WALBRIDGE ALDINGER CO. v. City of Detroit

495 F. Supp. 2d 642, 2007 U.S. Dist. LEXIS 52720, 2007 WL 2083780
District Court, E.D. Michigan·Decided July 5, 2007·No. Civil 07-11736·Published·Cited by 1 cases

Opinion

OPINION AND ORDER GRANTING MOTION FOR SUMMARY JUDGMENT

FEIKENS, District Judge.

Plaintiffs, Walbridge Aldinger Company, Midwest Building Supplies, Inc. and Joseph Shelton (Plaintiffs) sued for injunc-tive relief after falling short in the bidding process to build Oakwood CSO Control Facility and Pump Station Project, Contract No. PC 755. 1 Defendant, City of Detroit, moves for summary judgment, alleging that Plaintiffs do not have standing to bring this matter before this Court and, alternatively, Plaintiffs would fail on the merits. As I agree that there is no standing to bring this claim, I GRANT summary judgment to the Defendant. 2

I. FACTUAL BACKGROUND

In January 2007, Defendant solicited competitive sealed bids for contracts to build the Oakwood CSO Control Facility and Pump Station Project. The bids were subject to Detroit’s purchasing ordinance, *643 1984 Detroit Code § 18-501 et seq., which states that the bid would be awarded to the lowest responsible bidder, and that Defendant reserved the right “to waive any nonconformance.” (Def.Br., Ex. 1.) (emphasis added) The bid solicitation documents also included the following:

• a copy of Mayor Kwame Kilpatrick’s Executive Order No.2003^4, which stated Detroit’s policy of promoting Detroit-Based Businesses (DBB) and Detroit-Headquartered Businesses (DHB) by establishing a goal of 30% DBB and DHB participation in Detroit projects;
• a statement that “[i]n accordance with Executive Order No.2003-4 ... this contract [had] a goal of 30% of the total contract dollar amount to be subcontracted to ... [either] Detroit-Based Businesses [or] Detroit-Headquartered Businesses; and
• a requirement that bidders include with their bids completed DBB Subcontractor Forms, showing the identity of each DBB or DHB with whom the bidder intended to contract, its scope of work, the agreed subcontract price, and the signature of both the bidder and the identified subcontractors.”

(CompLUf 13, 14.) The process therefore required bidders who were either a DBB or a DHB to either commit themselves to performing the work or to subcontract 30% of the work to specifically identified subcontractors.

A completed DBB Subcontractor Data Form must accompany the bid of each Contractor who is bidding on a DBB contract. Bids that do not include a completed DBB Subcontractor Form shall be deemed non-responsive and shall be disqualified. 3

(Compl. Ex. A at 6.)

Only two bids were received on PC-755: one submitted by L. D’Agostini & Sons, Inc/Lakeshore Engineering, Inc. Joint Venture (D’Agostini) in the amount of $154,507,025; the other by the Wal-bridge/Oakwood Joint Venture (Wal-bridge) in the amount of $159,931,000. After application of a 2% equalization credit for a Detroit-based joint venture from Table II of the Detroit Code § 18-5-2, the Walbridge JV equalized bid totaled $156,732,380. (Deft Br. Ex. 3.)

The bids were opened on or about March 29, 2007. D’Agostini was deemed the lower bid, both in terms of the actual bids proposed and after Detroit officials added a 2% equalization credit only to the Walbridge bid because D’Agostini’s bid failed to provide a copy of the joint venture agreement. (Id.) D’Agostini also failed to complete its DBB Subcontractor Data Forms which would have revealed how it planned to meet the City’s 30% DBB work goals. The flaws were deemed minor, and D’Agostini’s bid was chosen.

Walbridge complained to Detroit in a letter dated March 30, 2007 that D’Agosti-ni’s bid should have been rejected as non-responsive, or alternatively, that D’Agosti-ni should not be given an equalization credit for being a DBB or DHB. (Compl.Ex.D.) In a letter dated April 5, 2007, Detroit’s purchasing director informed Walbridge that the D’Agostini bid was responsive and that the non-conform-ances in the bid were minor and would be waived by Detroit. (Compl.Ex.E.) Wal-bridge then submitted its bid protest on *644 April 9, 2007, raising the same issues it argued in its March 30th bid inquiry letter. (Compl.Ex.F.) In an April 13, 2007 response, Detroit explained, as relevant, that:

(1) The lack of a complete DBB Subcontractor Data Form is a minor defect that is waivable without causing prejudice to Walbridge because all bidders including Walbridge were allowed to shop their bids among subcontractors.
(2) Generally a substantial deviation is one that affects the price, the quantity, or quality of the goods or services being supplied. Further a substantial deviation is one that affects price and gives one bidder an advantage not allowed to others. Pascoe v. Barlum, 247 Mich. 343, 225 N.W. 506 (1929).
(3) The missing information did not affect price or the amount of the bid, and was a matter of form and not substance.
(4) Walbridge was given a 2% joint venture equalization credit for being a DBB or DHB joint venture.

(Deft Br. Ex. 4.)

Detroit then required D’Agostini to “demonstrate responsibility” by providing 11 items, including a complete list of subcontractors, and the manufacturer or supplier of 154 items that were referenced in D’Agostini’s bid proposal. (Deft Br. Ex. 5.) On April 19th, Plaintiffs filed a two count complaint for preliminary and permanent injunctive relief. At the May 1 st hearing on a motion for a preliminary injunction, this Court denied relief because it did not appear that any of the non-con-formances that were waived by Detroit affected the bid price or D’Agostini’s ability to fulfill its contract. This Court now addresses Defendant’s motion for summary judgment.

II. ANALYSIS

A. Standard of Review

Free access — add to your briefcase to read the full text and ask questions with AI

WALBRIDGE ALDINGER CO. v. City of Detroit, 495 F. Supp. 2d 642, 2007 U.S. Dist. LEXIS 52720, 2007 WL 2083780 (E.D. Mich. 2007).

495 F. Supp. 2d 642 (WALBRIDGE ALDINGER CO. v. City of Detroit) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Walbridge Aldinger Co. v. City of Detroit
296 F. App'x 527 (Sixth Circuit, 2008)