Walsh v. North American Cold Storage Co.

170 Ill. App. 393, 1912 Ill. App. LEXIS 791
CourtAppellate Court of Illinois
DecidedMay 21, 1912
DocketGen, No. 16,528
StatusPublished

This text of 170 Ill. App. 393 (Walsh v. North American Cold Storage Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walsh v. North American Cold Storage Co., 170 Ill. App. 393, 1912 Ill. App. LEXIS 791 (Ill. Ct. App. 1912).

Opinion

Mr. Justice Clark

delivered the opinion of the court.

This appeal brings up for review a decree entered in a mechanics’ lien case. The petition was filed by the appellees, Herbert S. Walsh and Michael C. Masterson, doing business as Walsh & Masterson, against the appellant, North American Cold Storage Company, and sundry other individuals and corporations who were charged to Aave an interest in the subject matter as contractors, sub-contractors, trustees under mortgage, holders of notes upon the mortgage, etc. The only lienors, however, who prosecuted the suit to effect were the appellees, Walsh & Masterson, and the American Bridge Company of New York. By the decree the former were awarded the sum of $8,713.20 and the latter $20,848.69. These amounts included interest from the dates that the contracts respectively were found by the master to have been completed, to the date of the master’s report, and also interest upon the amounts found to be due by the master from the date of his report to the date the decree was entered by the court. It was also ordered that the appellant pay to the appellees Walsh & Masterson $385.63 and to the Bridge Company $1,320.30, being the sums paid by them respectively to the master as fees.

The appellant, North American Cold Storage Company, in 1904 undertook the building of a large addition to its warehouse on North Canal street in the City of Chicago. Contracts were made with different independent contractors for various portions of the work. The contract entered into with Walsh & Masterson was for what was known as the sub-structure work, and that with the Bridge Company was for the steel work. The former contract was entered into on May 5, 1904, and the latter on June 9, 1904. The appellant also entered into three contracts with Carlson & Dunning, made respectively in June, August and October, 1904. These contracts were for mason work, ■tearing down a wall, etc. The addition to the building covered a space of about 60 by 60 feet, the old structure being about twice as long as and of equal width to the addition. The old structure was 15 stories in height, and the new 16 stories. There was no place for the storage of material to be used in the construction of the building except on the site itself, and material could only be delivered at the site at about the time the several contractors were ready to make use of it. Because of the difficulties in the way of contractors who were doing different portions of the work at the same time, and because of the lack of space for materials, a great many practical and serious difficulties were encountered in the construction of the building.

The contract of Walsh & Masterson provided that the work thereunder should be completed by June 5, 1904. The testimony tended to indicate and the master found that the work was completed on August 4, 1904; that this work was done by them to the satisfaction of the architect named in the contract, and that they furnished material and did extra work at the request of the appellant, the reasonable value of which was $791.13. The master further found that subsequent to the making of the contract with Walsh & Masterson changes were made by the appellant in the original drawings or plans; that the new plans were furnished some time during the month of June, 1904. There was testimony to the effect, and the master found, that during the progress of the work a change was again made in the plans, which necessitated the re-arranging of a row of piers and slight other changes, which required Walsh & Masterson to go further out into the river in building the dock and cofferdam in order to protect the foundations. It further appears that delay was caused because of the fact that the appellant did not obtain permission from a railroad company to excavate under the tracks west of the foundation, until about June 30, 1904. It appears that on June 8, 1904, Mr. Abbott, the architect, "wrote to Walsh & Masterson notifying them that the contract •time had expired for the completion of the work, and requesting them immediately to proceed to do certain work required of them under the contract. Letters were written by the appellant in June and July, complaining of the delay in the completion of the work, and to these letters Walsh & Masterson replied, in one letter giving as their reason for not proceeding with the excavation that it would be very dangerous to attempt to start it on so small a lot while the pile driver was being operated, and giving as a reason for not driving the sheet piling on the west end of the lot that the appellant had not arranged to divert the C. M. & St. P. trains, which would have to be done before the piles could be driven. The master in his report states that he was unable to determine the exact amount of delay that was caused by changes in the plans. He finds, however, that there was due Walsh & Masterson from the Storage Company the sum of $6,791.13, after the allowance of $5,000 theretofore paid by the Storage Company. This amount of balance is admitted by the appellant to be correct. On August 30, 1904, the architect referred to wrote Masterson to the effect that the work done by his firm was acceptable and that they were relieved from any responsibility touching the work should it be damaged by other contractors or by vessels passing along the river. Although demand was made for what is called a final certificate, no such certificate was issued, unless the letter referred to can be treated as such. The fact that no such certificate was issued is not relied upon by appellant as ground for reversal.

Prom the testimony the master found that the American Bridge. Company of New York employed the American Bridge Company of New Jersey to do most of the fabrication of the material which was used in the building; that the plans and specifications were prepared by the architect and submitted to the American Bridge Company of New York, the plans then being sent to the drafting department of the Detroit plant of the New Jersey corporation; that some of the drawings were not received at the Detroit drafting department until the month of September, 1904. The amount to be paid to the American Bridge Company under its contract was $41,000, and the work was agreed to be completed by September 1, 1904. The master found that the delay, changes, and lack of information from the appellant, resulted in considerable delay in the drafting of the shop drawings, and that thereby the time taken for the purpose of completing the working or shop drawings was prolonged about a month beyond what it ordinarily would have taken. The master further found that there were changes made in the plans of the architect subsequent to the entering into the contract with the American Bridge Company of New York, and some time during the progress of the work on the building; that these changes caused delay, the exact amount of which it was impossible from the evidence to determine; that it was impossible for the American Bridge Company of New York to proceed with the work until certain dimension stone, to be laid, as we understand it, by Carlson & Dunning under their contract, had been set on top of the piers heretofore referred to; that therefore the American Bridge Company could not commence its portion of the work on the building until August 8, 1904.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McDonald v. Patterson & Co.
57 N.E. 1027 (Illinois Supreme Court, 1900)
Manowsky v. Stephan
84 N.E. 365 (Illinois Supreme Court, 1908)
Ruddy v. McDonald
91 N.E. 651 (Illinois Supreme Court, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
170 Ill. App. 393, 1912 Ill. App. LEXIS 791, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walsh-v-north-american-cold-storage-co-illappct-1912.