VOLLERS EXCAVATING & CONSTRUCTION, INC. v. BORO DEVELOPERS, INC.

CourtDistrict Court, E.D. Pennsylvania
DecidedSeptember 30, 2022
Docket2:21-cv-00455
StatusUnknown

This text of VOLLERS EXCAVATING & CONSTRUCTION, INC. v. BORO DEVELOPERS, INC. (VOLLERS EXCAVATING & CONSTRUCTION, INC. v. BORO DEVELOPERS, INC.) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
VOLLERS EXCAVATING & CONSTRUCTION, INC. v. BORO DEVELOPERS, INC., (E.D. Pa. 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF PENNSYLVANIA

VOLLERS EXCAVATING &

CONSTRUCTION, INC.

Plaintiff, CIVIL ACTION NO. 21-455 v. BORO DEVELOPERS, INC., et al. Defendants.

MEMORANDUM OPINION RUFE, J. September 29, 2022 In this construction dispute, Plaintiff Vollers Excavating & Construction, Inc. sued Defendants, Boro Developers, Inc. and its surety, Liberty Mutual Insurance Company, seeking amounts allegedly owed for extra work, for delays caused by a differing site condition (contaminated soil), and on the contract balance. Boro was a prime contractor on a construction project for the Cheltenham Township School District; Vollers was a subcontractor. Boro has asserted a counterclaim against Vollers and filed a third-party complaint against the School District. Vollers has moved to dismiss Boro’s counterclaim and for sanctions, and the School District has moved to dismiss the third-party complaint. I. BACKGROUND The School District awarded Boro the general construction contract and the electrical construction contract for a project at Cedarbrook Middle School. Boro and Vollers entered into a subcontract for Vollers to provide site work such as site clearing, earthwork, trenching, backfilling and compaction, and soil erosion and sediment control. Vollers alleges that it performed extra work at Boro’s direction, and that it encountered contaminated soils which constituted a differing site condition beyond the scope of Vollers’s responsibility under the subcontract which prevented Vollers from completing its work according to the original schedule. Vollers alleges that Boro has been paid in full but owes Vollers $731,648.01, which includes a balance on the contract, the extra work, and the costs associated with the differing site conditions.

Vollers filed this suit asserting claims against Boro for breach of contract, unjust enrichment, and violation of the prompt payment provisions of the Commonwealth Procurement Code.1 Vollers also asserted a claim against Liberty for breach of its bond obligation. Boro filed a motion asserting that the School District was an indispensable party and seeking dismissal or an order requiring Vollers to join the School District. The Court denied the motion, holding that the School District was not an indispensable party to the dispute between Boro and Vollers, and that Boro could file a third-party claim against the School District if necessary to protect Boro’s interests.2 Boro then filed a counterclaim against Vollers and a third-party complaint against the School District. Also pending is an action in the Court of Common Pleas of Montgomery County, Pennsylvania, in which Boro sued the School District for damages resulting from project delays.3

II. MOTIONS TO DISMISS A. Legal Standards To survive a motion to dismiss under Federal Rule of Civil Procedure 12(b)(6), the Complaint “must contain sufficient factual matter . . . to state a claim . . . that is plausible on

1 62 Pa. Stat. §§ 3901, et seq. 2 Order of Sept. 8, 2021 [Doc. No. 10]. 3 Boro Developers v. Cheltenham Area Sch. Dist., No. 2020-02500 (Montgomery C.C.P. filed Feb. 11, 2020).] 2 its face.”4 “A claim has facial plausibility when the pleaded factual content allows the court to draw the reasonable inference that the defendant is liable for the misconduct alleged.”5 The Court must “accept all factual allegations as true, construe the complaint in the light most favorable to the plaintiff, and determine whether, under any reasonable reading of the complaint, the plaintiff may be entitled to relief.”6 Any attached exhibits “[are] a part of the

pleading for all purposes,” and will be considered by the Court.7 Federal Rule of Civil Procedure 12(b)(1) permits a party to move for dismissal of any claim over which the district court lacks subject matter jurisdiction.8 A motion to dismiss under Rule 12(b)(1) therefore challenges the power of a federal court to hear a claim or case.9 The plaintiff has “the burden of proof that jurisdiction does in fact exist.”10 “A Rule 12(b)(1) motion may be treated as either a facial or factual challenge to the court’s subject matter jurisdiction.”11 “In reviewing a facial attack, the court must only consider the allegations of the complaint and documents referenced therein and attached

4 Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (internal quotations omitted) (quoting Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570 (2007)). 5 Id. at 663 (citing Twombly, 550 U.S. at 556). 6 Fowler v. UPMC Shadyside, 578 F.3d 203, 210 (3d Cir. 2009) (quoting Phillips v. Cnty. of Allegheny, 515 F.3d 224, 233 (3d Cir. 2008)). 7 Fed. R. Civ. P. 10(c) (“A copy of a written instrument that is an exhibit to a pleading is a part of the pleading for all purposes”). 8 Fed. R. Civ. P. 12(b)(1). 9 Petruska v. Gannon Univ., 462 F.3d 294, 302 (3d Cir. 2006). 10 Id. at 302 n.3. 11 Gould Elecs. Inc. v. United States, 220 F.3d 169, 176 (3d Cir. 2000) (citation omitted). 3 thereto, in the light most favorable to the plaintiff.”12 “In reviewing a factual attack, the court may consider evidence outside the pleadings.”13 B. Vollers’ Motion To Dismiss Boro’s Counterclaim In its Counterclaim, Boro asserts that under the subcontract, Vollers is responsible for

costs and expenses associated with prosecuting a claim on Vollers’ behalf against the School District, and that Vollers must pay “all fees, costs, expenses, including attorneys’ fees, incurred by Boro in the prosecution of its claims against the School District for alleged compensation which Vollers seeks . . . .14 Vollers has moved to dismiss, arguing that Boro has not prosecuted any claim on behalf of Vollers with the School District.15 Article 17.1 of the Subcontract provides in relevant part: If during the course of completing this Subcontract work, a dispute or claim should arise due to the actions of the Owner, the Contractor, in its sole discretion may allow and direct the Subcontractor to submit such claims to the Contractor and after determined claim has merit submit their claim on behalf of the Subcontractor under the Contract Disputes Act or any state public works Contractor’s Contract Dispute procedures and laws. In any event, all costs and expenses, including attorneys’ fees and expert witness fees associated with prosecuting such claim shall be borne solely by Subcontractor and Subcontractor shall, prepare, submit and prosecute any such claims without loss, cost or expense to Contractor. Upon receipt of any funds from the Owner pertaining to the resolution of said claims, the Contractor agrees to forward [to] the Subcontractor all monies received, less only applicable mark-up due the Contractor and any amount required to otherwise compensate Contractor for the amounts due Contractor hereunder. The Subcontractor agrees to defend, indemnify and hold the Contractor harmless for all actions of the Owner that would initiate an action under any claim.16

12 Id. (citations omitted). 13 Id. (citation omitted). 14 Counterclaim ¶ 6. 15 Doc. No. 20. 16 Doc. No. 20 Ex. B.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cooter & Gell v. Hartmarx Corp.
496 U.S. 384 (Supreme Court, 1990)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
OR v. Gerri Hutner
515 F. App'x 85 (Third Circuit, 2013)
Phillips v. County of Allegheny
515 F.3d 224 (Third Circuit, 2008)
Fowler v. UPMC SHADYSIDE
578 F.3d 203 (Third Circuit, 2009)
LJL Transportation, Inc. v. Pilot Air Freight Corp.
962 A.2d 639 (Supreme Court of Pennsylvania, 2009)
TruServ Corp. v. Morgan's Tool & Supply Co.
39 A.3d 253 (Supreme Court of Pennsylvania, 2012)
Lauri Howe v. Robert Litwack
579 F. App'x 110 (Third Circuit, 2014)
Simmerman v. Corino
27 F.3d 58 (Third Circuit, 1994)
Wert v. ManorCare of Carlisle PA, LLC
124 A.3d 1248 (Supreme Court of Pennsylvania, 2015)
BP p.l.c. v. Mayor and City Council of Baltimore
593 U.S. 230 (Supreme Court, 2021)
Sprint Commc'ns, Inc. v. Jacobs
134 S. Ct. 584 (Supreme Court, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
VOLLERS EXCAVATING & CONSTRUCTION, INC. v. BORO DEVELOPERS, INC., Counsel Stack Legal Research, https://law.counselstack.com/opinion/vollers-excavating-construction-inc-v-boro-developers-inc-paed-2022.