Wallace O'Connor International, Ltd. v. United States

37 Cont. Cas. Fed. 76,165, 23 Cl. Ct. 754, 1991 U.S. Claims LEXIS 404, 1991 WL 165460
CourtUnited States Court of Claims
DecidedAugust 28, 1991
DocketNo. 532-89C
StatusPublished
Cited by4 cases

This text of 37 Cont. Cas. Fed. 76,165 (Wallace O'Connor International, Ltd. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wallace O'Connor International, Ltd. v. United States, 37 Cont. Cas. Fed. 76,165, 23 Cl. Ct. 754, 1991 U.S. Claims LEXIS 404, 1991 WL 165460 (cc 1991).

Opinion

OPINION

FUTEY, Judge.

This government contract case is before the court on defendant’s motion to dismiss [755]*755for lack of subject matter jurisdiction, or in the alternative, on cross-motions for summary judgment.1 Plaintiff, an electrical and mechanical subcontractor, alleges privity of contract with the government, and seeks compensation for the alleged retention of proceeds by the prime contractor under “the direction or knowledge” of defendant. Defendant argues that plaintiff advances a claim arising under a subcontract to which the United States was not a party, and alternatively, that plaintiff has not complied with the claim submission requirements of the Contract Disputes Act (CDA), 41 U.S.C. § 601 et seq. In its motion for summary judgment, defendant asserts that plaintiff’s retainage claim is legally insufficient.

Factual Background

On November 3, 1982, the United States Department of State—Office of Foreign Building Operations, awarded Kramico, S.A.E. (Kramico), contract No. 3416-231001, for the construction of a United States Embassy Facility in Cairo, Egypt. Kramico subcontracted most of the electrical and mechanical work on the project to Wallace O’Connor International, Ltd. (WOC).

WOC began work on the project in late 1983/early 1984. Shortly thereafter, WOC notified defendant that Kramico was delinquent in remitting progress payments for work performed on the project. On February 8, 1984, defendant issued Amendment No. 1 to the prime contract in an effort to alleviate Kramico’s nonpayment to WOC. The Amendment provided:

The Section 340 of the FM-2 Handbook 1/71 procedure for direct payment of non-Egyptian material suppliers by the Government will be employed for this project and is hereby incorporated into this contract as modified below:
******
345.1 The procedure is hereby amended so that the Government shall deduct the direct payments made to suppliers from the Gross Amount Earned in determining the “Amount now due” to the Contractor on the monthly Contract Estimate, Form FS 379A only when the materials corresponding to the payments have been included in the Gross Amount Earned as materials “on site” within the meaning of Article 47(b) above or incorporated into the structure as approved by the Project Manager. The Contractor shall grant the Government the finance and administrative price credit as described below.

The amendment, therefore, incorporated the State Department “340 procedure” into the Kramico contract. The State Department approved WOC as a “340 supplier” in May 1984.

Section 340 of the State Department FM-2 Handbook “prescribes the procedure under which the U.S. Government undertakes on behalf of government-engaged construction contractors to pay directly to suppliers of building materials and equipment procured in countries other than that in which the project is located.” The State Department will use the 340 procedure “upon a determination that significant benefits may be expected to accrue to the U.S. Government.” Subparagraph 341.2 of the FM Handbook states that the 340 procedure “parallels commercial letter of credit principles, with posts performing the function of correspondent banks.” To this extent, sub-paragraph 341.3 of the Handbook provides:

In paying a supplier, a fiscal servicing post is acting as a fiscal agent for the construction contractor, performing the same function as a correspondent bank in commercial letter of credit operations. The payment, being for the account of the contractor, is liquidated against the construction contract obligation.

Under the “340 procedure,” Kramico was required to negotiate the terms of the purchase order or the equivalent, with WOC. Kramico submitted the subcontractor invoice to the State Department for approval. The State Department then sent WOC a letter guaranteeing the subcontractor pay[756]*756ment for the work.2 In all, the State Department sent six guarantee letters to WOC for the following amounts:

September 25, 1984 $292,853.30

May 81, 1984 $618,923.35

June 12, 1984 $233,681.15

June 25, 1984 $618,647.76

July 9, 1984 $ 32,604.04

August 28, 1984 $149,001.06

On January 13,1985, defendant terminated Kramico for default. The termination notice stated:

Kramico shall immediately discontinue all work on the Project, and shall cause to be discontinued all performance by your subcontractors and suppliers, except such performance as is described below. You should continue to process existing orders for construction materials. The Government mil honor the letters issued under the terms of Amendment No. 1 of the contract guaranteeing direct payments by the Embassy in Cairo to particular subcontractors, and these contractors should be so informed. [Emphasis added.]

Plaintiff prepared a “Claim for Retain-age/Contract Proceeds” on June 22, 1989. In the claim, plaintiff contended that WOC supplied the Embassy project a total of $1,945,710.66 worth of materials of which Kramico retained $112,758.62. Plaintiff asserted that defendant had a duty to “negate Kramico’s ability to withdraw retain-age from the amount paid WOC under the ‘340 Procedure.’ ” Plaintiff, therefore, requested the contracting officer (CO) to render a final decision for WOC in the amount of $112,758.62, plus interest. Plaintiff sent the claim certified mail to the State Department CO on June 23, 1989. The claim was received by Mr. Dickerson, a State Department mailroom employee, on June 28,1989. The CO never received the WOC claim and, therefore, never rendered a final decision on the claim.

Plaintiff instituted suit in this court on September 29, 1989, seeking $112,758.62 in damages for the alleged contract retainage. Defendant filed a motion to dismiss, contending that plaintiff lacked privity of contract with the government and, therefore, lacked standing under the CDA and the Tucker Act, 28 U.S.C. § 1491, to bring suit in this court. Alternatively, defendant maintained that plaintiff failed to submit a claim to the CO in accordance with § 605 of the CDA.3 Plaintiff countered that the “340 procedure” created an express contract or an implied-in-fact contract between WOC and the government over which this court may exercise jurisdiction. In addition, plaintiff avers that it submitted a proper claim to the CO. Plaintiff also filed a motion for summary judgment, alleging entitlement to the contract retainage as a matter of law. Plaintiff asserts that the government committed a breach of contract and violated its duty of good faith and fair dealing with WOC in failing to ensure that WOC received full payment for “340 supplies” delivered under the contract. Defendant filed a cross-motion for summary judgment, contending that WOC did not sustain its claimed damages.

Jurisdiction

I.

It is well established that a subcontractor not in privity with the government cannot advance a claim directly in this court. United States v. Johnson Controls,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Metrotop Plaza Associates v. United States
82 Fed. Cl. 598 (Federal Claims, 2008)
United Partition Systems, Inc. v. United States
12 A.L.R. Fed. 2d 867 (Federal Claims, 2004)
Sparks v. United States
41 Cont. Cas. Fed. 76,988 (Federal Claims, 1996)
Facilities Systems Engineering Corp. v. United States
38 Cont. Cas. Fed. 76,315 (Court of Claims, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
37 Cont. Cas. Fed. 76,165, 23 Cl. Ct. 754, 1991 U.S. Claims LEXIS 404, 1991 WL 165460, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wallace-oconnor-international-ltd-v-united-states-cc-1991.