Ruddy v. McDonald

91 N.E. 651, 244 Ill. 494
CourtIllinois Supreme Court
DecidedApril 21, 1910
StatusPublished
Cited by11 cases

This text of 91 N.E. 651 (Ruddy v. McDonald) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ruddy v. McDonald, 91 N.E. 651, 244 Ill. 494 (Ill. 1910).

Opinion

Mr. Justice Cooke

delivered the opinion of the court:

This is an appeal from the judgment of the Appellate Court for the Second District affirming a decree of the circuit court of Kane county.

Appellee, James J. Ruddy, filed his bill against appellant to enforce a mechanic’s lien. Early in the year 1904 appellant began the erection of a dwelling house according to plans and specifications drawn by architects employed by him. The contract for the plumbing and the installation of the heating apparatus, with the exception of the boiler, was let separately upon written bids. Appellee submitted bids to do the plumbing work for $846 and to put in that part of the heating apparatus specified for $760, the bids being based- upon the plans and specifications as prepared by the architects and furnished him by appellant. He was the lowest bidder, and the contract was awarded to him in June or July of that year. A written contract was prepared by the architects and executed by appellee but was never executed by the appellant. Appellant, however, was present when the bids were opened and personally awarded the contract to appellee upon his bids. The contract relied on here consists of the plans and specifications, the written bids and the-oral acceptance. The plumbing was put in and the heating apparatus installed under this contract and the same was accepted and approved by the architects in December, 1904. No objection was made by appellant to the plumbing and no effort made on the hearing to show that the contract in reference to the plumbing was not properly performed. Appellee claimed to be entitled to compensation for certain extra work done and material furnished in connection with the work done under this contract at the request of appellant; also for amounts due under two oral contracts made between him and appellant, one for the installation of a plant for the heating of appellant’s creamery and the other for the installation of a water lift. Upon the original contract appellant had paid appellee the sum of $500. Appellant by his answer denied that appellee had any right to a lien, and denied that the contracts, except the contract in reference to the plumbing,' had been performed by appellee. The cause was referred to a special master to take the testimony and to report his conclusions thereon. The master took the testimony and reported the same, together with his conclusions, to the court. He disallowed a part of the claim for extras and the claim for the water lift and made a slight deduction on account of the failure of appellee to put in the exact amount of radiation specified, and found that there was due from appellant to appellee on these contracts the sum of $1294.65, for which sum he found appellee was entitled to a lien, subject to the prior lien of a mortgage held by the Northwestern Mutual Life Insurance Company, and recommended that a decree be entered in accordance with such findings. Appellant filed numerous objections to the report of the master while the same was still in his hands, which were overruled. These objections were treated as exceptions before the court. Upon the hearing on the exceptions the same were overruled by the court and a decree entered in accordance with the findings and recommendations of the special' master, giving appellee a lien upon the premises for the sum of $1353.65, being the amount found due by the master together with interest at the rate of five per cent per annum from the date of the filing of the master’s report to the time of the rendition of the decree. Appellee did not object to any of the findings of the master, hence the action of the master in making his deductions from the claim of appellee is not presented for review.

Appellant contends that appellee did not install the heating plant according to the plans and specifications, and on account of his failure to comply with his contract in that respect is not entitled to a lien on the premises. Considerable testimony was taken before the special master in reference to the manner in which the heating plant was constructed and as to its efficiency. This testimony was sharply conflicting. The larger part of the argument of the appellant is taken up with an attempt to show that the findings of the master on that question are not supported by the weight of the evidence. There is evidence in the record to support each finding made. The chancellor, upon exceptions to the report, has confirmed the findings of the master in every particular. Where the evidence is conflicting and the chancellor has confirmed the findings of the master, this court will not disturb the decree unless it is clearly and manifestly against the weight of the evidence. (Siegel v. Andrews & Co. 181 Ill. 350; Duncan v. Duncan, 203 id. 461; Treloar v. Hamilton, 225 id. 102; Day v. Wright, 233 id. 218; Champion v. McCarthy, 228 id. 87.) We have examined this record carefully, and while we find the testimony very conflicting upon the matters in controversy in reference to the performance of the contract as to the heating plant, we cannot say that the weight of the evidence is clearly and palpably against the findings of the decree.

Appellant insists that appellee is not entitled to a decree upon the rpere finding that he has installed the heating plant in substantial compliance with the plans and specifications, for the reason that the specifications for the heating plant contained the following provisions: “The contract, when awarded, will be for a complete and perfect job, even though every item required to make it such is not specially noted in the drawings or these specifications,” and “contractor shall furnish all labor, tools and appliances necessary to complete his work according to these specifications, and shall perform his work in a true workmanlike manner in every particular and thus provide the building with a durable and mechanically perfect system, and should any defects in his work appear, contractor shall remedy such defects at his own cost within a reasonable time after receiving a written notice of same.” Appellant argues that on account of these provisions in the specifications appellee is not entitled to a lien upon a mere substantial compliance with his contract, but that he must install a system that is absolutely complete, durable and mechanically perfect, even though in so doing he should be required to furnish labor and material not indicated by the drawings and specifications or should be required to deviate from the drawings and specifications themselves. We do not think this is a fair interpretation to put upon the conditions contained in the specifications. They were undoubtedly meant only to require the. contractor to supply anything which might be omitted in the drawings and specifications themselves necessary to make a mechanically perfect job according to the general plan outlined in the drawings and specifications. We do not think it could be seriously contended that if the plans and specifications were so prepared and drawn, in their general design, as to provide for a job which would not be mechanically perfect and which could not give satisfactory results, the appellee would be denied his statutory lien upon showing that he had complied with the plans and specifications as detailed and agreed upon. These plans and specifications were presented to appellee by appellant as showing the general design of the heating system and the exact manner in which appellant desired to have it installed, and upon the acceptance of the bid became a part of the contract. Appellee did not contract to improve upon the plans of appellant and his architects but did obligate himself to follow them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Folk v. Central National Bank & Trust Co.
567 N.E.2d 1 (Appellate Court of Illinois, 1991)
Wirth v. Industrial Commission
347 N.E.2d 136 (Illinois Supreme Court, 1976)
St. Joseph Hospital v. Corbetta Construction Co.
316 N.E.2d 51 (Appellate Court of Illinois, 1974)
People v. Brown
214 N.E.2d 465 (Appellate Court of Illinois, 1966)
Koester v. Huron Development Co.
185 N.E.2d 196 (Illinois Supreme Court, 1962)
Placher v. Streepy
153 N.E.2d 369 (Appellate Court of Illinois, 1958)
Ellis v. Allen
154 S.W.2d 815 (Supreme Court of Arkansas, 1941)
Brownholtz v. Providers Life Assurance Co.
236 Ill. App. 494 (Appellate Court of Illinois, 1925)
Kelly v. Lehmann
217 Ill. App. 376 (Appellate Court of Illinois, 1920)
Martinet v. Duff
178 Ill. App. 199 (Appellate Court of Illinois, 1913)
Walsh v. North American Cold Storage Co.
170 Ill. App. 393 (Appellate Court of Illinois, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
91 N.E. 651, 244 Ill. 494, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ruddy-v-mcdonald-ill-1910.