Wagner v. CSX Transportation, Inc.

CourtDistrict Court, W.D. New York
DecidedJanuary 4, 2023
Docket1:20-cv-01314
StatusUnknown

This text of Wagner v. CSX Transportation, Inc. (Wagner v. CSX Transportation, Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wagner v. CSX Transportation, Inc., (W.D.N.Y. 2023).

Opinion

UNITED STATES DISTRICT COURT WESTERN DISTRICT OF NEW YORK

DOUGLAS WAGNER,

Plaintiff, 20-CV-1314-LJV-MJR v. DECISION & ORDER

CSX TRANSPORTATION, INC.,

Defendant.

On September 16, 2020, the plaintiff, Douglas Wagner, commenced this action under the Federal Employers’ Liability Act, 45 U.S.C. § 51 et seq. (“FELA”). Docket Item 1. Wagner was employed by the defendant, CSX Transportation, Inc. (“CSXT”), at the time of the incident at issue here. Id. He alleges that he suffered injuries caused by CSXT’s negligence when he climbed a ladder propped up against a utility pole and the pole fell. Id. On November 23, 2020, CSXT answered the complaint. Docket Item 8. On December 3, 2020, the case was referred to United States Magistrate Judge Michael J. Roemer under 28 U.S.C. § 636(b)(1)(A). Docket Item 9. After the parties engaged in extensive discovery,1 on May 31, 2022, CSXT moved for summary judgment. Docket Item 29. On August 1, 2022, Wagner responded, Docket Item 32; on September 1,

1 See Docket Item 29-8 at 3 (“The parties have completed written discovery, including the exchange of [i]nterrogatories and document production. In addition to the plaintiff’s sworn deposition testimony, nine depositions of CSXT witnesses have been completed.”). 2022, CSXT replied, Docket Item 37; and on December 21, 2022, this Court head oral argument, see Docket Item 40. For the following reasons, CSXT’s motion for summary judgment is denied.

BACKGROUND2 When utility poles are in use, they are connected by cables that run from one

pole to the next. See Docket Item 29-3 at 18-19. But when the poles are “retired,” the cables are taken down and the poles are removed from the ground. See Docket Item 29-2 at 91; Docket Item 29-3 at 23. Sometime before February 5, 2019, the 7Z11 Signal Team (the “Signal Team”)— one of CSXT’s railroad signal construction teams—removed the cables from the utility poles of the Niagara subdivision in Niagara Falls, New York. Docket Item 29-7 at ¶¶ 2, 20; Docket Item 32-13 at ¶¶ 2, 20.3 To remove the cables, the Signal Team cut the bolts that held the cables in place and “let the cable[s] drop and slap” on the ground. Docket Item 29-3 at 19. According to Chuck McLaughlin, the Signal Team’s foreman, Docket Item 29-7 at ¶ 4; Docket Item 32-13 at ¶ 4, allowing the cables to fall tested the

poles’ stability because the falling cable “would rock the poles back and forth, and if

2 On a motion for summary judgment, the court construes the facts in the light most favorable to the non-moving party. See Collazo v. Pagano, 656 F.3d 131, 134 (2d Cir. 2011). The following facts are taken from CSXT’s statement of undisputed facts, Docket Item 29-7; Wagner’s statement of undisputed facts, Docket Item 32-13; and the exhibits incorporated in the parties’ filings. They are viewed in the light most favorable to Wagner. 3 Wagner was not then a member of the Signal Team and did not participate in that work. Docket Item 29-2 at 157; Docket Item 32-13 at ¶ 20. there was a problem or issue with anything, it would have showed up then,” Docket Item 29-3 at 19-20. Foreman McLaughlin explained that in addition, “once you take the cables off, there’s nothing else to support [the poles],” so poles that remain standing after their

cables are removed should be stable. Id. at 20. Signal Team members also visually inspected the poles, Docket Item 29-4 at 12, and “hand rock[ed]” them by “hammering out the bolts that were in them,” Docket Item 29-3 at 20-21. McLaughlin thought that testing the poles using these methods “was the safest way to go.” Id. at 20. On February 5, 2019, the Signal Team returned to the Niagara subdivision to remove the poles from the ground. Docket Item 29-7 at ¶¶ 1-2; Docket Item 32-13 at ¶¶ 1-2. On that day, the Signal Team had five members: Wagner; McLaughlin; Gary Holland, the boom truck and crane operator; Travis Osantoski, the backhoe operator; and Matt Schall, who assisted Holland by maneuvering the boom. Docket Item 29-7 at ¶¶ 3-10; Docket Item 32-13 at ¶¶ 3-10. Wagner’s “job duties involved placing a sling

around each pole,” which was then attached to the boom and used to lift the pole out of the ground. Docket Item 29-7 at ¶ 10; Docket Item 32-13 at ¶ 10. Wagner “carr[ied] a 20-foot extension ladder from pole-to-pole[, ]lean[ed] it against each pole,” climbed the ladder with the sling over his shoulder, and then attached the sling to the pole. Docket Item 29-7 at ¶¶ 12-14; Docket Item 32-13 at ¶¶ 12-14.4

4 Although none of the Signal Team members had removed utility poles in their work for CSXT before February 5, 2019, Docket Item 32-13 at ¶ 9 (citing Schaal’s, Holland’s, and Osantoski’s depositions), Wagner had prior experience using slings to perform other tasks, Docket Item 29-2 (“[I]n signal construction we use slings all of the time . . . for just about everything.”); Docket Item 29-7 at ¶ 11; Docket Item 32-13 at ¶ 11. Wagner placed slings on five or six poles without any problem. Docket Item 29-2 at 127-28. And when he first placed the ladder against the next pole and began to climb it, the ladder and the pole seemed stable. Id. at 136. But once Wagner was at the height where he “was about to put th[e] sling on,” the pole “started to sway” and he

“knew it was coming down.” Id. at 137. As the pole fell forward, Wagner “jumped off” the ladder backward, landed on his feet, and then fell to the ground. Id. at 137-39.5 He “felt like the air got knocked out of [him],” id. at 141, but “[e]ventually” stood back up, continued working, and placed slings on several more poles even though he was “hurting,” id. at 147-48. None of the Signal Team members could say for certain why the pole fell. See Docket Item 29-3 (McLaughlin’s deposition); Docket Item 29-4 (Holland’s deposition); Docket Item 29-5 (Osantoski’s deposition); Docket Item 29-6 (Schaal’s deposition). The end of the pole that had been in the ground appeared “notched,” Docket Item 29-3 at 49-50 (also noting that the pole “didn’t look right”), “tapered,” id.; Docket Item 29-4 at

19-20; Docket Item 29-5 at 9-10, or “chiseled,” Docket Item 29-6 at 11, but the Signal Team members were not able to explain why or how the end of the pole became like that. Docket Item 29-3 at 50 (McLaughlin’s confirmation that he did not know “how [the pole] got like that”); Docket Item 29-4 at 20 (Holland’s confirmation of the same); Docket Item 29-5 at 9-10 (Osantoski’s confirmation of the same); Docket Item 29-6 at 11 (Schaal’s confirmation of the same).

5 The height from which Wagner jumped is unclear. Compare Docket Item 29-2 at 136 (Wagner’s estimate that he was standing on “at least the eighth” rung of the ladder when the pole fell), with Docket Item 29-3 at 57 (McLaughlin’s statement that when he asked Wagner how high he was on the ladder when the pole fell, Wagner pointed to the “third run[g] up”). Wagner hypothesized, however, that the pole “probably broke a long time ago” and was replaced in the ground without being fixed. Docket Item 29-2 at 162-65. He suggested that after the base of the pole broke, someone “stuck [the broken] pole on top of” the piece of the pole that remained in the ground, “put a piece of rubber down

there to hold it together[,] and filled it in with stone.” Id. Wagner based this theory on what he and the other Signal Team members saw and discussed when they looked at the pole after Wagner fell, id. at 164-66 (confirming that the Signal Team members “all observed and talked about that as the reason why the pole fell”), and on a photograph of the pole, id. at 162-63.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lyman v. CSX Transportation, Inc.
364 F. App'x 699 (Second Circuit, 2010)
Poller v. Columbia Broadcasting System, Inc.
368 U.S. 464 (Supreme Court, 1962)
Gallick v. Baltimore & Ohio Railroad
372 U.S. 108 (Supreme Court, 1963)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Atchison, Topeka & Santa Fe Railway v. Buell
480 U.S. 557 (Supreme Court, 1987)
Thomas Plagianos v. American Airlines, Inc.
912 F.2d 57 (Second Circuit, 1990)
James Sinclair v. Long Island Railroad
985 F.2d 74 (Second Circuit, 1993)
Collazo v. Pagano
656 F.3d 131 (Second Circuit, 2011)
Higgins v. Consolidated Rail Corp.
451 F. App'x 25 (Second Circuit, 2011)
Philip A. Syverson v. Consolidated Rail Corporation
19 F.3d 824 (Second Circuit, 1994)
Van Gorder v. Grand Trunk Western RR, Inc.
509 F.3d 265 (Sixth Circuit, 2007)
Paul v. Genesee & Wyoming Industries, Inc.
93 F. Supp. 2d 310 (W.D. New York, 2000)
Brandon v. City of New York
705 F. Supp. 2d 261 (S.D. New York, 2010)
Piroscafo v. Metro North Commuter Railroad Co.
552 F. App'x 6 (Second Circuit, 2013)
Coale v. Metro-North Commuter Railroad
621 F. App'x 13 (Second Circuit, 2015)
Soto v. Gaudett
862 F.3d 148 (Second Circuit, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Wagner v. CSX Transportation, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/wagner-v-csx-transportation-inc-nywd-2023.