Voxtel, Inc.

CourtArmed Services Board of Contract Appeals
DecidedMarch 9, 2023
DocketASBCA No. 60129
StatusPublished

This text of Voxtel, Inc. (Voxtel, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Voxtel, Inc., (asbca 2023).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Voxtel, Inc. ) ASBCA No. 60129 ) Under Contract Nos. FA8750-05-C-0041 et al. )

APPEARANCES FOR THE APPELLANT: Eric Nackarud, Esq. Counsel

Marcus W. Eyth, Esq. Davis Wright Tremaine LLP Portland, OR

Kate H. Kennedy, Esq. Davis Wright Tremaine LLP Seattle, WA

APPEARANCE FOR THE GOVERNMENT: Samuel W. Morris, Esq. DCMA Chief Trial Attorney Defense Contract Management Agency Chantilly, VA

OPINION BY ADMINISTRATIVE JUDGE CATES-HARMAN

Appellant Voxtel, Inc. (Voxtel) appeals from a final decision of the Defense Contract Management Agency (DCMA or government) administrative contracting officer (ACO) unilaterally establishing final overhead rates. In that decision, the ACO found that Voxtel included unallowable costs related to independent research and development (IR&D), rent, executive compensation, and depreciation in its indirect cost rate proposals for fiscal years (FY) 2007-2009. We have jurisdiction pursuant to the Contract Disputes Act (CDA), 41 U.S.C. §§ 7101-7109. We sustain in part and deny in part the appeal.

FINDINGS OF FACT

Background

1. Voxtel is a small business that develops and manufactures advanced 3D imaging technologies (compl. ¶ 3). Voxtel’s primary customer since its inception in 1999 has been the U.S. government. For the years in question (FY 2007-2009), its work was almost exclusively federal contracts, including Small Business Innovative Research (SBIR) contracts. (Tr. 2/18-19) Voxtel is organized as a subchapter S corporation, and its sole owner is its president and chief executive officer, George Williams (tr. 2/12).

2. For purposes of this appeal, the relevant contracts include one contract awarded to Voxtel in 2005 by the United States Air Force Research Laboratory (No. FA8750-05-C-0041), another awarded in 2008 by the Office of Naval Research (No. N00014-08-C-0101), and a small business and innovation research (SBIR) contract with the Naval Surface Warfare Center, issued in 2006 (No. N00178-06-C3024) (R4, tabs 1-2, 5).

Contract Requirements

3. Each of the contracts incorporated by reference Federal Acquisition Regulation (FAR) 52.216-7, ALLOWABLE COST AND PAYMENT (DEC 2002), 1 which imposes obligations upon both the government and contractors (R4, tabs 1 at 16, 2 at 42, 5 at 83). 2 This clause requires the government to pay the contractor as work progresses in amounts determined to be allowable by the contracting officer and in accordance with the version of FAR subpart 31.2 in effect on the date of the contract. See FAR 52.216-7(a)(1). This includes “[p]roperly allocable and allowable indirect costs, as shown in the records maintained by the Contractor for purposes of obtaining reimbursement under Government contracts . . . .” FAR 52.216- 7(b)(1)(ii)(F).

4. FAR 52.216-7 also requires contractors to submit to the Defense Contract Audit Agency (DCAA) an adequate final indirect cost rate proposal (ICP) based upon the contractor’s actual cost experience for that particular fiscal year. Those ICPs are due within six months of the expiration of each fiscal year. See FAR 52.216- 7(d)(2)(i)-(ii).

5. Except for the SBIR contract, the relevant contracts incorporate by reference DFARS 252.215-7002, COST ESTIMATING SYSTEM REQUIREMENTS, which generally requires contractors to have an acceptable cost estimating system and disclose it to the government (R4, tab 1 at 18, 5 at 87).

1 One of the contracts renumbers this clause as 52.216-07 (R4, tab 1 at 16). 2 The parties numbered pages in their Rule 4 submissions with a prefix of letters and/or leading zeros. We have dropped the prefix and leading zeros and just cite the numeric page number.

2 Voxtel’s FY 2007-2009 ICPs

6. Voxtel failed to submit its ICPs for FY 2007-2009 within the required time frame set forth in FAR 52.216-7(d)(2)(i)-(ii). DCAA informed Voxtel in nine separate letters between 2008 and 2013 that its ICPs were overdue (R4, tab 14). It was revealed much later that Voxtel did submit its 2007 ICP to DCAA on August 31, 2011 (ex. 134 at 2).

7. In a memorandum dated December 16, 2014, DCAA advised DCMA that Voxtel had failed to provide its ICPs for 2007-2009, and that DCAA would therefore be unable to provide an audit opinion on proposed rates and costs. Instead, DCAA recommended that DCMA “unilaterally determine contract costs using a decrement factor [of] up to 16.2 percent applied to contract costs (direct and indirect)” for the subject years. (R4, tab 14 at 117) This decrement was to be applied to both active and already completed contracts, as well as for fiscal years in the future when the active contracts were completed (id.).

8. Meanwhile, at some point in 2014, Voxtel informed DCMA and DCAA that its 2007-2009 ICPs would be submitted in January 2015; Voxtel did in fact submit the ICPs on January 21, 2015 (R4, tabs 15-18; tr. 2/56-57).

9. Neither DCAA nor DCMA advised Voxtel that its ICPs would not be audited (tr. 2/58, 61). There is also no indication in the record that Voxtel knew that when the ICPs were submitted that DCAA had already recommended the 16.2% decrement.

10. After Voxtel submitted the 2007-2009 ICPs at DCMA’s request, DCAA auditor Nicole Hilliard performed both an “adequacy” and a “nomenclature” review (tr. 1/30-32).

11. An “adequacy review” is a checklist or set of steps that DCAA uses to verify that the contractor included all the required schedules in its ICP (tr. 1/31, 2/136). It is described in part on the standard DCAA form used for adequacy reviews in the following manner:

Adequacy reviews of contractor [ICPs] include verification for completeness and accuracy. The reviewer should verify the [ICP] includes the required schedules . . . . The reviewer should also perform a general review of the submission to verify math calculations in the schedules and perform a cross-check of amounts that are common to two or more of the schedules.

3 (Ex. 113 at 252; see also tr. 1/31)

12. A “nomenclature review involves “visually reviewing the accounts and amounts claimed in direct and indirect cost pools to try to identify any unallowable costs” (tr. 1/31). The DCAA Contract Audit Manual (January 2015) describes a nomenclature review in the following manner:

(1) Nomenclature Review. Using a copy of the contractor’s post-closing trial balance, which has been reconciled in accordance with the guidance in [§] 6-610, the auditor should select for thorough analysis those accounts which are new and/or significant in amount, vary from developed trends, or which on the basis of nomenclature review or past experience appear to be sensitive in nature and likely to contain questionable costs. However, categories of indirect expense should not be accepted or rejected solely on the basis of a nomenclature review. The actual content of accounts being evaluated must be established through testing of transactions.

(DCAA Contract Audit Manual § 6-608.2(c)(1) (2015)) (emphasis added)

13. On cross-examination, Ms. Hilliard conceded that even though she conducted only adequacy and nomenclature reviews, Voxtel’s ICPs for 2007-2009 were adequate for audit (tr. 1/63). DCMA ACO Laura Musgrave, who authored the final decision that is the subject of this appeal, testified that she and Ms. Wada decided to “go ahead and set rates” rather than request a full audit (tr. 1/121). In ACO Musgraves’ view, ordering an audit did not make good business sense given the delay it would have caused on the processing of already significantly delinquent ICPs (tr. 1/120).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Frank Lyon Co. v. United States
435 U.S. 561 (Supreme Court, 1978)
Joseph Radtke, S.C. v. United States
895 F.2d 1196 (Seventh Circuit, 1990)
United States v. James C. Dunkel
927 F.2d 955 (Seventh Circuit, 1991)
Hercules Incorporated v. United States
292 F.3d 1378 (Federal Circuit, 2002)
Barron Bancshares, Inc. v. United States
366 F.3d 1360 (Federal Circuit, 2004)
David E. Watson, P.C. v. United States
714 F. Supp. 2d 954 (S.D. Iowa, 2010)
Glaser v. Haskin
13 P.2d 1071 (Oregon Supreme Court, 1932)
David Nassif Associates v. United States
557 F.2d 249 (Court of Claims, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
Voxtel, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/voxtel-inc-asbca-2023.