Pleasant v. Arizona Storage & Distributing Co.

267 P. 794, 34 Ariz. 68, 1928 Ariz. LEXIS 128
CourtArizona Supreme Court
DecidedMay 21, 1928
DocketCivil No. 2694.
StatusPublished
Cited by23 cases

This text of 267 P. 794 (Pleasant v. Arizona Storage & Distributing Co.) is published on Counsel Stack Legal Research, covering Arizona Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pleasant v. Arizona Storage & Distributing Co., 267 P. 794, 34 Ariz. 68, 1928 Ariz. LEXIS 128 (Ark. 1928).

Opinion

LOCKWOOD, J.

Carl Pleasant, one of the defendants herein, entered into a contract to construct a certain storage dam on the Agua Fria River about twenty miles north of Marinette, the railroad station nearest to the dam site. In the construction of this dam and the works appurtenant thereto it was necessary to haul large quantities of cement, steel, and other supplies to the proposed dam site. J. H. Jenkins, the other defendant, had contracted originally with Pleasant to do the hauling, but for some reason it was deemed advisable to have the actual work done by someone else, and Arizona Storage & Distributing Company, a corporation, plaintiff herein, entered into a contract with Jenkins and Pleasant to do it. The contract was in writing, and executed by the parties thereto on the nineteenth day of April, 1926. On the following day, April 20th, plaintiff began hauling material and supplies to the dam site, and continued so doing until September 11th, on which date it ceased to haul. Defendants demanded that plaintiff con *72 tinue the work and complete its contract, and notified it that, if it did not do so, they would he compelled to relet the unperformed portion of the contract, which they finally did, and thereafter plaintiff brought this suit.

It is founded upon three causes of action. In the first, plaintiff first alleges the execution of the written contract, which is set up in full, and which, so far as its language is material in this case, reads as follows:

“It is understood and agreed that the contractor will be responsible for and pay all railroad demur-rage claims, if any, which may arise under this contract. It is understood and agreed that the road joining the Marinette-New River county highway and the Pleasant Lake dam site shall be widened and reconstructed as per drawing G-38, entitled ‘Alignment Prog Tanks Auto Road.’
“It is understood and agreed that the owner will grade sufficient length along the Marinette team track so that any and all materials can be unloaded in the event arrangements cannot be made with the railroad for handling heavy equipment or machinery from the industry spur now serving the Marinette cotton gin.' The owner will maintain embankment from engineer’s station 4 to station 8, drawing G-38.
“Article II.
“Time of Completion.
“The work to be performed under this contract shall be commenced within ten (10) days and shall be completed by January 1, 1928. ...”
“Article 5. Contractor’s Understanding. It is understood and agreed that the contractor has, by careful examination, satisfied himself as to the nature and location of the work, the conformation of the ground, the character, quality, and quantity of the materials to be encountered, the character of - equipment and facilities needed preliminary to and during the prosecution of the work, the general and local conditions, and all other matters which can in any way affect the work under this contract. No verbal agreement or conversation with any officer, agent, or employee' of the owner, either before or after the execution of *73 this contract, shall affect or modify any of the terms or obligations herein contained. ...”
“Article 9. The Owner’s Right to Do Work. If the contractor should neglect to prosecute the work properly or fail to perform any provision of this contract, the owner, after three days’ written notice to the contractor, may,-without prejudice to any other remedy he may have, make good such deficiencies and may deduct the cost thereof from the payment then or thereafter due the contractor.”

Plaintiff then alleged as follows:

“Plaintiff alleges that at the time of the entering into of said contract, to wit, on the 19th day of April, 1926, it was verbally agreed by and between plaintiff and said defendants that said contract should not go into effect until the defendants should do and perform or cause to be done and performed certain work, namely, the construction and improvement of the road mentioned and referred to in article I of said contract, and that, pending the time when said defendants should do or cause to be done said work, plaintiff should furnish the tools, labor, and equipment and prosecute the work described in said contract, and that defendants should pay plaintiff therefor at what is termed the day rate; that is to say, the prices which plaintiff ordinarily and usually charged and received for doing similar work. Plaintiff further alleges that it proceeded to furnish said tools, labor, and equipment and to perform said work under said verbal agreement from said 19th day of April, 1926, until the 25th day of July, 1926.”

It was further alleged that there was still due under the verbal contract the sum of $22,199.45.

The second cause of action set up the written contract and alleged work thereunder from July 25 to September 11, 1926, a failure by defendants to pay the contract price for such work, a refusal by plaintiff on account of such failure to continue with the contract after September 11th, and an allegation that the reasonable value of the work done between July 25th and September 11th was $7,718.41.

*74 The third cause of.action need not be considered, as it was admitted on oral argument that the judgment thereon was correct.

Defendants demurred to each cause of action separately, which demurrers were by the court overruled. Answering, defendants admitted the • execution of the written contract, and alleged that all work done by plaintiff and for which it was seeking to recover under the first and second causes of action was done under the written contract, denied that they had failed to make the payments provided for in such contract, and alleged that plaintiff had, without excuse, ceased to perform the contract on September 11th. They admitted that there was due plaintiff on the contract the sum of $11,972.81. They then set up six set-offs and counterclaims. The first was for work performed for plaintiff, in the sum of $2,945.87; the second, for board furnished to plaintiff’s employees in the sum of $1,804.50; the third, for the rental value of certain machinery in the sum of $4,380; the fourth, for demurrage paid in the sum of $1,328; the fifth, for $3,690.98, the amount defendants claimed they had been compelled to pay in excess of the contract price to have certain hauling done during the month of July, which should have been done by plaintiff, at the-request of the latter that defendants do it; and the sixth, for damages defendants allege was caused them by reason of plaintiff’s abandoning the contract on the 11th of September, through the necessity of paying an increased price for all hauling done thereafter, over the amount for which plaintiff had contracted to do it. All these counterclaims were denied by plaintiff.

Upon the issues thus framed, the case was tried before a jury and a verdict returned in favor of plaintiff on the first cause of action in the sum of $14,-057.45; on the second cause of action in the sum of $6,891.83; on the third cause of action in the sum of *75

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Villas at Hidden Lakes Condominiums Ass'n v. Geupel Construction Co.
847 P.2d 117 (Court of Appeals of Arizona, 1993)
Milberger v. Chaney Building Co.
704 P.2d 822 (Court of Appeals of Arizona, 1985)
Coronado Co. v. Jacome's Department Store, Inc.
629 P.2d 553 (Court of Appeals of Arizona, 1981)
Wippman v. Rowe
540 P.2d 141 (Court of Appeals of Arizona, 1975)
United Gas Pipe Line Co. v. Tyler Gas Service Co.
162 F. Supp. 496 (E.D. Texas, 1958)
Owens v. Conelly
272 P.2d 345 (Arizona Supreme Court, 1954)
Young v. Border Broadcasting Co.
255 P.2d 888 (Arizona Supreme Court, 1953)
Spitalny v. Tanner Const. Co.
254 P.2d 440 (Arizona Supreme Court, 1953)
Tucson Federal Savings & Loan Ass'n v. Aetna Investment Corp.
245 P.2d 423 (Arizona Supreme Court, 1952)
Robberson Steel Co. v. Harrell
177 F.2d 12 (Tenth Circuit, 1949)
Fadex Foreign Trading Corp. v. Crown Steel Corp.
272 A.D.2d 273 (Appellate Division of the Supreme Court of New York, 1947)
Denman v. Hall
191 S.W.2d 74 (Court of Appeals of Texas, 1945)
Sistrom v. Anderson
124 P.2d 372 (California Court of Appeal, 1942)
Lee v. Standard Cement Pipe Company
103 P.2d 457 (Arizona Supreme Court, 1940)
Merryman v. Sears
72 P.2d 943 (Arizona Supreme Court, 1937)
Perry v. Farmer
54 P.2d 999 (Arizona Supreme Court, 1936)
Ernst v. Morgan
36 P.2d 566 (Arizona Supreme Court, 1934)
Lockett v. Drake
31 P.2d 499 (Arizona Supreme Court, 1934)
Brogoitti v. Walter
30 P.2d 835 (Arizona Supreme Court, 1934)
Dover Copper Mining Co. v. Doenges
12 P.2d 288 (Arizona Supreme Court, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
267 P. 794, 34 Ariz. 68, 1928 Ariz. LEXIS 128, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pleasant-v-arizona-storage-distributing-co-ariz-1928.