Virginia Bridge & Iron Co. v. Crafts

58 S.E. 322, 2 Ga. App. 126, 1907 Ga. App. LEXIS 294
CourtCourt of Appeals of Georgia
DecidedJune 19, 1907
Docket42
StatusPublished
Cited by16 cases

This text of 58 S.E. 322 (Virginia Bridge & Iron Co. v. Crafts) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Virginia Bridge & Iron Co. v. Crafts, 58 S.E. 322, 2 Ga. App. 126, 1907 Ga. App. LEXIS 294 (Ga. Ct. App. 1907).

Opinion

Russell, J.

The Virginia Bridge and Iron Company brought-its action against George IT. Crafts in the city court of Atlanta to-recover a balance of $2,850.66 alleged to be due on an account for structural material furnished to the defendant, who was a contractor and builder of bridges. Defendant admitted the correctness of the account, but pleaded a counter-claim, b)r way of set-off” (averring that the plaintiff had no office or place of business, or assets, in Georgia), that the plaintiff “is indebted” to defendant in the sum of $3)836 for failure to comply with certain agreements made between plaintiff and defendant as to sharing in the work of building certain bridges in the Vicksburg National Military Park, in the State of Mississippi, let out under competitive bids by the United States government.

The defendant, in his extended answer, avers that in 1903 and 1904 both plaintiff and defendant were in the business of taking' contracts to build both substructure and superstructure of bridges; that plaintiff, in addition to being a contractor, was also a manufacturer of structural steel superstructures; that defendant made a special feature of building substructures, such as excavations, concrete bases, brick piers and walls, etc., commonly called the-“substructure;” that this fact was known to plaintiff, who often let-out the substructure work of bridges let to it by entire contract; that in January, 1903, when the United States called for bids-looking to the construction of certain bridges in the Military Park, negotiations were entered into between plaintiff and defendant that-they should so arrange their bids as that defendant should put in the only bid, with the understanding and agreement that plaintiff should have the steel work, or superstructure, and defendant the-other work, or substructure, on whatever contracts might be awarded by the United States government to defendant; that the bid so made by defendant was partly for the use and benefit of plaintiff and at prices for the respective portions agreed on by the parties before the bid was submitted; that on February 12, 1903, the contract to build three bridges was awarded to defendant, and he at once placed an order with plaintiff for the steel work, in accordance with their agreement, but subsequently (February 16,, 1903) the government, through its officers, decided to reject all the bids and call for new ones, and specified that the estimate of” cost for building both substructure and superstructure should be-[129]*129made separately, in each bid, these second bids to be opened April 16, 1903, in Vicksburg.

It is further averred that on March 16, 1903, the president of the plaintiff company addressed a letter to defendant, sa}'ing, “If it is your desire to take the matter up along the lines we worked together before, . . we know of no special objection;” and asked what method of procedure defendant would advise; the meaning of said letter (defendant avers) being to arrange some plan by which plaintiff and defendant could co-operate in securing one or more of the dozen bridges to be let by the government, so that one could furnish the substructure and the other the superstructure. Defendant had extended negotiations with Vernon II. Smith, the representative of plaintiff, and submitted to Smith the figures and calculations which were the basis of the bids made by plaintiff at the second letting, and under which plaintiff, in his own name, finally obtained the contracts and erected three of the bridges let by the government. Defendant avers that on the night of April 15, 1903, before submitting bids next day, in Vicksburg, plaintiff and Smith met, had a long interview, examined plans, estimates, figures, and prints; that Smith made an agreement with defendant to take defendant’s estimates, submit a bid in plaintiff’s name, and that defendant should have the substructure work at the figures submitted, and plaintiff the superstructure of whatever contracts might be awarded to plaintiff. Defendant, being on the ground with all equipments and implements for work (having just finished some similar work), could do the work cheaper than other contractors, and this fact was a mutual inducement for plaintiff and defendant to work in concert ; and defendant then and there disclosed and turned over to the plaintiff’s said agent his estimates, prices, calculations of quotations, etc., to be used by plaintiff in preparing his bid. He says, further, that immediately on said contract being made with the Fnited States government by plaintiff to construct three bridges, known as Nos. 4, 5, and 8, in said park, defendant offered to perform his part of said contract, and demanded his right to do the substructure work at the price named for same in plaintiff’s ibid, all of which was denied and refused by plaintiff, who awarded the substructure to another contractor (Kubush) at a cheaper price, all to his injury and damage as aforesaid. To the defend[130]*130ant’s answer were attached tabulated statements showing how he would be entitled to damages, and for which he prays set-off, amounting to $3,85G, besides interest from October 1, 1903.

The jury found for the plaintiff $837.75, upon which judgment was entered. Plaintiff moved for new trial on the several grounds stated in the record. At the hearing of the motion the trial judge passed the following order: “Defendant having voluntarily written off the sum of $144.23 from the set-off found in his favor, leaving the amount due the plaintiff the sum of $981.98, the motion for new trial is hereby overruled and denied.”

In the voluminous record there is evidence for the defendant that the first letting, which was afterwards rejected by the government, took place as alleged; that afterwards, on the night of April 15, 1903, before the second letting next day, plaintiff’s agent, Vernon H. Smith, and the defendant met in the latter’s room at the hotel in Vicksburg to confer as to methods of submitting bids; that plaintiff’s agent said his principal was chiefly a manufacturer of steel structural work and did not care for foundation work, though it did not refuse it; that defendant had figures made out in detail on substructure, and Smith some detailed figures on superstructure; that Smith stated that he had compared certain figures he had from his company, on both substructure and superstructure work, with the plans of the engineer on substructure work, and did not consider them reliable; that, if defendant would show him his estimates on quantities and prices, he (Smith) would use those prices in bidding on the substructure, and, if he got any contract on any of the subwork of the bridges, he would turn the subwork over to the defendant. In bidding for the entire bridge Smith agreed to put his separate bid for the subwork 1 per cent, ■higher than the defendant’s bid, and the defendant was to put his price .for superstructure higher than the plaintiff’s. Both submitted bids. There was no agreement as to what should be done in the event defendant got the award for superstructure and substructure. If defendant got the award for superstructure, then he was to do it; and there was nothing said as to where he should get»the superstructure materials. “I was not presumed to get the superstructure work, as I was to bid above him.” Some time afterwards the defendant and Smith met in Atlanta, and for the first time the defendant learned that the plaintiff had given the [131]*131contract to Eubush. When pressed for an explanation, he said that the bid had named 4 months as the time for completion of the work, and that he had to make the contract in such a time as that the substructure work must be done in %y2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Allen v. Heys
51 S.E.2d 417 (Supreme Court of Georgia, 1949)
McLendon v. Johnson
31 S.E.2d 89 (Court of Appeals of Georgia, 1944)
Bayha v. Public Utility District No. 1
97 P.2d 614 (Washington Supreme Court, 1939)
Anderson v. Lynch
3 S.E.2d 85 (Supreme Court of Georgia, 1939)
Hartsfield Co. v. Shoaf
191 S.E. 693 (Supreme Court of Georgia, 1937)
Southern Loan Co. v. McDaniel
177 S.E. 834 (Court of Appeals of Georgia, 1934)
State v. Regents of the University System
175 S.E. 567 (Supreme Court of Georgia, 1934)
Goodier v. Hamilton
19 P.2d 392 (Washington Supreme Court, 1933)
Floding Inc. v. Gunter
136 S.E. 798 (Court of Appeals of Georgia, 1927)
Roberts v. Allen
122 S.E. 86 (Court of Appeals of Georgia, 1924)
Allen v. Sams
120 S.E. 808 (Court of Appeals of Georgia, 1923)
Harvey v. Bartow County
119 S.E. 538 (Court of Appeals of Georgia, 1923)
Mendel v. Converse & Co.
118 S.E. 586 (Court of Appeals of Georgia, 1923)
Dixie Manufacturing Co. v. Ricks
118 S.E. 452 (Court of Appeals of Georgia, 1923)
Davis v. State
100 S.E. 50 (Court of Appeals of Georgia, 1919)
Potts v. Riddle
63 S.E. 253 (Court of Appeals of Georgia, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
58 S.E. 322, 2 Ga. App. 126, 1907 Ga. App. LEXIS 294, Counsel Stack Legal Research, https://law.counselstack.com/opinion/virginia-bridge-iron-co-v-crafts-gactapp-1907.