Warford v. Industrial Power Systems

2008 DNH 192
District Court, D. New Hampshire·Decided October 20, 2008·No. CV-06-463-JL·Published

Opinion

Warford v. Industrial Power Systems CV-06-463-JL 10/20/08 UNITED STATES DISTRICT COURT DISTRICT OF NEW HAMPSHIRE

Douglas Warford, Isabelle Tavlor, LLC, and CNA Insurance Company

v. Civil No. 06-cv-463-JL Opinion No. 2008 DNH 192

Industrial Power Systems, Inc. and A.F. Theriault & Son Ltd.

FINDINGS OF FACT AND RULINGS OF LAW

The plaintiffs, Douglas Warford, Isabelle Taylor, LLC ("the shipowner"), and CNA Insurance Company, proceeding as Warford's assignee and the shipowner's subrogee, seek recovery for personal injury and property damage arising out of an explosion and fire on the shipowner's fishing vessel, the F/V Isabelle Taylor, insured by CNA. The defendants. Industrial Power Systems ("IPS") and A.F. Theriault & Son Ltd. ("Theriault"), have denied any liability. The court, which has jurisdiction under 28 U.S.C. § 1333(1) (maritime), conducted a bench trial in this matter over May 21-23 and May 26-27, 2008.

Each of the parties submitted a set of proposed findings and rulings both before and after trial; the parties also submitted a joint post-trial statement of agreed upon facts and timeline of significant events. With the assistance of these materials, the

court makes the following findings of fact and rulings of law, see Fed. R. Civ. P. 52(a), which result in the entry of judgment for the defendants on all claims.

Findings of Fact

1. The shipowner entered into contracts with a number of companies to work on converting the Isabelle Taylor into a mid­ water pair trawler capable of refrigerating her catch at sea, enabling her use in a "pair trawling" operation with two other vessels. The conversion work included installing a refrigeration system and upgrading the vessel's electrical system.

2. This work entailed the installation of three new electrical generators, to run the refrigeration system and to provide an auxiliary power supply for the vessel. These generators, manufactured by Caterpillar, Inc., were to be supplied by Southworth Milton, an authorized Caterpillar dealer, and to be installed by defendant Theriault while the vessel was at Theriault's shipyard in Meleghan River, Nova Scotia, where she was delivered in April 2003.

3. The shipowner (together with its parent company, Shafmaster Fleet Services) entered into a written contract with Theriault specifying the scope of its work on the conversion project. In relevant part, this contract provided that Theriault

would "[i]nstall 2 main engines, 3 gen[erator] sets, and hydraulic power engine, in cooperation with Caterpillar . . . . [C]onnect generators to ship's switchboard." Theriault was also responsible for converting the ship's electrical system--but not the generators themselves--from 220 volts to 480 volts.

4. The ship's switchboard was to be designed and installed by another contractor, defendant IPS, which entered into an agreement to that effect with the shipowner. IPS agreed, in relevant part, to "convert the vessel's switchboard to paralleling ability and to convert the ship to 480" volts. (The term "paralleling" refers to the proportional sharing of an electrical load among multiple power sources, in this case, the generators.) Theriault also agreed in its contract with the shipowner to provide "[s]upport and assistance to IPS technician(s) to convert switchboard to paralleling ability."

5. Theriault began its work converting the vessel in early April 2003. Plaintiff Warford was on board the vessel for most of this process, supporting the various contractors working on the conversion. Though Warford has no formal education or training in electrical engineering, he had worked on a number of fishing vessels, including the Isabelle Taylor, as the "ship's engineer," making him responsible for, among other things, the continued and safe operation of the vessel's electrical system during her voyages.

6. Theriault duly brought the new generators aboard the Isabelle Taylor by cutting open her decks and securing them to her structure. While connecting one of the generators--generato no. 2--to the ship's wiring, however, an electrician working for Theriault noticed that two of the lead wires necessary to make that connection had been mislabeled. In response, a representative from Theriault contacted Southworth Milton, which arranged for another Caterpillar dealer, Atlantic Tractor, to send a technician to fix the problem. Theriault explained that it proceeded in this fashion so as not to risk voiding the warranty on the generator. Atlantic Tractor's technician eventually arrived and rewired the generator.

7. Atlantic Tractor's technician also performed "start-up testing on the generators after they had been installed. As Atlantic Tractor informed the shipowner, however, this testing could not verify that the generators would perform properly unde a full electrical load, including the demands of the new refrigeration system. Atlantic Tractor further informed the shipowner that enabling the generators to run properly under a full load would require making adjustments to their voltage regulators, components which essentially control the generators'

output. Specifically, in an e-mail to Nick Jenkins, Shafmaster's fleet operations manager, Atlantic Tractor's representative indicated that Caterpillar would "be aboard for sea trials, when we can run the [refrigeration] gear, circ[ulation] pumps, etc., etc., so I don't see any need for a return visit by" IPS.

8. Don Edwards, a service technician for IPS, was on board the vessel for two weeks in October 2003, at work installing the switchboard designed by the company. Though Edwards had planned on "fine tuning" the voltage regulators as part of this work, the vessel could not yet produce the electrical loads necessary to complete that process, due principally to the fact that the new refrigeration system had yet to be installed. Edwards had also discovered that the regulators that came with the generators were not all made by the same manufacturer, which he believed would result in operational problems. He communicated this belief to both Southworth-Milton and the shipowner; Southworth-Milton told Edwards, in response, that the regulators should work fine together. Ultimately, Edwards asked Southworth-Milton to send a technician to set up the voltage regulators, but this request went unanswered. Edwards was unable to finish installing the switchboard during this period because he lacked certain components that had yet to be supplied by the shipowner.

9. Despite the incomplete nature of this and other aspects of the conversion project, the shipowner elected to remove the vessel from Theriault's shipyard on December 13, 2003. In a contemporaneous "Borrower and Shipyard Certificate" executed by the shipowner and Theriault, the shipowner acknowledged that the vessel was "complete," except for the electrical panel, refrigeration, electronics, and the fishing deck layout, which were the responsibility of contractors other than Theriault.

10. The vessel was returned to her home port of Newington, New Hampshire. While the generators were operable under the relatively small loads necessitated by this journey, the generators could not yet be paralleled, as Edwards informed Warford before he set out for Newington. This meant that the vessel was not ready for fishing, because the load demanded by the refrigeration system--which was not yet installed, in any event--required at least two generators running in parallel. Warford did not notice any problems with the generators during the voyage from Nova Scotia to Newington.

11. After the vessel returned, Edwards resumed his work on installing the switchboard until December 20, 2003. On that day, he and Warford worked together to parallel the generators, succeeding in getting them to share a load of 200 kilowatts. The men agreed, in fact, that "load sharing [was] fine," according to

Free access — add to your briefcase to read the full text and ask questions with AI

Warford v. Industrial Power Systems, 2008 DNH 192 (D.N.H. 2008).

2008 DNH 192 (Warford v. Industrial Power Systems) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Sagan v. United States
342 F.3d 493 (Sixth Circuit, 2003)
Winters v. Fru-Con Inc.
498 F.3d 734 (Seventh Circuit, 2007)
Malloy v. Doty Conveyor
820 F. Supp. 217 (E.D. Pennsylvania, 1993)
Curcuru v. Rose's Oil Service, Inc.
846 N.E.2d 401 (Massachusetts Appeals Court, 2006)
Knight v. Alaska Trawl Fisheries, Inc.
154 F.3d 1042 (Ninth Circuit, 1998)
In re Trailer & Plumbing Supplies
578 A.2d 343 (Supreme Court of New Hampshire, 1990)
Frantz v. Brunswick Corp.
866 F. Supp. 527 (S.D. Alabama, 1994)
Exxon Co. v. Sofec, Inc.
517 U.S. 830 (Supreme Court, 1996)