Vrabel v. Williams, Unpublished Decision (12-6-2001)

CourtOhio Court of Appeals
DecidedDecember 6, 2001
DocketNo. 79495.
StatusUnpublished

This text of Vrabel v. Williams, Unpublished Decision (12-6-2001) (Vrabel v. Williams, Unpublished Decision (12-6-2001)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vrabel v. Williams, Unpublished Decision (12-6-2001), (Ohio Ct. App. 2001).

Opinion

JOURNAL ENTRY AND OPINION
William Vrabel appeals from a net $10,843.26 judgment of the common pleas court entered in favor of Colleen Williams in connection with work he performed for her pursuant to a home remodeling construction contract. At the trial court level, a magistrate awarded Vrabel $3,250.00 on his breach of contract claim and an additional $8,205.00 for services and materials he provided to Williams that were not part of the original contract. The magistrate then awarded Williams $22,298.26 on her counterclaim for credit, reductions, and the cost to repair Vrabel's allegedly incomplete and unworkmanlike performance, resulting in a net judgment in favor of Williams in the amount of $10,843.26.

On appeal, Vrabel challenges the manifest weight of the magistrate's decision, which the trial court adopted, urging that the court should have awarded him $20,784.00 for the extra services and materials he provided to Williams, and also arguing that the court erred in awarding Williams damages on her counterclaim because she did not give him an opportunity to remedy any defects in the construction project. Vrabel further challenges the qualifications of Williams' expert witness. After carefully considering these arguments and reviewing the facts of this case, we reject Vrabel's assignments of error and affirm the judgment of the trial court.

On March 3, 1998, Williams received architectural plans for an addition to her home, located at 343 Arudel Road, in Rocky River. She hired Vrabel, who owns and operates Vrabel Construction Company, a home construction business, to construct this addition. On March 22, 1998, Vrabel provided Williams with an estimate of $73,420.00 to complete the project.

On June 3, 1998, Williams signed a contract agreeing to pay Vrabel $86,250.00 for labor and materials in connection with the home addition. This contract, which Vrabel prepared, stated in part that, Any alteration or deviation from above specifications involving extra costs will be excuted [sic] only upon written orders * * *.

Vrabel told Williams that it would take him approximately three months to complete the project. On June 8, 1998, Vrabel and his employees began work on Williams' home.

On July 9, 1998, Vrabel withdrew $12,000 from an escrow account set up by Williams to pay for the project. On July 20, 1998, Vrabel withdrew another $54,000 from the account, and on September 10, 1998, Vrabel made a third withdrawal of $27,000, for a total of $93,000.

Williams confronted Vrabel for withdrawing more than the contract amount of $86,250. He informed her that there were extras beyond the terms of the contract, but agreed to return $10,000. As such, Williams paid Vrabel $83,000, which is $3,250 less than the contract amount.

Vrabel then continued to work on Williams' home sporadically through November of that year. During the course of this job, Williams requested several alterations to the original plans. Although no written change orders were executed for this work, Williams acknowledges that she had agreed to pay for certain extras, which totaled $8,205.00.

Williams complained to Vrabel on numerous occasions concerning his workmanship during the course of his performance. Many of these issues remained unresolved on December 1, 1998, the last day Vrabel and his crew performed any work at the Williams' home.

Vrabel claims that Williams prevented him from entering his home to complete the final punch list. Williams, on the other hand, claims that she gave Vrabel ample opportunity to complete the work, but that he failed to do so.

On December 2, 1998, Vrabel gave Williams an invoice in the amount of $20,784 for extras he claimed were not part of the original contract.

On December 11, 1998, Rocky River Building Inspector Enrico Bucci performed an inspection of the Williams' home. The home passed inspection, but Bucci found the repairs to be 95% complete.

On January 8, 1999, Vrabel filed a mechanic's lien against Williams in the amount of $26,134.00, and on June 23, 1999, Vrabel attempted to foreclose on this mechanic's lien. Williams filed an answer and counterclaimed for breach of contract, alleging that Vrabel failed to perform his services in a workmanlike manner. Williams subsequently filed an amended answer and an amended counterclaim averring that Vrabel violated the Ohio Consumer Sales Practices Act.

On January 25, 2000, after obtaining leave of court, Vrabel filed an amended complaint adding a claim for unjust enrichment. The court then referred this matter to a magistrate, who heard this matter on November 1, 2000.

On January 8, 2001, the magistrate found in favor of Vrabel in the amount of $3,250.00, the amount Williams still owed under the original contract, and an additional award of $8,205.00 for the extras Williams agreed to pay for; the magistrate next found in favor of Williams on Vrabel's claim for the other disputed extras; the magistrate found in favor of Williams in the amount of $22,298.26 for her breach of contract counterclaim; and the magistrate found in favor of Vrabel on Williams' claim under the Ohio Consumers Sales Practices Act. As such, the magistrate found that the evidence at trial supported a net judgment in favor of Williams and against Vrabel in the amount of $10,843.26.

The parties filed their respective objections to the magistrate's decision, but on March 13, 2001, the court adopted the magistrate's report and entered judgment in conformity with it.

Vrabel now appeals, raising two assignments of error for our review. The first one states:

I. THE TRIAL COURT COMMITTED SUBSTANTIAL ERROR IN ADOPTING THE MAGISTRATE'S DECISION THAT THE MECHANIC'S LIEN ON APPELLEE'S PROPERTY IS VOID AND UNENFORCEABLE.

Vrabel urges that the court should not have adopted the magistrate's decision because it only awarded him $8,205.00 for the services and materials he provided to Williams beyond the scope of the contract; he maintains that this amount failed to compensate him fully for the extras he provided, which he claims were worth over $20,000.00. Williams asserts that the court awarded the correct amount because Vrabel is only entitled to payment for the extras to which she requested and agreed to pay for; she further contends the court properly found many of the disputed extras were included in the original contract.

In effect, the issue presented here is whether the judgment of the trial court adopting the magistrate's decision in this regard is against the manifest weight of the evidence.

Our court set forth the following standard of review for manifest weight appeals at page 744 in Star Bank National Assn. v. Cirrocumulus Ltd. Partnership (1997), 121 Ohio App.3d 731:

* * * A judgment supported by some competent, credible evidence going to the essential elements of the case will not be reversed by a reviewing court as being against the manifest weight of the evidence. C.E. Morris Co. v. Foley Construction Co. (1978), 54 Ohio St.2d 279, 376 N.E.2d 578. Since the trial judge is best able to view the witnesses and observe their demeanor when he weighs the credibility of the offered testimony, there is a presumption that the findings of the trier of fact are correct. Seasons Coal Co. v. Cleveland (1984), 10 Ohio St.3d 77, 80, 461 N.E.2d 1273.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shore, Shirley Co. v. Kelley
531 N.E.2d 333 (Ohio Court of Appeals, 1988)
Star Bank National Ass'n v. Cirrocumulus Ltd. Partnership
700 N.E.2d 918 (Ohio Court of Appeals, 1997)
C. E. Morris Co. v. Foley Construction Co.
376 N.E.2d 578 (Ohio Supreme Court, 1978)
Central Realty Co. v. Clutter
406 N.E.2d 515 (Ohio Supreme Court, 1980)
State v. Williams
446 N.E.2d 444 (Ohio Supreme Court, 1983)
Seasons Coal Co. v. City of Cleveland
461 N.E.2d 1273 (Ohio Supreme Court, 1984)
State v. Awan
489 N.E.2d 277 (Ohio Supreme Court, 1986)
Kelly v. Medical Life Insurance
509 N.E.2d 411 (Ohio Supreme Court, 1987)
State v. Boston
545 N.E.2d 1220 (Ohio Supreme Court, 1989)
Shifrin v. Forest City Enterprises, Inc.
597 N.E.2d 499 (Ohio Supreme Court, 1992)
State v. D'Ambrosio
616 N.E.2d 909 (Ohio Supreme Court, 1993)
Graham v. Drydock Coal Co.
667 N.E.2d 949 (Ohio Supreme Court, 1996)
Goldfuss v. Davidson
679 N.E.2d 1099 (Ohio Supreme Court, 1997)
State v. Baston
709 N.E.2d 128 (Ohio Supreme Court, 1999)
State v. Hartman
754 N.E.2d 1150 (Ohio Supreme Court, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
Vrabel v. Williams, Unpublished Decision (12-6-2001), Counsel Stack Legal Research, https://law.counselstack.com/opinion/vrabel-v-williams-unpublished-decision-12-6-2001-ohioctapp-2001.