Walter Bishop v. Shirley Baubits

Court of Appeals of Washington·Decided March 9, 2021·No. 53142-9·Unpublished

Opinion

Filed

Washington State

Court of Appeals

Division Two

March 9, 2021

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

DIVISION II

WALTER “JIM” BISHOP dba BISHOP No. 53142-9-II ENTERPRISES,

Appellant,

v.

SHIRLEY BAUBLITS, UNPUBLISHED OPINION Defendant,

DONALD TUCKER AND PILAR TUCKER and the marital community composed thereof,

Respondents.

LEE, C.J. — Walter J. Bishop, doing business as Bishop Enterprises, appeals the trial court’s Judgment awarding him $18,731.15. Bishop argues that the trial court erred by 1) awarding the incorrect amount owed for the Oceanview project, one of the two underground work projects Bishop provided services for, and 2) denying him prejudgment interest. We disagree and affirm the trial court’s Judgment.

FACTS

A. BACKGROUND Donald Tucker orally contracted with Bishop, a general contractor, to have Bishop perform sewer and ground work for Tucker on two separate properties, Oceanview Park (Oceanview) and Milwaukee Drive (Milwaukee).

On November 20, 2017, Bishop filed a complaint against Tucker and his wife, Pilar Tucker, (the Tuckers) claiming that they failed to pay Bishop for part of the work. In his complaint, Bishop requested judgment against the Tuckers in the principal amount of $18,731.15 together with prejudgment interest, attorney fees, and costs. The $18,731.15 included $10,867.59 for Oceanview and $7,863.56 for Milwaukee. The $10,867.59 balance owed on the Oceanview project was based on Bishop’s bill to Tucker, which included $13,190.50 for labor and equipment, less payments Tucker had already made. B. BENCH TRIAL The matter was tried to the bench. Before the testimony began, Bishop informed the trial court that the amounts billed to Tucker for both Oceanview and Milwaukee were incorrect. 1 The trial court stated, “I understand you filed something that shows what you believe the correct figures are, it’ll be up to testimony as to what was actually submitted to the Defendants for payment.” Verified Report of Proceedings (VRP) at 25.

During trial, Bishop testified about his process for generating the bills sent to Tucker.

Bishop stated that his crew would fill out timesheets in notebooks. Noel Van Giesen, the foreman on the Oceanview project, generated a spreadsheet based on the timesheets. Bishop took the spreadsheets and typed the values into a billing statement. Bishop would also sit down with Van Giesen and go through the cost of materials used. Bishop also stated:

Because the materials, I have to go through the materials because, uh, I have to sit down with Noel and we have to talk about what we used, you know. Because a lot of our materials came from our stock. I mean, I have a supply at my house. I mean,

1 Bishop states on appeal that “[t]he Milwaukee billing . . . was correctly computed.” Br. of Appellant at 6.

we just don’t run down, you know, pick them all up at the same time. We might run into something—like the City changed valves on us and we had to turn around and reorder valves because they didn’t want the ones that we had.

VRP at 99. Bishop further stated that “I’m careful with the billings. They have to all, uh—they have to be, you know, accounted for. We don’t just make them up.” VRP at 102.

Bishop also testified that admitted Exhibit 62 was his bill to Tucker in the amount of $10,867.59 for the Oceanview project. The $10,867.59 amount owed reflects the amounts billed less the amount Tucker had already paid. The bill shows that the total for labor and equipment was $13,190.50. Bishop stated that he was not aware that the $13,190.50 amount in the total labor and equipment line of the Oceanview bill did not reflect the amounts of the individual itemized entries for labor included in the statement.3

2 All trial exhibits are included in the Clerk’s Papers. We also note that the exhibits lack page numbers. For our purposes we number each exhibit starting from the first page of the exhibit. 3 Exhibit 6 lists individual itemized entries for hours worked on the Oceanview project and the labor cost for each of those entries. Exhibit 6 also shows:

Total labor and equipment 13190.50 Total Materials 6060.04 total 19250.54 Tax .084 1617.05 20867.59

Less deposit 10000.00

TOTAL $10,867.59 Trial Ex. 6 at 7.

Bishop further testified that admitted Exhibit No. 7 was the bill for his work on the Milwaukee project.4 The bill shows that the amount owed on the Milwaukee project was $7,863.56. The total amount for the two projects as shown in the admitted Exhibits 6 and 7 is $18,731.15.

Bishop testified that his attorney recalculated the individual itemized entries in Bishop’s billings. An email from Bishop’s attorney to Tucker’s attorney stated that he ran adding machine tapes for the Oceanview and Milwaukee bills. “Oceanview comes to $14,209.00 instead of $13,190.50 [for equipment and labor] and Milwaukee comes to $18,636.96 instead of $10,944.21 [for subtotal].” Trial Ex. 10 at 2. When Bishop was asked if he could account for the $18,636.96 in his attorney’s email, Bishop stated, “No. I don’t know—I don’t know how he c[a]me up with that number.” VRP at 122. When asked if the amounts listed in his attorney’s email were the correct amounts for the projects, Bishop responded, “Not according to my billing here. But I don’t know where I could have made the mistake.” VRP at 122. However, Bishop later testified that

4 Exhibit 7 lists individual itemized entries for hours worked on the Milwaukee project and the labor costs for each of those entries. Exhibit 7 also shows:

Equipment and Labor 8,014.00 Materials 2930.21 subtotal 10,944.21 Tax 919.31 11,863.56

Less deposit -4000.00 Total $7,863.56

Trial Exhibit 7 at 4.

his attorney’s email included the correct balances owed, including taxes and prejudgment interest on Oceanview and Milwaukee projects. C. THE TRIAL COURT’S RULINGS The trial court entered Findings of Fact and Conclusions of Law. These findings and conclusions stated, in relevant part:

FOF NO. 1: Donald Tucker (“Tucker”) orally contracted with Plaintiff whereby Plaintiff agreed to perform certain sewer and ground work for Tucker on two (2) separate properties and Tucker agreed to pay Plaintiff for said work on a time-and-materials basis.

....

FOF NO. 7: Plaintiff’s unpaid charges for the work total $18,731.15.

....

CONCLUSIONS OF LAW NO. 1: Defendants personally owe Plaintiff $18,731.15 for Plaintiff’s work on the two properties.

Clerk’s Papers at 12. The trial court entered a judgment for Bishop in the amount of $18,731.15.

Bishop appeals.

ANALYSIS

A. OCEANVIEW BILL Bishop argues that the trial court erred by entering a judgment that included an incorrect amount owed for work performed on the Oceanview project. Bishop contends that “[a]n adding machine tape was run and the true itemized billing entries on the Oceanview invoice actually totaled $14,209.00: not $13,190.50.” Br. of Appellant at 5.

We apply a two-step standard of review for a trial court’s findings of fact and conclusions of law: first, we determine if the trial court’s findings of fact were supported by substantial evidence in the record, and if so, we next determine whether those findings of fact support the trial court’s conclusions of law. Landmark Development, Inc. v. City of Roy, 138 Wn.2d 561, 573, 980 P.2d 1234 (1999). “‘Substantial evidence exists if the record contains evidence of sufficient quantity to persuade a fair-minded, rational person of the truth of the declared premise.’” In re Marriage of Griswald, 112 Wn. App. 333, 339, 48 P.3d 1018 (2002) (quoting Bering v. SHARE, 106 Wash.2d 212, 220, 721 P.2d 918 (1986), cert. dismissed, 479 U.S. 1050, 107 S. Ct. 940, 93 L. Ed. 2d 990 (1987)), review denied, 148 Wn.2d 1023 (2003). Unchallenged findings of fact are verities on appeal. Fuller v. Employment Sec. Dept., 52 Wn. App. 603, 605, 762 P.2d 367 (1988). We review the trial court’s conclusions of law de novo. Casterline v. Roberts, 168 Wn. App. 376, 381, 284 P.3d 743 (2012).

Free access — add to your briefcase to read the full text and ask questions with AI

Walter Bishop v. Shirley Baubits, (Wash. Ct. App. 2021).

Walter Bishop v. Shirley Baubits (Walter Bishop v. Shirley Baubits) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Hansen v. Rothaus
730 P.2d 662 (Washington Supreme Court, 1986)
Prier v. Refrigeration Engineering Co.
442 P.2d 621 (Washington Supreme Court, 1968)
Bering v. Share
721 P.2d 918 (Washington Supreme Court, 1986)
Fuller v. Department of Employment Security
762 P.2d 367 (Court of Appeals of Washington, 1988)
Forbes v. AMERICAN BLDG. MAINTENANCE WEST
240 P.3d 790 (Washington Supreme Court, 2010)
Trummel v. Mitchell
131 P.3d 305 (Washington Supreme Court, 2006)
In Re Marriage of Griswold
48 P.3d 1018 (Court of Appeals of Washington, 2002)
SCOCCOLO CONST. v. City of Renton
145 P.3d 371 (Washington Supreme Court, 2006)
Landmark Development, Inc. v. City of Roy
980 P.2d 1234 (Washington Supreme Court, 1999)
Trummel v. Mitchell
156 Wash. 2d 653 (Washington Supreme Court, 2006)
Scoccolo Construction, Inc. v. City of Renton
158 Wash. 2d 506 (Washington Supreme Court, 2006)
Forbes v. American Building Maintenance Co. West
170 Wash. 2d 157 (Washington Supreme Court, 2010)
In re the Marriage of Griswold
112 Wash. App. 333 (Court of Appeals of Washington, 2002)
Casterline v. Roberts
284 P.3d 743 (Court of Appeals of Washington, 2012)
Falcon Insurance Co. v. Eli Lilly & Co.
479 U.S. 1060 (Supreme Court, 1987)