Vineyard v. Harvey

231 S.W.2d 921, 1950 Tex. App. LEXIS 2246
CourtCourt of Appeals of Texas
DecidedMay 22, 1950
Docket6050
StatusPublished
Cited by9 cases

This text of 231 S.W.2d 921 (Vineyard v. Harvey) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vineyard v. Harvey, 231 S.W.2d 921, 1950 Tex. App. LEXIS 2246 (Tex. Ct. App. 1950).

Opinion

LUMPKIN, Justice.

On April 28, 1949, the defendant, George S. Vineyard, entered into an agreement with the Panhandle Roofing Company to repair 1000 square feet of roofing covering the western portion of a building occupied by the Sunshine Dairy. The work required the removal of part of the roofing and the pouring of 2½ inches of gypsum decking. The work began on April 29, 1949, and before the work was completed a heavy rain fell, and water entered the building and soaked a large number of paper milk containers, paper caps and ice cream cartons. Two days later the roof was completed. The defendant’s testimony shows that he was present at the time the plaintiff’s workmen left the premises on the evening of April 29 and that it was agreeable with him for them to leave, even though it was raining hard at the time. He raised no question as to damage or injury to anything inside the building, and he made no effort to remove the paper containers himself.

This suit was instituted by the plaintiff, W. L. Harvey, d/b/a Panhandle Roofing Company, against the defendant, George S. Vineyard, d/b/a the Sunshine Dairy, to recover for the work done on the roof of the building occupied by the Sunshine Dairy. The plaintiff alleged that at the request of the defendant he removed and rebuilt a section of the roof and that the repair work was done in accordance with specifications contained in a written proposal made by the plaintiff to the defendant and dated April 25, 1949. The plaintiff pleaded that the removal of the old roof required a reasonable expenditure of $43.74 for labor and that the plaintiff rebuilt the roof at a cost of $740; that the defendant promised to pay for the material, work and labor but that he had refused to do so, although demand had been made upon him and he had accepted the repaired roof.

The defendant answered by exceptions, denials, and instituted a cross-action against the plaintiff. lie pleaded in his cross-action that plaintiff was acting as an independent contractor; that he undertook to do certain work in connection with repairing the roof of defendant’s building; that the plaintiff removed portions of the roof at a time and under circumstances when a person of reasonable prudence would not have done so — at a time when it appeared that there would be a rain storm. The defendant pleaded that the roof was taken off and left in such condition that the inside of the building was exposed to the elements; that while the plaintiff was working on the roof he knew the defendant was operating a business; and that a substantial stock of goods, wares and merchandise was stored in the building and in close proximity to that portion of the roof which was being repaired. The defendant alleged that while the plaintiff was working on the roof, and after he had removed a part of it so that the inside of the building was exposed to the elements, it commenced to rain; that the plaintiff made no arrangement for the protection of the merchandise stored in the building; that the plaintiff withdrew his employees from the work and left the roof in a condition which he knew, or by the exercise of reasonable diligence should have known, would cause the water to seep into the building and destroy the value of the goods, wares and merchandise stored therein; and that the plaintiff made no effort to notify the defendant that no provision had been made to protect the inside of the building. The defendant alleged that such action on the part of the plaintiff was negligence and was the direct and *923 proximate cause of the injury and damage sustained by him. The defendant asked for damages in the amount of $628.57.

By special exception the plaintiff pointed out that there was nothing in the original agreement which bound him to protect the roof while repairing same, nor were there any allegations in defendant’s pleadings ■charging the plaintiff with any act of negligence in connection with the construction and repair of the roof. At the trial the defendant tendered into court $111.43 which he stated was the difference between the damage sustained by him and the amount the plaintiff was claiming for repairing the roof.

The trial court overruled the plaintiff’s exceptions and submitted the case to the jury upon special issues. In answer to the special issues the jury found that the plaintiff in repairing the defendant’s roof had not guarded against damage to personal property which might result from rain, that such action was negligence and that such negligence was the proximate cause of the defendant’s damages, which amounted to $628.57. In answer to Special Issue No. 5 the jury found that the defendant’s failure to keep the containers, bottles and caps from getting wet was negligence, and in answer to Special Issue No. 6 the jury found the defendant’s negligence was the proximate cause of the damage done the containers, caps and bottles.

Each party filed and urged a motion for judgment in his favor, the plaintiff’s motion being based upon the verdict of the jury and the defendant’s motion being in the nature of a motion for a judgment non obstante veredicto. The defendant’s motion was overruled and the plaintiff’s motion was granted. From the uncontra-dicted evidence and the admission of counsel in open court, the trial court found that the plaintiff, W. L. Harvey, was entitled to recover $740 for the repairing of defendant’s roof and' $43.75 for the removal of the old deck and roof. The trial court, therefore, rendered judgment for the plaintiff in the sum of $783.75. The court rendered judgment, based upon the verdict of the jury, that the defendant take nothing by reason of his cross-action. To this ruling and judgment of the trial court the defendant has duly perfected his appeal to this court.

The defendant attacks the court’s judgment in three points of error. First, he contends the trial court violated the best evidence rule when the plaintiff was permitted to introduce oral testimony as to the terms of the written agreement between the parties. Irrespective of whether the record shows a written contract, the defendant’s pleadings admit the existence of a contract between the parties; and the defendant himself, without objection, testified as to its terms. Furthermore, as we have seen above, the defendant tendered $111.43 into court, the amount the defendant stated was the difference between the contract price of repairing the roof and the value of the merchandise which was damaged by the water. McCormick and Ray, Texas Law on Evidence, page 944, states the rule which, in our opinion, answers defendant’s point of error: “However, even though it appears that the evidence relates to a written document, if it is admitted without objection, or if objected to only upon another and untenable ground, the objection that it is secondary is waived, and the evidence so admitted (being perfectly relevant and only subject to objection under a technical rule of preference) is to be considered on appeal on the same footing as other competent evidence.”

Next, the defendant contends the court erred in the manner in which Special Issue No. 5 was submitted to the jury. This special issue reads as follows: “Do you find that the failure of the defendant, Vineyard, to take any action to keep the containers, bottles and caps in question from getting wet was negligence?”

The jury answered “Yes.” The defendant insists that this issue as submitted places the burden of proof on him.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bank of El Paso v. T.O. Stanley Boot Co.
809 S.W.2d 279 (Court of Appeals of Texas, 1991)
Fidelity & Casualty Co. of New York v. Shubert
646 S.W.2d 270 (Court of Appeals of Texas, 1983)
Commercial Insurance Co. of Newark v. Smith
596 S.W.2d 661 (Court of Appeals of Texas, 1980)
Drake Co. v. Lesikar Construction Co.
413 S.W.2d 424 (Court of Appeals of Texas, 1967)
Brittian v. Hale County
297 S.W.2d 721 (Court of Appeals of Texas, 1957)
Ditta v. Pogue
249 S.W.2d 938 (Court of Appeals of Texas, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
231 S.W.2d 921, 1950 Tex. App. LEXIS 2246, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vineyard-v-harvey-texapp-1950.