VOF BouwCombinatie Egmond v. Oceanteam Power & Umbilical B.V.

644 F. Supp. 2d 411, 2009 U.S. Dist. LEXIS 69116, 2009 WL 2432693
CourtDistrict Court, S.D. New York
DecidedAugust 6, 2009
Docket09 Civ. 4023(SAS)
StatusPublished

This text of 644 F. Supp. 2d 411 (VOF BouwCombinatie Egmond v. Oceanteam Power & Umbilical B.V.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
VOF BouwCombinatie Egmond v. Oceanteam Power & Umbilical B.V., 644 F. Supp. 2d 411, 2009 U.S. Dist. LEXIS 69116, 2009 WL 2432693 (S.D.N.Y. 2009).

Opinion

OPINION AND ORDER

SHIRA A. SCHEINDLIN, District Judge.

I. INTRODUCTION

On April 22, 2009, VOF BouwCombinatie Egmond (“VOF” or “plaintiff’) commenced this action and requested an ex parte order directing attachment and garnishment (“Attachment Order”) of up to $16,980,500 of the assets of Oceanteam Power & Umbilical B.V. (“OPU”), Ocean-team B.V., and Oceanteam A.S.A (together with OPU and Oceanteam B.V., the “defendants”). On May 4, 2009, this Court issued an Attachment Order granting VOF’s request to attach the funds of defendants. The Attachment Order mandated use of the U.S. Marshal for service of process, allowed for continuous service of the garnishee banks only with the consent of individual banks, and permitted garnishee banks to impose a “reasonable” fee to compensate them for the costs of processing the Attachment Order and restraining funds.

Since the issuance of the Attachment Order, J.P. Morgan Chase & Co., J.P. Morgan Clearing Corp. (U.S.), and J.P. Morgan Chase Bank (U.K.) (“the JP Morgan Garnishees”) have instituted policies with respect to the Attachment Order, including the charging of a fee of $125 per day. VOF now requests that the Court *413 issue an order providing that (1) VOF is not required to pay any fee to the JP Morgan Garnishees; (2) that supplemental service may be made by any attorney, paralegal or other employee of Eaton & Van Winkle LLP; and (3) that service of the Attachment Orders on the JP Morgan Garnishees be deemed continuous from the time of service until 10:00 a.m. .on the next business day. For the reasons that follow, VOF’s request is denied.

II. BACKGROUND

A. Facts

On May 26, 2005, Noordzee Wind Investor I CV entered into an Engineering Procurement & Construction contract with VOF in which VOF agreed to develop the Offshore Windpark Egmond aan Zee, located off the Dutch coast, and which was to comprise “36 wind turbines with mono-pile foundations, associated subsea, substation and onshore cables connected to the electrical grid and a meteorological measurement mast (the “Project”).” 1 On or about March 9, 2006, VOF entered into a Cable Transportation, Handling and Installation subcontract with OPU, in which OPU agreed to “carry out cable loading, transportation, cable installation and sub-sea trenching/burial works in connection with the Project (the “Subcontract”).” 2 As part of its work under the Subcontract, OPU chartered the MTV Northern River. 3

VOF’s Complaint alleges that OPU breached the Subcontract by failing to keep the M/V Northern River under charter and delaying the performance of OPU’s work beyond the summer of 2006 and by failing to “bury the cables to the intended depths of 3 meters below sea bottom close to shore and 1.5 meters below sea bottom elsewhere.” 4 Although VOF demanded that OPU complete all work required by the Subcontract, OPU refused to do so and eventually abandoned its work on the Project. 5 VOF therefore alleges that it sustained damages equal to $12,980,500, which is the amount contractually agreed upon by the parties in the event of a breach by OPU. 6

The Subcontract provides additionally that all disputes between VOF and OPU be resolved by arbitration in The Netherlands in accordance with the law of The Netherlands. 7 Arbitration has commenced between the parties. 8 The total amount VOF seeks to attach pursuant to this Rule B action is $16,980,500, which comprises the principal sum of $12,980,500; $3,000,000 in interest, estimated at six percent for four years; and $1,000,000 of attorneys’ fees, disbursements, and arbitrator fees. 9

B. Procedural History

On May 4, 2009, this Court entered an Attachment Order allowing for the attachment of defendants’ funds up to *414 $16,980,500. 10 The Order directed that initial service be made by U.S. Marshal personally, and that any subsequent service of process be made personally, unless the garnishee consents to service of process by way of facsimile or other electronic means. 11 The Attachment Order also provided that garnishees may request a “reasonable fee” from plaintiff. 12 Finally, the Attachment Order provided that a garnishee may consent to deem service continuous for a period not to exceed sixty days from the date of the Order. 13

Initial service of the Attachment Order was completed by May 18, 2009. 14 On June 18, 2009, the JP Morgan Garnishees gave notice to VOF that, in accordance with the terms of the Attachment Order, it intended to impose a fee of $125 per day for garnishment services. 15 In addition, the JP Morgan Garnishees declined to consent to continuous service and further refused to accept supplemental service from anyone other than a U.S. Marshal. 16 VOF now requests relief from the Court.

III. LEGAL BACKGROUND AND STANDARD

A. Attaching After-Acquired Property

In Reibor International Limited v. Cargo Carriers (KACZ-CO.) Limited, the Second Circuit considered whether a maritime plaintiff may attach “after-acquired property” — i.e., property that was not in the hands of the garnishee at the time the attachment order was served. 17 In Reibor, plaintiff served an order of maritime attachment on a garnishee bank at about 10:25 a.m., but the bank did not receive the transferred funds until 2:21 p.m. that afternoon. 18 The bank attached the funds. The district court vacated the attachment, holding that a plaintiff may only attach funds that are in the hands of the garnishee at the time the attachment order is served. 19 The Second Circuit affirmed. Addressing the permissibility of attaching after-acquired property under Rule B, the court first noted that

The Admiralty Rules themselves offer little guidance. Rule B does not mention attachment of after-acquired property. Two other rules, Rule C and Rule E, appear to contemplate service on garnishees actually in possession of the property to be attached, but neither addresses the issue of after-acquired property directly. 20

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
644 F. Supp. 2d 411, 2009 U.S. Dist. LEXIS 69116, 2009 WL 2432693, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vof-bouwcombinatie-egmond-v-oceanteam-power-umbilical-bv-nysd-2009.