Wally Fischer v. Iowa Mold Tooling Company, Inc.

690 F.2d 155, 34 Fed. R. Serv. 2d 1554, 1982 U.S. App. LEXIS 24819
CourtCourt of Appeals for the Eighth Circuit
DecidedOctober 15, 1982
Docket82-1489
StatusPublished
Cited by23 cases

This text of 690 F.2d 155 (Wally Fischer v. Iowa Mold Tooling Company, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wally Fischer v. Iowa Mold Tooling Company, Inc., 690 F.2d 155, 34 Fed. R. Serv. 2d 1554, 1982 U.S. App. LEXIS 24819 (8th Cir. 1982).

Opinion

ARNOLD, Circuit Judge.

This is an interlocutory appeal pursuant to 28 U.S.C. § 1292(b) from the District *156 Court’s order denying the defendant Iowa Mold Tooling Co., Inc.’s motion to dismiss on the ground of limitations. The question presented is whether “commencement” of an action for purposes of applying the statute of limitations is governed by state law or Fed.R.Civ.P. 3. On the authority of Walker v. Armco Steel Corp., 446 U.S. 740, 100 S.Ct. 1978, 64 L.Ed.2d 659 (1980), we hold that state law governs in this diversity case. Under the law of South Dakota, the action was not commenced in time. We must therefore reverse the judgment and direct that the complaint be dismissed.

The relevant facts may be briefly stated. The complaint alleged that plaintiff was injured as a result of negligence on the part of the defendant in the design and manufacture of a hydraulic crane. The complaint was filed in the District Court on September 3, 1981, and the summons was issued by the Clerk and handed to the plaintiff’s attorney for service the same day. Since the accident at issue had occurred on September 6, 1978, the suit would, on the surface, appear to be timely under the applicable period of limitations, which all agree is three years. See S.D.C.L. § 15-2-14. Rule 3 of the Federal Rules of Civil Procedure provides that an action is commenced by filing a complaint.

The plaintiff’s difficulty arises from the fact that service on the defendant was not had within the three-year statutory period, and South Dakota law in general requires service in order to commence an action. S.D.C.L. § 15-2-30. The plaintiff’s attorney, apparently following accepted local procedure, received the summons from the Clerk on September 3, 1981, and mailed it to the Sheriff of the defendant’s home county in Iowa for service. The Sheriff received the summons on September 14; his return shows service on September 23,1981.

The plaintiff asserts first that this action was timely commenced because the defendant was served within a sixty-day extension period allowed by South Dakota law. He refers to S.D.C.L. § 15-2-31, which provides:

An attempt to commence an action is deemed equivalent to the commencement thereof when the summons is delivered, with the intent that it shall be actually served, to the sheriff or other officer of the county in which the defendants or one of them, usually or last resided; or if a corporation be defendant, to the sheriff or other officer of the county in which such corporation was established by law, or where its general business was transacted, or where it kept an office for the transaction of business. Such an attempt must be followed by the first publication of the summons, or the service thereof, within sixty days.

The plain language of § 15-2-31, however, reveals nothing helpful to the plaintiff. The attempt to commence the action occurs, under the statute, on the date the summons is placed in the hands of the sheriff. In this case that date is September 14, 1981, more than three years after September 6, 1978. The Supreme Court of South Dakota has emphasized that, in order for the sixty-day extension period to apply, the summons must be placed in the sheriff’s hands within the period of the statute. Arbach v. Gruba, 86 S.D. 591, 199 N.W.2d 697 (1972). 1

Mr. Fischer’s second argument is that, even ignoring the sixty-day extension period, his complaint was timely filed under Rule 3, which provides that “[a] civil action is commenced by filing a complaint with the court.” This rule, he asserts, is inconsistent with S.D.C.L. § 15-2-30, and the state law is therefore of no effect under the doctrine of Hanna v. Plumer, 380 U.S. 460, 85 S.Ct. 1136, 14 L.Ed.2d 8 (1965). Specifically, he *157 cites our decision in Prashar v. Volkswagen of America, Inc., 480 F.2d 947 (8th Cir. 1973), cert. denied, 415 U.S. 994, 94 S.Ct. 1596, 39 L.Ed.2d 891 (1974), which decided that “compliance with Rule 3 ... constitutes ‘commencement of an action’ sufficient to toll the South Dakota statute of limitations.” Id. at 948. Prashar clearly supports the plaintiff’s position. It would, in fact, carry the day but for the Supreme Court’s intervening unanimous decision in Walker v. Armco Steel Corp., 446 U.S. 740, 100 S.Ct. 1978, 64 L.Ed.2d 659 (1980).

Walker holds that there is no conflict between Rule 3 and state law, because the scope of Rule 3 is not so broad as the plaintiff contends. Justice Marshall’s opinion for the Court found “no indication that the Rule was intended to toll a state statute of limitations [footnote omitted], much less that it purported to displace state tolling rules for purposes of state statutes of limitations.” Id. at 750-751, 100 S.Ct. at 1985. Walker makes clear that there is no actual conflict between Rule 3 and state limitations law, as the plaintiff suggests. The only presently existing conflict is between our decision in Prashar and the Supreme Court’s decision in Walker. The latter must control.

The plaintiff suggests a distinction between the instant case and the situations in Walker v. Armco Steel, supra, and Ragan v. Merchants Transfer & Warehouse Co., 337 U.S. 530, 69 S.Ct. 1233, 93 L.Ed. 1520 (1949), which was specifically reaffirmed in Walker. The South Dakota commencement statute is a general one, not an “integral” part of the statute of limitations. It is true that this Court in Prashar v. Volkswagen, supra, indicated that the South Dakota commencement statute was not “integral” to the limitations statute because it did not specifically refer to limitations and because it defined the commencement of an action for other purposes as well. 2 Additionally, the Supreme Court in Walker v. Armco Steel, supra, referred to the actual service provision of the Oklahoma commencement statute as “an integral part of the several policies served by the statute of limitations.” 446 U.S. at 751, 100 S.Ct. at. 1985. Plaintiff’s point seems to be that the Oklahoma commencement statute was described by the Walker court as “integral,” that Prashar holds the South.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Good v. Sugar Creek Packing Co.
D. South Dakota, 2018
Schach v. Ford Motor Co.
210 F.R.D. 522 (M.D. Pennsylvania, 2002)
Moore v. Michelin Tire Co., Inc.
1999 SD 152 (South Dakota Supreme Court, 1999)
Marilyn M. Marshall v. Mikel Warwick
155 F.3d 1027 (Eighth Circuit, 1998)
Hart v. Bates
897 F. Supp. 710 (E.D. New York, 1995)
Wolfberg v. Greenwood Development Corp.
868 F. Supp. 132 (D. South Carolina, 1994)
Converse v. General Motors Corp.
893 F.2d 513 (Second Circuit, 1990)
Converse v. General Motors Corporation
893 F.2d 513 (Second Circuit, 1990)
Rogers v. Furlow
729 F. Supp. 657 (D. Minnesota, 1989)
Schebo v. Laderer
720 F. Supp. 146 (D. South Dakota, 1989)
Personis v. Oiler
714 F. Supp. 617 (N.D. New York, 1989)
Poulos v. Wilson
116 F.R.D. 326 (D. Vermont, 1987)
In Re the Alleged Mental Illness of Gillespi
397 N.W.2d 476 (South Dakota Supreme Court, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
690 F.2d 155, 34 Fed. R. Serv. 2d 1554, 1982 U.S. App. LEXIS 24819, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wally-fischer-v-iowa-mold-tooling-company-inc-ca8-1982.