaintiff’s reply to new matter, if any, is to be ignored: see Gary v. Lower Merion School District, 362 Pa. 310, 312, 66 A. 2d 762. But, a plaintiff’s motion for judgment on the pleadings (which, in effect, is a demurrer to the defendant’s answer) does not authenticate its inferences of fact and conclusions of law: London v. Kingsley, 368 Pa. 109, 111, 81 A. 2d 870. And, while summary judgment should be entered only in clear cases, where an answer to a complaint in assumpsit presents no meritorious legal defense to the claim, judgment for the plaintiff should, on motion, be summarily entered in the interest of expediting justice: MadisonKipp Corporation v. Price Battery Corporation, 311 Pa. 22, 25, 166 A. 377.

While the issue here present is, in form, a question of adequacy of pleadings, the case is directly concerned with the finality or conclusiveness of an award in an arbitration proceeding to which the parties voluntarily submitted in accordance with their written contract. Stated otherwise, the basic question is whether a party to a consensual arbitration may, in the absence of an allegation of fraud, bias or the like, set upon an in *581 quiry into the reasons and the mental processes by which the arbitrators arrived at their award.

The parties to the present action entered into a written building contract by which the plaintiff agreed to construct a public garage for the defendant. The contract called for progress payments and final payment thirty days after completion of the structure and approval of the work by the architect named in the contract. It also expressly provided for the arbitration of disputes arising out of the contract. When the plaintiff sought payment of the balance of the contract price which it claimed to be due, the defendant asserted counterclaims for allegedly defective work. The parties submitted the entire controversy to the American Arbitration Association for arbitration in accordance with the rules of the Association. Each of the parties selected an arbitrator and three others were designated by the Association to round out a panel of five. The plaintiff averred full compliance with the contract and completion of its obligations thereunder and claimed $20,205.47, with interest, as the unpaid balance. The defendant denied liability because of alleged faulty construction and counterclaimed in the sum of $75,478.89 as damages.

The arbitrators conducted hearings and received evidence from some ten witnesses, making a transcript of testimony of 387 pages. The arbitrators also personally inspected the garage. About a month after the hearings, the arbitrators reopened the proceedings and directed the plaintiff to obtain a certified statement from Clarence S. Thalheimer, the architect named in the building contract, as to the date of satisfactory completion of the garage. At the same time, the defendant was given an opportunity “to reply to the statement by Mr. Thalheimer.” The architect certified that the garage “was substantially completed by September *582 19, 1951, and satisfactorily completed by November 28, 1952.” The defendant’s “reply” to the architect’s certification asserted that Thalheimer’s status as architect had been terminated prior to the completion of the garage and that, as a consequence, his statement was entitled to no more weight than that given to an ordinary witness.

In due course, three of the five arbitrators announced an award in favor of the plaintiff and disallowed the defendant’s counterclaim. The majority award (which is permissible under the rules of the Arbitration Association) gave the plaintiff the full amount of its claim ($20,205.47) with interest thereon from December 28, 1952, i.e., thirty days after the date upon which the architect certified that the garage had been satisfactorily completed. A dissent to the award was filed by the two minority arbitrators which stated that the majority arbitrators had based the award not upon a consideration of the merits of the controversy but upon the certificate of the architect filed at the direction of the majority arbitrators. The dissent further asserted that the majority arbitrators believed it was “unnecessary for the arbitrators to decide the merits of the claims” since “the questions in issue were matters for the architect to decide and that he had decided” them. In a reply to the dissent, the majority arbitrators categorically stated that the award was “based not only on the architect’s certificates but on the weight of the evidence submitted and upon the arbitrators’ examination of the building.” Despite the undertaking of the parties in the submission agreement that they would “abide by and perform any Award rendered pursuant to this Agreement”, the defendant refused to comply with the award. The plaintiff thereupon instituted the present action in assumpsit to recover the amount of the award.

*583 The case basically involves a common law arbitration. Such proceedings have not been displaced by the Arbitration Act of April 25, 1927, P. L. 381, 5 PS § 161 et seq.: see Goldstein v. International Ladies’ Garment Workers’ Union, 328 Pa. 385, 389, 196 A. 43. The defendant freely admits that the dispute over the building contract was voluntarily submitted to the arbitrators for their determination in accordance with the rules of the American Arbitration Association; that the arbitrators conducted hearings on the merits of the controversy; and that a majority of the arbitrators (as permitted by Rule 27 of the Arbitration Association) rendered an award for the plaintiff which has not been paid. The defendant also concedes the settled legal principle that, unless the authority of the arbitrators is limited by the agreement of submission, they are the final judges of both law and fact, and an award will not be reviewed or set aside for a mistake in either: Electric Power Construction Co. v. Allen, Lane & Scott, Inc., 367 Pa. 319, 324, 80 A. 2d 799; Rosenbaum v. Drucker, 346 Pa. 434, 437, 31 A. 2d 117;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Malekzadeh v. Wyshock
611 A.2d 18 (Court of Chancery of Delaware, 1992)
Bloomsburg University v. Ass'n of Pennsylvania State College & University Faculties
552 A.2d 1180 (Commonwealth Court of Pennsylvania, 1989)
Devlin v. Shearson Hayden Stone, Inc.
21 Pa. D. & C.3d 213 (Delaware County Court of Common Pleas, 1981)
Lewis v. Erie Insurance Exchange
421 A.2d 1214 (Superior Court of Pennsylvania, 1980)
Lipman v. Cortazzo
19 Pa. D. & C.3d 287 (Lackawanna County Court of Common Pleas, 1980)
Hazleton Area School District v. Hazleton Area Education Ass'n
408 A.2d 544 (Commonwealth Court of Pennsylvania, 1979)
Reisman v. Ranoel Realty Co.
57 Pa. D. & C.2d 695 (Philadelphia County Court of Common Pleas, 1972)
Haddon Craftsmen, Inc. v. Bookbinders Local No. 97
281 A.2d 713 (Superior Court of Pennsylvania, 1971)
Toms v. Bev-Maid, Inc.
218 A.2d 300 (Supreme Court of Pennsylvania, 1966)
Scheirer v. Faith-Lehigh Plating Co.
37 Pa. D. & C.2d 777 (Lehigh County Court of Common Pleas, 1965)
Luria Steel & Trading Corp. v. Dittig
199 A.2d 465 (Supreme Court of Pennsylvania, 1964)
Walton v. Chilla
28 Pa. D. & C.2d 599 (Chester County Court of Common Pleas, 1962)
Bennett v. Kurland
21 Pa. D. & C.2d 587 (Luzerne County Court of Common Pleas, 1959)
Freeman v. Ajax Foundry Products, Inc.
20 Pa. D. & C.2d 128 (Philadelphia County Court of Common Pleas, 1959)
Syme v. Bankers National Life Insurance
144 A.2d 845 (Supreme Court of Pennsylvania, 1958)
Geyer v. Challenger Trailers, Inc.
16 Pa. D. & C.2d 61 (Alleghany County Court of Common Pleas, 1958)
Grossman v. Hill
122 A.2d 69 (Supreme Court of Pennsylvania, 1956)
Erie Insurance Exchange v. Gouse
119 A.2d 672 (Superior Court of Pennsylvania, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
107 A.2d 856, 378 Pa. 578, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wark-co-v-twelfth-sansom-corp-pa-1954.