Walker v. J.E. Merit Constructors, Inc.

707 F. Supp. 254, 1988 U.S. Dist. LEXIS 15563, 50 Empl. Prac. Dec. (CCH) 39,031, 48 Fair Empl. Prac. Cas. (BNA) 415, 1988 WL 149302
CourtDistrict Court, S.D. Mississippi
DecidedMarch 10, 1988
DocketCiv. A. No. S87-0296(R)
StatusPublished
Cited by4 cases

This text of 707 F. Supp. 254 (Walker v. J.E. Merit Constructors, Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walker v. J.E. Merit Constructors, Inc., 707 F. Supp. 254, 1988 U.S. Dist. LEXIS 15563, 50 Empl. Prac. Dec. (CCH) 39,031, 48 Fair Empl. Prac. Cas. (BNA) 415, 1988 WL 149302 (S.D. Miss. 1988).

Opinion

MEMORANDUM OPINION

DAN M. RUSSELL, Jr., District Judge.

This cause is before this Court on Motion of the defendant, J.E. Merit Constructors, Inc. (hereinafter referred to as “J.E. Merit”), for Summary Judgment on the claims brought against it by the plaintiff Sidney L. Walker (hereinafter referred to as “Walker”), pursuant to Rule 56 of the Federal Rules of Civil Procedure. The Motion for Summary Judgment was filed by the [256]*256defendant on December 24, 1987. Pursuant to the Uniform Local Rules for the United States District Courts for the Southern District of Mississippi, specifically Rule 8(d), the plaintiff Walker had ten (10) days in which to respond. As of the date of this opinion, the ten-day period, as computed by Rule 6 of the Federal Rules of Civil Procedure, has run and the plaintiff has not responded.

A careful review of the pleadings, exhibits, submitted affidavits, and memorandum of law moves this Court to find the following Uncontroverted Findings of Facts and Conclusions of Law.

UNCONTROVERTED FINDINGS OF FACTS

The plaintiff was first employed by J.E. Merit as a pipefitter from December 29, 1980, to August 14, 1981, during the original construction phase of the Borg-Warner Chemicals project in Port Bienville, Mississippi. Construction work at this site was sporadic, and personnel requirements fluctuated on a daily basis depending upon the progress of the construction and the skills required at each particular stage. Specific crafts were employed only until the portion of the project they were working on was completed, and then they were laid off. Although the plaintiff was eventually laid off when the work requiring his craft was completed, he raised no allegations of racial discrimination during this period.

The period from which the plaintiffs claims do arise begins on September 16, 1985, when the plaintiff was again hired by J.E. Merit as a pipefitter for the expansion phase of the Borg-Warner project. Walker was then promoted on February 24, 1986, to foreman in the piping department. This was his first supervisory position.

In July of 1986, Walker expressed interest in a general foreman position in the piping department, after which two general foreman positions became available. Both of these positions were filled by minorities. The first piping foreman position was filled by Ronnie D. Eppinett, an American Indian, on August 26, 1986. Eppinett was a former general foreman who had been laid off on July 10, 1986, due to a reduction in force. The second position was filled by Lecter J. Cuevas, Jr., an Hispanic, on September 8, 1986. Cuevas had supervisory experience before his employment with J.E. Merit and had performed well as a piping foreman with J.E. Merit since April 28, 1986.

On August 22,1986, Walker filed Charge No. 131-86-1750 with the Equal Employment Opportunity Commission (hereinafter referred to as the “EEOC”). This charge alleged a discriminatory failure to promote.1

On September 2, 1986, the plaintiff was reprimanded for safety violations committed by employees under his supervision for his failure to assist his crew in the proper assembly of a fire monitoring station, which resulted in the breaking of this equipment. The plaintiff was notified that a reoccurrence of this safety violation could result in his termination.

On September 3, 1986, J.E. Merit received notice of the plaintiffs first EEOC charge, No. 131-86-1750, regarding the alleged discriminatory failure to promote. On September 12, 1986, Walker filed another EEOC charge, No. 131-86-1877, alleging a retaliatory reprimand.2

In the period of time between August 1 and October 13, 1986, major cutbacks in personnel took place at the project, resulting in the reclassification and layoff of several foremen. Six piping foremen were reclassified and two piping foremen were laid off. Of the eight piping foremen, six were white. Walker was reclassified from piping foreman to pipefitter on October 6, 1986.

On that same day, Walker filed an amendment to EEOC Charge No. 131-86-1877 regarding an alleged retaliatory demotion.3

[257]*257In late October, 1986, further cutbacks in personnel were necessary. On October 23, 1986, Walker was laid off from his position as a pipefitter. During the same time period, five white employees, in addition to Walker, were also laid off.

On October 28, 1986, Walker filed the present lawsuit. He also filed on December 2, 1986, EEOC Charge No. 131-87-0300, which alleges a retaliatory layoff.4

CONCLUSIONS OF LAW

The plaintiff has alleged that this Court has jurisdiction of the instant case since the issues raised are brought pursuant to Title VII of the Civil Rights Act of 1964, 42 U.S.C. Section 2000e et seq., and pursuant to 42 U.S.C. Section 1981 and 42 U.S.C. Section 1983. The Court is of the opinion that for the reasons set forth below this Court has no basis for jurisdiction of this action pursuant to § 1983. Further, the Court finds that no genuine issue of material fact exists regarding plaintiffs Title VII and § 1983 claim and that the instant action is ripe for summary judgment.

Summary judgment is appropriate only if “the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Fed.R.Civ.P. 56(c). Once the movant shows the Court that it is entitled to summary judgment as a matter of law, the burden shifts to the resisting party to show why summary judgment is not proper. Nicholas Acoustics and Specialty Co. v. H & M Construction Co., 695 F.2d 839, 844 (5th Cir.1983). The non-movant is then obligated to present competent evidence setting forth specific facts to illustrate the existence of a genuine issue of material fact for trial. Id. The resisting party may not create a genuine dispute simply by alleging that a dispute exists. Id. “When a motion for summary judgment is made and supported as provided in this rule, an adverse party may not rest upon the mere allegations or denials of the adverse party’s pleading, but the adverse party’s response, by affidavits or as otherwise provided in this rule, must set forth specific facts showing that there is a genuine issue for trial. If the adverse party does not so respond, summary judgment, if appropriate, shall be entered against the adverse party.” Fed.R.Civ.P.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bass v. City of Jackson
878 F. Supp. 2d 701 (S.D. Mississippi, 2011)
Cothren v. Baxter Healthcare Corp.
798 F. Supp. 2d 779 (S.D. Mississippi, 2011)
Lee v. National Railroad Passenger Corp.
791 F. Supp. 2d 550 (S.D. Mississippi, 2011)
Johnson v. Burnett
826 F. Supp. 2d 979 (S.D. Mississippi, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
707 F. Supp. 254, 1988 U.S. Dist. LEXIS 15563, 50 Empl. Prac. Dec. (CCH) 39,031, 48 Fair Empl. Prac. Cas. (BNA) 415, 1988 WL 149302, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walker-v-je-merit-constructors-inc-mssd-1988.