Walsh Construction Company Puerto Rico v. United Surety and Indemnity Company

CourtDistrict Court, D. Puerto Rico
DecidedNovember 5, 2025
Docket3:12-cv-01401
StatusUnknown

This text of Walsh Construction Company Puerto Rico v. United Surety and Indemnity Company (Walsh Construction Company Puerto Rico v. United Surety and Indemnity Company) is published on Counsel Stack Legal Research, covering District Court, D. Puerto Rico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walsh Construction Company Puerto Rico v. United Surety and Indemnity Company, (prd 2025).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF PUERTO RICO

WALSH CONSTRUCTION COMPANY

PUERTO RICO,

Plaintiff, Civil No. 12-1401 (GLS)

v.

UNITED SURETY AND INDEMNITY COMPANY, Defendant.

OPINION AND ORDER

Walsh Construction Company Puerto Rico (“WCC”) filed breach of contract claims against United Surety and Indemnity Company (“USIC”) seeking compensation under a Subcontractor Performance Bond, which guaranteed the performance by InSite Corporation in the project named Seismic Correction Phase II/Outpatient Addition. Docket No. 1. The instant case was stayed on September 28, 2015, pending the outcome of litigation before the U.S. Bankruptcy Court in In re: Insite Corporation, Bank. Case No. 11-11209 (MCF). Docket No. 179. The stay was lifted on July 1, 2022. Docket No. 197. Both sides moved for summary judgment at Docket Nos. 202 and 205. On July 19, 2024, the Court issued an Opinion and Order finding in favor of WCC and against USIC. Docket No. 237. Having adjudicated liability against USIC, a bench trial on damages was held on March 11, 12, 13, and 14, 2025. Docket Nos. 292-295. WCC presented the testimony of Mark Brunski and Dennis González-Sánchez. USIC presented the testimony of Roque Pérez- Frangie. Documentary evidence was admitted and arguments were heard. The parties submitted post-trial briefs at Docket Nos. 305-306. I. Findings of Fact After hearing the testimonies of the witnesses and examining the documentary evidence submitted by the parties, the Court makes the following findings of fact: 1. WCC is a corporation organized under the laws of the State of Illinois, with principal place of business in Illinois. Docket No. 290 at Stipulated Facts No. 1. 2. USIC is a corporation organized under the laws of Puerto Rico, which is authorized by the Insurance Commissioner of Puerto Rico to issue performance and payment bonds for construction projects. Docket No. 290 at Stipulated Facts Nos. 2-3.

3. USIC is also certified by the Government of the United States to issue performance and payment bonds for federal construction projects. Docket No. 290 at Stipulated Facts No. 4.

4. On or about September 30, 2010, the Department of Veterans Affairs awarded WCC a contract titled Seismic Correction Phase II, Outpatient Addition (the “Project”). Opinion and Order at Docket No. 237 Uncontested Facts No. 1; Docket No. 290 at Stipulated Facts No. 5.

5. WCC entered in a subcontract with InSite Corporation (“InSite”) on November 23, 2010, for the performance of certain construction services in the Project (the “Subcontract”). Opinion and Order at Docket No. 237 Uncontested Facts No. 2; Docket No. 290 at Stipulated Facts No. 6; Joint Exhibit 1.

6. The Subcontract described the Subcontractor’s Work as “Furnish all labor, materials, equipment, insurance, taxes, and supervision as required to fully fabricate, deliver F.O.B. Project and install all Concrete and Masonry as more completely described in the exhibits attached hereto, in strict compliance with the plans and specifications and as directed by Contractor.” For the Subcontract Amount of $3,175,000.00. Joint Exhibit 1.

7. The scope of work of InSite included vertical and horizontal construction of roof decks and miscellaneous construction or masonry. This included providing all materials, labor, and equipment and ancillary costs to place permanent concrete, which included reinforcing steel and any formwork to hold up the desired shapes and strengths in place until the formwork could be removed. Transcript of the Hearing on March 11, 2025 at Docket No. 299 (“TR1”) 27 ¶¶ 8-17. It also included providing shop drawings to be reviewed and approved by the project architect and engineer, so that materials could be fabricated, and delivered to the site, rebar placed according to shop drawings and concrete poured in time. TR1 44 ¶¶ 20-25, 45 ¶¶ 1-7. It also included procuring, purchasing, and placing all components of the lightweight concrete on the Project. TR1 37 ¶¶ 17-25, 109 ¶¶ 7-14; Transcript of the Hearing on March 12, 2025 at Docket No. 300 (“TR2”) 96 ¶¶ 17-21. 8. The Subcontract provides that “The Subcontractor will complete all Work for the Subcontract Amount.” Joint Exhibit 1. The Subcontract was a lump sum all-inclusive contract. TR1 28 ¶¶ 7-8; TR2 at 104 ¶¶ 18-21.

9. InSite’s projected subcontracted work on the Project could impact the project schedule and/or the critical path. TR1 28 ¶¶ 9-12, 44 ¶¶ 2-25, 45 ¶¶ 1-7, 46 ¶¶ 1-15.

10. The critical path of a project is a sequence of events that must happen in a certain order within a certain time frame so that the overall project can be completed in the time frame required by the contract. TR1 28 ¶¶ 15-18. If a scope of work is on a project’s critical path and gets delayed, it has a negative impact on the project schedule because the trailing activities are either not allowed to start or the duration of those trailing activities must be rearranged or shortened. TR1 29 ¶¶ 8-15.

11. USIC issued a Subcontractor Performance Bond on March 22, 2011 (the “Bond”) in the amount of $3,175,000, naming WCC as obligee and InSite as principal, to secure the faithful performance of InSite’s obligations under the Subcontract with WCC. Opinion and Order at Docket No. 237 Uncontested Facts No. 3; Docket No. 290 at Stipulated Facts No. 7.

12. The Bond provides:

Upon declaration that Subcontractor is in default, Obligee may proceed to perform the Subcontract Work in accordance with the terms of the Subcontract. Obligee’s cost to perform Subcontract Work shall be credited against any remaining Subcontract balance and then reimbursed by Surety. Reimbursement by Surety shall reduce the penal sum of this Bond by the amount of reimbursement to Obligee. Docket No. 1-2 at Paragraph 4(f).

13. The Bond provides:

The Surety shall be liable for:

a. The responsibilities of the Subcontractor for correction of defective work and completion of the Subcontract Work.

b. The responsibilities of the Subcontractor for additional legal and design professional costs resulting or arising from the Subcontractor’s default, or resulting or arising from the actions or failure to act of the Surety under Paragraph 4 herein.

c. The responsibilities of the Subcontractor for damages caused by the performance or non-performance of the Subcontractor.

d. The Surety’s liability under this Paragraph 6 shall not exceed, in the aggregate, the penal sum set forth on the cover page of this Bond, subject to Paragraph 2. Docket No. 1-2 at Paragraph 6.

14. The Bond provides:

Surety agrees to pay Obligee its reasonable attorney’s fees and costs in the event that suit on this Bond is commenced and successfully prosecuted by Obligee. Docket No. 1-2 at Paragraph 7.

15. The Bond provides:

In the event of a dispute between Surety and Obligee related to the Subcontract or Bond, then either Surety or Obligee may institute litigation in the state or federal court where the project is located. Docket No. 1-2 at Paragraph 10.

16. Mark Brunski was the WCC project manager of the Project. He was responsible for all activities on the project, which included meeting with the subcontractors, processing paperwork, maintaining documents, and meeting with the owner of the Project. TR1 24 ¶¶ 8-12, 49 ¶¶ 1-8.

17. The Project lasted 35 months. TR1 24 ¶¶ 17-19.

18. WCC began to supplement InSite’s scope of work in August 2011. TR1 76 ¶¶ 11-22. InSite stopped performing work in the Project in December 2011. TR1 66 ¶¶ 15-24. InSite abandoned the Project without completing its scope of work in March 2012. TR1 70 ¶¶ 5- 10.

19. USIC did not complete InSite’s scope of work. TR1 75 ¶¶ 22-25.

20.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Prado Alvarez v. R.J. Reynolds Tobacco Co.
405 F.3d 36 (First Circuit, 2005)
Levin v. Dalva Brothers, Inc.
459 F.3d 68 (First Circuit, 2006)
Midrose Foods, Inc. v. Victor J. Roman
454 F.2d 1159 (First Circuit, 1972)
United States v. Iona M. Moore
923 F.2d 910 (First Circuit, 1991)
Smith v. Dorchester Real Estate, Inc.
732 F.3d 51 (First Circuit, 2013)
Reyes v. Banco Santander De P.R., N.A.
583 F. Supp. 1444 (D. Puerto Rico, 1984)
Oriental Financial Group, Inc. v. Federal Ins. Co., Inc.
598 F. Supp. 2d 199 (D. Puerto Rico, 2008)
Colon v. Blades
717 F. Supp. 2d 175 (D. Puerto Rico, 2010)
U.S. Bank Trust, N.A. v. Jones
925 F.3d 534 (First Circuit, 2019)
R & T Roofing Contractor, Corp. v. Fusco Corp.
265 F. Supp. 3d 145 (D. Puerto Rico, 2017)
Triangle Cayman Asset Co. v. LG and AC, Corp.
52 F.4th 24 (First Circuit, 2022)
Nimely v. City of New York
414 F.3d 381 (Second Circuit, 2005)
Rivera v. Crescioni
77 P.R. Dec. 47 (Supreme Court of Puerto Rico, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
Walsh Construction Company Puerto Rico v. United Surety and Indemnity Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walsh-construction-company-puerto-rico-v-united-surety-and-indemnity-prd-2025.