Wadin v. Czuczka

146 P. 491, 16 Ariz. 371, 1915 Ariz. LEXIS 149
CourtArizona Supreme Court
DecidedFebruary 13, 1915
DocketCivil No. 1403
StatusPublished
Cited by14 cases

This text of 146 P. 491 (Wadin v. Czuczka) is published on Counsel Stack Legal Research, covering Arizona Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wadin v. Czuczka, 146 P. 491, 16 Ariz. 371, 1915 Ariz. LEXIS 149 (Ark. 1915).

Opinion

FRANKLIN, J.

The plaintiff in the court below, and the appellee here, being the owner of a lot in the town of Yuma, caused an architect to prepare plans and specifications for a dwelling-house to be erected thereon. The appellant, who was. defendant below, is engaged at Yuma in the business commonly designated as building contractor.

The plaintiff submitted the plans and specifications to defendant for the purpose of receiving a tender or offer on the part of the defendant as to the price for which he would agree to furnish all the labor and material and construct the house according to the plans and specifications submitted. After retaining the plans and specifications for a period of about two weeks, the defendant made an offer to build the house and furnish the labor and materials therefor, according to the [373]*373plans and specifications, for the sum of $2,715. After some bargaining as to the cost of the house, the plaintiff finally accepted the offer and directed the defendant to go ahead and build it. The defendant said:

‘ ‘ Czuczka, in case there should be a possible chance that I can make it a little cheaper, I will give you the benefit of it. ’ ’

The defendant thereupon began the construction of the house and the furnishing of the labor and material therefor, and completed the same according to the plans and specifications. He also furnished some extras; that is to say, additional work and material over and above the amount of work and material required by the plans and specifications. No point is made concerning the extras, for the jury, in the award to the plaintiff, deducted therefrom the reasonable value of the same.

The action is grounded on an alleged breach of the contract. In abridgment, the complaint states: That plaintiff and defendant, in the month of November, 1912, at Yuma, Arizona, entered into a verbal contract whereby the defendant agreed to construct, and to furnish all labor and materials for the erection of, a dwelling-house for the plaintiff according to certain plans and specifications submitted to defendant. That said dwelling-house was to be erected on certain lots of land owned by plaintiff in the town of Yuma, and for the fixed and agreed price of $2,715. Full performance of the agreement on the part of plaintiff is alleged, and the failure of the defendant to construct and complete the house within the contract price. That plaintiff was obliged to pay for labor and materials used in the construction of said house the sum of $552.13 in excess of the contract price therefor, for which amount judgment is asked.

Defendant answered by way of general demurrer and gen- • eral denial, also interposing with a counterclaim and cross-complaint ; the counterclaim and cross-complaint being pleaded by reason of a difference between the parties arising over their differing claims as to what was the contract in dispute. It was the claim of defendant: That the contract was a different one from that alleged by plaintiff. That by the agreement between them the defendant was merely employed to superintend the construction of the building and to use his best skill and knowledge in purchasing material and furnishing [374]*374labor therefor, and generally direct the construction, so as to keep the cost of the building to plaintiff down to the minimum, and that for such services he was to receive a reasonable compensation. That the minimum cost of the building was $3,345. Plaintiff answered the counterclaim and cross-complaint.

The demurrer was overruled, and the issues arising on the complaint and cross-complaint were submitted to the jury under instructions from the court. The jury awarded plaintiff the sum of $450, upon which verdict judgment was entered.

The appeal is from the judgment and an order overruling a motion for a new trial, and also from an order denying defendant’s exceptions to plaintiff’s statement of costs. The terms of the contract in question were not reduced to writing, and were in dispute. They were left to oral proofs to determine what the parties said and did, and what they intended should be understood thereby. It therefore became a question of fact for the jury.

In McKenzie v. Sykes, 47 Mich. 294, 11 N. W. 164, the court said:

“It is for the court to interpret the written contracts of parties, for when they have assented to definite terms and stipulations and incorporated them in formal documents, the meaning of these, it is supposed, can always be discovered on inspection. Nothing which is within the purview of the contract is left in doubt; and there is, of course, nothing to submit to the jury. . . . But, where the terms of a negotiation are left to oral proofs, the question what the parties said and did, and what they intended should be understood thereby, is single, and cannot be separated, so as to refer one part to the jury and another part to the judge; but in its entirety the question is one of fact.”

So in the ease of Gannon v. Brady Brass Co., 82 N. J. L. 411, Ann. Cas. 1913C, 1308, 81 Atl. 727:

“The cases holding that, where no attempt has been made to reduce the terms of a contract to formal language, the intention of the parties, as gathered from what they said and did, is a question of fact for the jury, are very numerous. ’ ’

For numerous cases applying the rule, see note to the last case cited, to be found in Ann. Cas. 1913C, at page 1310.

[375]*375We lay aside the assignments of error involving the insufficiency of the evidence to sustain the verdict. It is sufficient to say that there was a sharp conflict in the evidence introduced on both sides of the question. It was therefore within the province of the jury to weigh the testimony and give credit where they believed credit should be given. It is sufficient that the verdict is supported by substantial evidence.

The chief contention is that the complaint fails to state a cause of action for the reason that the contract pleaded shows a lack of mutuality and consideration, and also a failure to assign any breach thereof.

The requirements of a complaint for damages based upon a breach of contract are very simple. No particular phraseology is imperative. The absence of words usually employed in such actions is not fatal. In a word, the dry formalism of a common-law pleading may be discarded with safety. A concise statement of the facts constituting the plaintiff’s cause of action is the measure by which to determine the sufficiency, with an injunction placed upon the court by the law to disregard any error or defect in the pleading which shall not affect the substantial rights of the parties.

Every reasonable intendment will be made to sustain the pleading, and, if a cause of action may be reasonably inferred from its averments, a general demurrer should be overruled. Looking at the complaint with a friendly eye, and with the intention of sustaining it, if possible to do so, as against an attack by general demurrer, does it allege facts sufficient to constitute a cause of action? In a ease of this character it is only necessary to state the making of the contract, the obligation thereby assumed, and the breach, superadding a statement of the amount claimed and a prayer for judgment. If such facts appear by direct averment, or by a necessary and unavoidable inference from the facts stated, it should be upheld. We think it necessarily and unavoidably follows, from the facts stated in this complaint: That an agreement was entered into by the parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lathrop v. Arizona Board of Chiropractic Examiners
894 P.2d 715 (Court of Appeals of Arizona, 1995)
Healey v. Coury
783 P.2d 795 (Court of Appeals of Arizona, 1989)
Builders Finance Co. v. Holmes
359 P.2d 751 (Arizona Supreme Court, 1961)
Spellman Lumber Co. v. Hall Lumber Co.
241 P.2d 196 (Arizona Supreme Court, 1952)
State Ex Rel. Campbell v. Case
47 P.2d 24 (Washington Supreme Court, 1935)
Ajax v. Gregory
32 P.2d 560 (Washington Supreme Court, 1934)
Wallace v. First National Bank
7 P.2d 586 (Arizona Supreme Court, 1932)
Phillips v. Yuma Trust & Holding Co.
291 P. 997 (Arizona Supreme Court, 1930)
Rodriquez v. Childress
272 P. 921 (Arizona Supreme Court, 1928)
Pleasant v. Arizona Storage & Distributing Co.
267 P. 794 (Arizona Supreme Court, 1928)
Merchants & Stock Growers Bank v. Marley
264 P. 471 (Arizona Supreme Court, 1928)
Tucson National Bank v. Gomez
234 P. 560 (Arizona Supreme Court, 1925)
Valentine v. Shepherd
168 P. 643 (Arizona Supreme Court, 1917)
State v. Bowen & Co.
149 P. 330 (Washington Supreme Court, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
146 P. 491, 16 Ariz. 371, 1915 Ariz. LEXIS 149, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wadin-v-czuczka-ariz-1915.