Villaume Industries, Inc. v. Dakota County Board of Commissioners

386 N.W.2d 344, 1986 Minn. App. LEXIS 4311
CourtCourt of Appeals of Minnesota
DecidedMay 6, 1986
DocketNo. C3-85-2313
StatusPublished

This text of 386 N.W.2d 344 (Villaume Industries, Inc. v. Dakota County Board of Commissioners) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Villaume Industries, Inc. v. Dakota County Board of Commissioners, 386 N.W.2d 344, 1986 Minn. App. LEXIS 4311 (Mich. Ct. App. 1986).

Opinion

OPINION

PARKER, Judge.

Appellant Villaume Industries, in its capacity as a taxpayer, brought this action to enjoin respondents Goodhue and Dakota Counties from entering into a long-term lease for the development of a jointly owned hydropower dam. Villaume appeals from a trial court order dissolving a temporary restraining order and dismissing Vill-aume’s complaint with prejudice. We affirm.

FACTS

Dakota and Goodhue Counties jointly own a dam and attached powerhouse at Lake Byllesby, located on the Cannon River. The counties received an order from the Federal Energy Regulatory Commission allowing the counties to proceed to develop hydropower at Lake Byllesby Dam. The counties prepared a formal request for sealed proposals (RFP) to select a developer for the project.

The draft RFP was presented to all potential developers expressing an interest in the project, including Byllesby Hydro Power Co. (BHP). BHP is closely tied to appellant Villaume. BHP’s principals are Robert Linsmayer and Peter Burno. Linsmayer is also president of Villaume Industries. The final RFP was submitted, and seven sealed proposals were received for the project, including proposals from BHP, respondent North American Hydro (NAH), and American Hydro.

A selection review committee was appointed by the Dakota and Goodhue County Boards. A subcommittee of this group recommended further consideration of the proposals of BHP, respondent NAH, and American Hydro. The full selection review committee recommended that NAH be awarded the project. BHP was the committee’s second choice.

Respondents state that the committee evaluated the proposals in accordance with the criteria contained in the RFP, including (1) technical and financial experience and capability; (2) guaranteed income to the counties; (3) the reimbursement formula to the counties; (4) the level of risk to the counties; and (5) start-up dates.

The counties retained the services of independent engineering and financial consultants to aid in drafting the RFP and evaluating the proposals. Barr Engineering provided engineering input, and Peat, Marwick, Mitchell & Co. provided financial advice. The RFP stated that preference would be given to proposals that “responsibly maximize the net economic benefit to the Counties from permitting development at the site, that provide maximum system dependability, and that responsibly minimize the risks to Dakota and Goodhue Counties in connection with the development of the site * * Nowhere does the RFP state that revenue maximization was the sole criterion in the selection process.

RFP section V, subsection (c), entitled “Right to Reject,” states:

In submitting this proposal, it is understood by the undersigned that the right is reserved by the Counties to accept any proposal, to reject any and all proposals, and to waive any irregularities or infor-malities that are in the best interest of the Counties.

The evaluation committee’s final recommendation of NAH as the number-one-ranked developer and BHP as the number-two-ranked developer was based on comparison of the two developers’ sealed pro-[346]*346posáis. This comparison indicated that NAH’s original proposal provided more revenue and less risk to the counties than BHP’s original proposal.1

The Goodhue County Board approved the committee’s recommendation and authorized commencement of contract negotiations with NAH in accordance with the selection procedure outlined in the RFP. The Dakota County Board unanimously passed a similar resolution despite BHP’s objections. The RFP provided for a 30-day negotiation period to follow selection of the developer:

Upon approval of the selected developer and receipt of authorization to commence negotiations, the Counties will enter into negotiations with the selected developer concerning the terms of the development agreement between the parties. If, however, the Counties and the selected developer have not executed a development agreement for the site within thirty calendar days of the date of authorization to commence negotiations, the Counties may, at their option, terminate negotiations with the selected developer and initiate negotiations with the second-ranked developer.

At the Dakota County Board meeting the board denied BHP’s request to negotiate jointly with the counties along with NAH, but told BHP it could submit additional information to the county for consideration. Afterward, BHP submitted documents criticizing the NAH proposal and making coun-terproposals. Several meetings were held in response to BHP’s continued activity.

The Dakota County Board responded to BHP’s allegations that the counties’ financial consultant had committed substantial errors by authorizing staff to retain Coopers and Lybrand to provide a second financial opinion. Coopers and Lybrand found no errors by Peat, Marwick, Mitchell & Co. in their analysis, as BHP alleged, and found no material factors overlooked.

During the negotiation period BHP submitted, on two occasions, substantial modifications to its original proposal. The first revision of BHP’s proposal changed its reimbursement formula from 50-55 percent of income to 33⅛ percent of revenue after expenses and raised its guaranteed tax payment from zero to $35,000. BHP’s second revised proposal was submitted to Dakota County staff three months after receipt of the sealed proposals. This proposal again changed the basis of the reimbursement formula to the counties by converting it to a 25-36 percentage of gross revenue, rather than a 33⅛ percentage of revenue after expenses. BHP argues that its proposal will return between $1,000,000 and $3,000,000 more to the counties than the NAH proposal.

NAH’s original proposal was modified to address items not specifically covered in the RFP but which came to light during the course of negotiations. NAH’s additional concessions included financial participation in sluice gate repairs, crest gate improvements, and compensation for income which may be lost as a result of the developer signing a long-term energy contract with NSP in 1987 rather than 1988. These additional concessions increase reimbursement to the counties by approximately $39,000 over the 50-year life of the lease.

ISSUE

Did the trial court err in dissolving the temporary restraining order and dismissing Villaume’s complaint?

[347]*347DISCUSSION

This appeal is taken from a trial court order granting respondents’ motion to dismiss for failure to state a claim. Nevertheless, it is clear that the trial court reached the merits of Villaume’s claim for injunc-tive relief when it dismissed the company’s complaint with prejudice.2 For purposes of this appeal, we treat the trial court’s order as a denial of injunctive relief.

The trial court found that Minn. Stat. § 105.482, subds. 8, 9 (1984), gives the counties broad discretionary power in the leasing of dams for the development of hydropower, and in the absence of fraud or gross abuse of discretion, the courts must accede to the exercise of that discretion by the legislative authority. We agree.

Minn.Stat. § 105.482, subd. 8, provides in pertinent part:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Griswold v. County of Ramsey
65 N.W.2d 647 (Supreme Court of Minnesota, 1954)
Dahlberg Brothers, Inc. v. Ford Motor Company
137 N.W.2d 314 (Supreme Court of Minnesota, 1965)
Borgelt v. City of Minneapolis
135 N.W.2d 438 (Supreme Court of Minnesota, 1965)
Hubbard Broadcasting, Inc. v. Metropolitan Sports Facilities Commission
381 N.W.2d 842 (Supreme Court of Minnesota, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
386 N.W.2d 344, 1986 Minn. App. LEXIS 4311, Counsel Stack Legal Research, https://law.counselstack.com/opinion/villaume-industries-inc-v-dakota-county-board-of-commissioners-minnctapp-1986.