Volunteer Electric Cooperative v. Tennessee Valley Authority

139 F. Supp. 22, 1954 U.S. Dist. LEXIS 2201
CourtDistrict Court, E.D. Tennessee
DecidedDecember 29, 1954
DocketCiv. 2161
StatusPublished
Cited by12 cases

This text of 139 F. Supp. 22 (Volunteer Electric Cooperative v. Tennessee Valley Authority) is published on Counsel Stack Legal Research, covering District Court, E.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Volunteer Electric Cooperative v. Tennessee Valley Authority, 139 F. Supp. 22, 1954 U.S. Dist. LEXIS 2201 (E.D. Tenn. 1954).

Opinion

DARR, Chief Judge.

On June 10, 1939 plaintiff and defendant entered into a contract which provides that plaintiff has participated in the acquisition of certain facilities of the Tennessee Power Company and that the purpose of the contract is to state the terms and conditions under which defendant shall sell electricity to the plaintiff. On March 29, 1949 sections two and three of the contract were amended to state in substance that defendant would supply plaintiff with all of its power requirements within certain limits. Section three as amended sets up the delivery points for power and the demand at each delivery point. Section two provides for the furnishing of additional power when applied for by plaintiff in writing, under certain conditions and restrictions. On April 15, 1952 the contract was further amended whereby plaintiff and defendant agreed to increases in the wholesale and retail prices of power resold for industrial purposes. The 1952 amendment contains the following recital: “Whereas, it is the desire of TVA and Distributor that they consult one another as early as feasible in the consideration of service to large new industrial loads in the area served by Distributor, and that standard ar-‘ rangements be available for normal application, so that only in unusual cases, where the loads are of disproportionate size, or involve unusual service conditions, or where direct service by TVA would make possible substantial economies through coordination of the TVA system with the customer’s facilities, would service by TVA, or by Distributor under special arrangements with TVA, be called for * * *” There have been other amendments, but they have no bearing upon the present dispute between the parties.

In 1944 certain tentative negotiations were held between representatives of defendant and Bowaters Southern Paper Corporation. Bowaters was interested in erecting a large plant somewhere in the Tennessee valley. Meetings on this question were resumed in January 1951. Defendant assisted Bowaters by furnishing it with information concerning the desirability of certain sites and also gave Bowaters preliminary assurances as to rates for power to be used by their plant if erected. In reliance upon defendant’s assurances that it would furnish power at certain rates together with other favorable conditions in the area, Bowaters decided to construct a plant in McMinn County, Tennessee. The plant site was located within the area in which plaintiff has power lines and sells power.

It seems that on March 27, 1952 a 'meeting was held between representatives of plaintiff and defendant concerning service problems within plaintiff’s area and that defendant brought up the Bowaters account suggesting that plaintiff supply the power needed by Bowaters during the construction of its plant. This *24 was agreed upon. The amount of power to be required by Bowaters during construction was not to exceed 1,000 kw and it appears that defendant suggested plaintiff supply this power since plaintiff’s system was adequate for the job. Such service was begun by plaintiff in 1952 and plaintiff was to continue to serve such construction power until Bowaters’ plant was completed.

On July 16, 1952 plaintiff wrote defendant requesting the establishment of a substation at the site of the Bowaters plant to supply a minimum of 17,000 kw of power (the firm power required by Bowaters) which plaintiff intended to distribute to Bowaters. Plaintiff also asked defendant to suspend further negotiations with Bowaters until plaintiff and defendant could agree concerning the service to Bowaters. On January 27, 1953 defendant answered plaintiff indicating defendant was studying the problem and would discuss their findings when they were completed. On April 1, 1953 defendant contracted with Bowaters to supply all of its power needs excluding the construction power being furnished by plaintiff. By letter dated April 20, 1953 defendant advised plaintiff that this contract had been negotiated. However, it appears from defendant’s affidavits that plaintiff had been advised as early as July 1952 that such a contract was to be negotiated and that on July 29, 1952 defendant wrote plaintiff advising that a proposed draft of such contract had been made.

Plaintiff alleges that it is prepared to furnish the facilities necessary to supply Bowaters with its power requirements, the plant being located within its service area, and that the action of defendant in contracting to furnish such power violates the contract existing between plaintiff and defendant, especially as interpreted by the conduct of the parties throughout the years.

Pursuant to Rule 56 of the Federal Rules of Civil Procedure, 28 U.S.C.A., defendant has filed an amended motion for summary judgment alleging there is no genuine issue as to any material fact and therefore defendant is entitled to judgment. Numerous detailed affidavits have been filed by defendant in support of its motion, together with written briefs. Plaintiff has also filed affidavits and brief in support of its position.

The first question which must be disposed of is whether this is a case which may properly be decided on motion for summary judgment. Rule 56(c) of the Federal Rules of Civil Procedure provides in part that summary judgment “shall be rendered forthwith if the pleadings, depositions, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” (Emphasis supplied.) The determination of the existence of a genuine issue of fact depends upon the entire record of the case being considered.

The Court is aware of the care which must be exercised in making such a determination. In such a case the Court is not authorized to try the issue of fact but rather must determine whether there is an issue to be tried. Toebelman v. Missouri-Kansas Pipe Line Co., 3 Cir., 130 F.2d 1016. The summary judgment procedure is not intended to be used as a substitute for trial of disputed questions of fact. It must be temperately and cautiously used lest abuse reap nullification. Avrick v. Rockmont Envelope Co., 10 Cir., 155 F.2d 568. The true intention of the summary judgment rule is to put an end to useless and expensive litigation if there is no genuine issue as to any material fact, even though an issue may be raised formally by the pleading. Battista v. Horton, Myers & Raymond, 76 U.S.App.D.C. 1, 128 F.2d 29. All of these considerations must be kept in mind in deciding the particular case lest the rights of either party be impinged.

In the present case the basic question is simply what the contract between the plaintiff and defendant means. The contract with pertinent amendments is before the Court having been filed by de *25 fendant in response to certain interrogatories put to it by the plaintiff.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
139 F. Supp. 22, 1954 U.S. Dist. LEXIS 2201, Counsel Stack Legal Research, https://law.counselstack.com/opinion/volunteer-electric-cooperative-v-tennessee-valley-authority-tned-1954.