W. Wayne Tiffany v. Forbes Custom Boats, Incorporated

959 F.2d 232
CourtCourt of Appeals for the Fourth Circuit
DecidedApril 27, 1992
Docket91-3001
StatusUnpublished
Cited by3 cases

This text of 959 F.2d 232 (W. Wayne Tiffany v. Forbes Custom Boats, Incorporated) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W. Wayne Tiffany v. Forbes Custom Boats, Incorporated, 959 F.2d 232 (4th Cir. 1992).

Opinion

959 F.2d 232

NOTICE: Fourth Circuit I.O.P. 36.6 states that citation of unpublished dispositions is disfavored except for establishing res judicata, estoppel, or the law of the case and requires service of copies of cited unpublished dispositions of the Fourth Circuit.
W. Wayne TIFFANY, Plaintiff-Appellee,
v.
FORBES CUSTOM BOATS, INCORPORATED, Defendant-Appellant.

No. 91-3001.

United States Court of Appeals,
Fourth Circuit.

Submitted: April 8, 1991
Decided: April 6, 1992
Amended by order filed April 27, 1992

Appeal from the United States District Court for the Eastern District of North Carolina, at Raleigh. Terrence W. Boyle, District Judge. (CA-90-43-2-CIV-BO)

John G. Trimpi, Trimpi & Nash, Elizabeth City, N.C., for appellant.

Edward A. O'Neal, Twiford, O'neal & Vincent, Elizabeth City, N.C., for appellee.

E.D.N.C.

Before RUSSELL and PHILLIPS, Circuit Judges, and CHAPMAN, Senior Circuit Judge.

OPINION

PER CURIAM:

This is a suit which was initially instituted in the state court and removed to the district court on diversity grounds.1 It involves the purchase by the plaintiff of a 53-foot fishing vessel to be constructed by the defendant conforming generally to the plans and specifications of an earlier fishing vessel constructed by the defendant. The vessel's construction has been completed and the defendant is prepared to deliver it to the plaintiff upon the payment of the balance due it by the plaintiff. The plaintiff denied he owed the defendant anything; in fact, he asserted charges in its favor against the defendant by way of an offset and counterclaim. The plaintiff seeks what he denominates a declaratory judgment action for an accounting between the parties, a restraining order against the sale of the vessel by the defendant and, finally, for preliminary affirmative injunctive relief compelling the defendant to deliver immediately the completed vessel with all necessary documentation, warranties, and manuals to him. The plaintiff tendered to the defendant his check for the balance claimed by the defendant to be remaining due on the vessel, subject to a subsequent accounting between the parties. When the plaintiff refused to make an unconditional payment of the balance due, the defendant notified the plaintiff it expected to sell the vessel as permitted under the written contract between the parties. The plaintiff responded by filing this suit. The state court entered an ex parte restraining order against a sale of the vessel by the defendant. When the action was removed, this restraining order was continued by the district court. The plaintiff moved in the district court for a preliminary injunction continuing the restraint on the sale of the vessel by the defendant and for an affirmative mandatory injunction requiring the defendant to turn over the vessel with all necessary documentation to the plaintiff pending the disposition of the dispute between the parties over the amount due the defendant. The district court granted the preliminary injunctive relief sought by the plaintiff. The defendant on appeal challenges that order. We affirm in part, reverse in part, and remand to the district court for further proceedings consistent with the rulings herein.

I.

The defendant, a North Carolina corporation, is a custom boat builder with its boatyard located at Manteo, North Carolina. The plaintiff is a lawyer living in Norfolk, Virginia. On November 16, 1989, the two parties, after some negotiations and following the preparation of a number of drafts, entered into a written contract by which the defendant agreed to construct and sell to the plaintiff a 53-foot fishing vessel. The plans and specifications for the vessel's construction were to be prepared by the defendant and were to "be similar to and based on the design of FANTASTIC, a boat recently constructed by the BUILDER." The base price, as shown on Schedule A, attached to and made a part of the contract, was $246,963.05. The prices of "amenities" to be installed on the vessel, as"based upon Schedule B," were tentatively to be determined by "the costs of equipment as provided on the vessel 'FANTASTIC' and [were to] be adjusted accordingly as costs may vary at the time of the purchase." The contract prohibited any changes in the plans and specifications not agreed to by the parties and, provided that if the changes that might be agreed on resulted in "deletions or reduction" there were to be "reasonable downward charges in the contract price [as] ... agreed by the parties" or, if the changes represented agreed additions, the plaintiff was to be "billed at actual costs of materials plus all labor time spent at the rate of $15.00 per hour (currently $15.00 per hour but subject to increase as the cost of labor increases and only after written notice to BUYER)." Payments were to be made by the plaintiff to the defendant as the work progressed. The amounts of the progress payments were to be determined by materials and labor expended by BUILDER within the 30-day period subsequent to the date of last progress payment. Request for progress payments were to be made no later than the 10th of each month with each request itemizing materials and labor. Payments are to be due and payable to BUILDER within two days after receipt by the BUYER. These payments were subject to an agreement that no more than 90% of the purchase price were to be due from plaintiff prior to launching of the vessel and acceptance by plaintiff. "Upon acceptance [of the vessel] by the BUYER the remaining balance of the purchase price shall be paid to BUILDER." The "Default" section of the contract provided that, should the defendant default, "the BUYER shall have such rights and remedies as are provided for by law but in no event shall be entitled to specific performance or a money judgment greater than the amounts the BUYER has actually paid to the BUILDER."

After the execution of the contract, the defendant proceeded with the construction of the vessel. During that time it periodically presented progress payments, properly itemized, to the plaintiff who paid the same with the exception of the last payment due with the completion of the boat. On October 17, 1990, the defendant had notified the plaintiff that it was "ready to allow delivery of the MY BOY IV2 but you have refused to pay the remaining balance of $28,891.67," and that, in the event payment is not made within 5 days it advised it would exercise its right under the contract to sell the vessel "as Owner." In response to this notice, the plaintiff filed his action "for Declaratory Judgment, Temporary Restraining Order and Injunction."

In his complaint, the plaintiff alleged that a dispute had arisen between the parties over the terms of the contract, over plaintiff's claim of defects in the workmanship and over the plaintiff's claim of overpayment. In connection with the last claim, the plaintiff states that the "total cost" to him of the vessel was fixed under the contract at the absolute over-all amount of $394,162.58 but that he had made cash payments of $431,026.59, showing an overpayment by him of $36,864.01.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
959 F.2d 232, Counsel Stack Legal Research, https://law.counselstack.com/opinion/w-wayne-tiffany-v-forbes-custom-boats-incorporated-ca4-1992.