Waickowski v. Perry

1994 Mass. App. Div. 40
CourtMassachusetts District Court, Appellate Division
DecidedMarch 11, 1994
StatusPublished

This text of 1994 Mass. App. Div. 40 (Waickowski v. Perry) is published on Counsel Stack Legal Research, covering Massachusetts District Court, Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Waickowski v. Perry, 1994 Mass. App. Div. 40 (Mass. Ct. App. 1994).

Opinion

Welsh, J.

This is a civil action in which purchasers of a townhouse on Nantucket seek relief by way of money damages against a former trustee of a realty trust which had conveyed the property to a predecessor in title of the plaintiff.

The gist of the action is that the contractor who had been retained to install the septic system in 1974 or 1975 (described in the report as an “independent contractor”), improperly installed all or a portion of the septic system on an adjoining parcel of land, the present owners of which had demanded and obtained the removal of the encroaching septic system, causing the plaintiffs to incur substantial expense in the reconstructing and relocation of the septic system.

The plaintiffs advance several theories in support of their claims for relief.2 The first is that the defendant fraudulently concealed a material fact, i.e. the mislocation of the septic system which serviced plaintiffs’ unit. The second is in negligence in the planning, supervision or installation of the system. Thirdly, breach of contract. Fourth, a violation of G.L.c. 93A

The answer denied the material allegations of the complaint and asserted that no contract or business relationship ever existed between the plaintiffs and the defendant, and that no representations of any sort were ever made to the plaintiffs by the defendant, or that any legal duty ever existed, the breach of which might afford relief by way of damages. Further answering, the defendant asserts that the statute of limitations and especially, the Statute of Repose for claims arising out of the construction of improvements to real estate, bar the instant action.

The judge in the trial court allowed defendant’s motion for summary judgment and dismissed the complaint. We conclude that appellant failed diligently to prosecute the appeal and order that the report be dismissed.

The undisputed facts as evidenced by the material submitted by the parties to the motion judge agreeable to Rule 56 of Mass. R. Civ. P. are as follows:

In January of 1984, plaintiffs (who are husband and wife) purchased a townhouse at 573 Cambridge Street, Nantucket. The townhouse and its appurtenant septic system were constructed in 1974 or 1975 by a private contractor who is not party to this action. The land on which the townhouse was built was then owned by Madaket Realty Trust, of which the defendant was a trustee. The townhouse was conveyed by Madaket Realty Trust in May of 1975 to the plaintiffs’ predecessor in tide. There was a mesne conveyance of the property. The grantee in turn conveyed [41]*41to the plaintiffs. In answers to interrogatories, plaintiffs admit that they never had any contract or any business relationship with the defendant at any time. The defendant has had no legal, beneficial or other interest in the property the plaintiffs purchased since he conveyed the same as trustee of Madaket to the predecessors in title of the plaintiff in May of 1975.

The plaintiffs assert they first became aware that the septic system which serviced their unit was built on land other than their own on May 14,1990. At the time of construction of the townhouse and the appurtenant septic system, the land on which the septic was constructed was owned by Tristam’s Landing, Inc. The lot was conveyed by Tristam’s Landing, Inc. to the defendant in 1978.

The defendant deeded the property to Madaket Realty, Inc., a different entity from Madaket Realty Trust, in 1981. Madaket Realty, Inc. conveyed the land to Oakland Realty Trust in 1989. The trustee of Oakland demanded the removal of the septic system by the plaintiffs and their neighbors. The removal and installation of the new system took place in May, 1991. The instant action was commenced on May 16,1991.

A motion to dismiss appeal was filed by the defendant-appellee. The docket shows that judgment entered dismissing the complaint on December 11, 1992. The appellant timely flied a request for report and draft report on December 21, 1992. On February 3,1993, the judge conducted a hearing on the draft report and directed the appellant to submit a revised draft report with certain changes. On March 1, 1993, a revised draft report was filed, to which the defendant-appellee also took exception. That draft report languished with no action by the appellant. On September 30,1993, a further hearing was held by the court. This hearing was initiated by appellee’s counsel to move matters to a conclusion. The judge directed a further revision of the draft report. On October 22,1993, the judge allowed the third draft report. On November 5, 1993, appellant’s motion for an extension of time to file brief was allowed. Briefs were filed and the clerk forwarded the papers required by Rule 64(f), Dist./Mun. Cts. R. Civ. R to the appellate division.

Rule 64(g), Dist./Mun. Cts. R. Civ P. provides that if a party whose request for report has been allowed or established fails to prosecute the same promptly by preparing the necessary papers or otherwise, the appellate division may order the cause to proceed as though no such claim had been made. Double costs may be imposed as a further sanction. We perceive no abuse of discretion on the part of the motion judge in allowing additional time for filing of briefs after allowance of the report. Cf. Stenberg v. Frost, 45 Mass. App. Dec. 193, 196.

Rule 64(c) (5), Dist./Mun. Cts. R. Civ. P. provides that if final action by the trial judge upon a draft report is not taken within three months after the filing thereof, the cause shall proceed as though no report had been requested. The required course of action would be for the party seeking to appeal either to make a motion in the appellate division for cause shown to obtain an extension of the three months or to file a petition to establish report within the three months to prevent a forfeiture of the right to appeal. MARC PERLIN AND JOHN M. CONNORS, HANDBOOK OF CIVIL PROCEDURE IN THE MASSACHUSETTS DISTRICT COURT (Second Edition, 1990) §12.16 n. 69. In this case the motion judge did allow a revised report after the expiration of over nine months after judgment.

In Brown v. Quinn, 406 Mass. 641 (1990), the Supreme Judicial Court concurred with the determination made by the Appeals Court that failure by the clerk’s office to send notice to the parties fourteen days before the elapse of three months following the filing of a draft report did not absolve the appellant’s failure to preserve his rights by either filing for an extension in the Appellate Division or filing a petition to establish his draft report. Id. at 643. In the Brown case, the trial judge allowed a draft report some nine months after it was filed. In the instant case, the initial draft report was filed on December 21,1992. In Brown, the appellant’s argument that dismissal was unduly harsh was rejected by the court. The court held [42]*42that appellant’s failure to preserve his rights by filing a petition to establish his draft report or to take some other action such as a timely motion to extend the time was a serious misstep warranting dismissal of the appeal. Id. at 643-644. The court observed that it is the obligation of the litigants and not that of the court to monitor the progress of their cases. The plaintiff-appellant’s initial revised draft report was filed on March 1, 1993. There was no activity on the docket until the hearing on September 30,1993, which resulted in yet another revision of the draft report which was finally allowed on October 22,1993.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conley v. Gibson
355 U.S. 41 (Supreme Court, 1957)
Lantner v. Carson
373 N.E.2d 973 (Massachusetts Supreme Judicial Court, 1978)
Tindol v. Boston Housing Authority
487 N.E.2d 488 (Massachusetts Supreme Judicial Court, 1986)
White v. Peabody Construction Co., Inc.
434 N.E.2d 1015 (Massachusetts Supreme Judicial Court, 1982)
Rae v. Air-Speed, Inc.
435 N.E.2d 628 (Massachusetts Supreme Judicial Court, 1982)
Brown v. Quinn
550 N.E.2d 134 (Massachusetts Supreme Judicial Court, 1990)
Klein v. Catalano
437 N.E.2d 514 (Massachusetts Supreme Judicial Court, 1982)
Glickman v. Brown
486 N.E.2d 737 (Massachusetts Appeals Court, 1985)
Arthur D. Little, Inc. v. East Cambridge Savings Bank
625 N.E.2d 1383 (Massachusetts Appeals Court, 1994)
Stenberg v. Frost
45 Mass. App. Dec. 193 (Mass. Dist. Ct., App. Div., 1970)

Cite This Page — Counsel Stack

Bluebook (online)
1994 Mass. App. Div. 40, Counsel Stack Legal Research, https://law.counselstack.com/opinion/waickowski-v-perry-massdistctapp-1994.