Viles v. Barre & Montpelier Traction & Power Co.

65 A. 104, 79 Vt. 311, 1906 Vt. LEXIS 129
CourtSupreme Court of Vermont
DecidedNovember 20, 1906
StatusPublished
Cited by8 cases

This text of 65 A. 104 (Viles v. Barre & Montpelier Traction & Power Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Viles v. Barre & Montpelier Traction & Power Co., 65 A. 104, 79 Vt. 311, 1906 Vt. LEXIS 129 (Vt. 1906).

Opinion

Haselton, J.

In June, 1897, the plaintiff and the defendant entered into a written contract by the terms of which the plaintiff agreed to' furnish, every day in the year for a period of five years, .electrical power to- the defendant sufficient for the operation of its electric railway between Montpelier and Barre, and the defendant agreed to pay for such power at a price named, in monthly installments.

The contract provided that the plaintiff should not be responsible to the defendant for damage resulting to it “from [314]*314interruptions to its traffic on its electric railways caused by fire, flood, tempest, riots, or a public enemy.”

It appeared that in 1899, from August 19 to1 September 1, inclusive, the plaintiff during some portions of each day but one, failed to furnish the amount of power which under his contract he was bound to- furnish, and it further appeared that during said days the defendant availed itself of power furnished, for the purpose of operating its road when it could, but that in consequence of shortage of power the operation of the road was from time to time necessarily suspended, and the defendant’s cars were at a standstill.

September first the defendant sent.the plaintiff a written notice stating that on account of the plaintiff’s breach of the contract in failing to furnish the power therein provided for, the defendant, after the delivery of the notice, would treat the contract as ended and Would neither take, accept nor pay for any more power under the contract. It appeared that this notice was received by the plaintiff in the morning of September second, and that thereafter no power was taken by the defendant from the plaintiff.

All the power taken by the company up' to July 1, 1899, had been paid for, and in this case, which is a consolidation of two- suits, recovery was sought for the power furnished on and after that date.

The plaintiff had fallen short of compliance with the contract. He could, therefore, recover, if at all, only upon such a showing as would entitle him to recover quantum- meruit. The plaintiff, subject to objection and exception, introduced evidence tending to show that his failure to fulfil the contract was not wilful, but that it resulted while he was endeavoring in entire good faith to- perform according to the exact terms' of the contract. His plant was operated by water power, and [315]*315some of the evidence objected to tended to show’ that his failure was the result of an extraordinary and unforeseen drouth. It appeared that he had other patrons besides the defendant, and some of the evidence objected to- tended tO' show that the wants of -these patrons were not allowed to hin,der him in his endeavors to> supply the defendant; in other words, that he gave the defendant a preference over his other patrons. Some of the evidence objected to was to the point that after the shortage occurred or. became imminent an auxiliary steam1 power could not have been established in time to relieve the situation. All this evidence was rightly admitted. Though the plaintiff had broken his contract, he had furnished power which the defendant had taken and used. In the nature of things there could be no rescission.

In the circumstances of the case, if the plaintiff could satisfy the jury that he had endeavored in entire good faith to .fulfil the contract to the letter, then he was entitled to a quantum meruit recovery unless- the amount of damage resulting to the defendant from the breach of contract was such as to prevent such recovery.

The common law rule which sometimes worked hardships undeserved and unsalutary has been somewhat relaxed, but good faith in endeavoring to perform fully and exactly is essential to a quantum meruit recovery in a case like this. In such a case, unless the party in default has in good faith endeavored to accomplish full performance he deserves nothing. To hold -otherwise would be to encourage a disregard of contract obligations; while so to hold is to enforce the law of contracts as rightly understood, for of this law there is no better definition than that of Sir Frederick Pollock, who says: “The law of contract may be described as the endeavor of the state, a more or less imperfect one, by the nature of the [316]*316case, to- establish a positive sanction for the 'expectation of good faith which has grown up in the mutual dealings of men of average right mindedness.” Willistoo’s Wald’s Pollock on Contracts, i.

The evolution and establishment in this State of the rule which now obtains, here in a case such as the plaintiff’s evidence tended to make, may be sufficiently traced through the following cases: Dyer v. Jones, 8 Vt. 205; Gilman v. Hall, 11 Vt. 510; Fenton v. Clark, 11 Vt. 557; Ripley v. Chapman, 13 Vt. 268; Barker v. Troy and Boston R. R. Co., 27 Vt. 780; Brackett v. Morse, 23 Vt. 557; Hubbard v. Belden, 27 Vt. 645; Swift v. Harriman, 30 Vt. 608; Bragg v. Bradford, 33 Vt. 38; Eddy v. Clement, 38 Vt. 486.

Sbme of the cases cited above speak of substantial performance as an element of recovery; but as is pointed out in Drew v. Goodhue, 74 Vt. 437, 52 Atl. 971, the phrase “substantial performance” is used in two senses. That it has a double and so> a confusing use is made altogether clear by the opinion in Manning v. School District, 124 Wis. 84, 102 N. W. 356. In some of the cases it means full performance according to' the fair intent 0-f the contract, and permits recovery on the contract without recoupment. But as used in the cases relevant toi the question here, it means something distinctly short of full performance, as the facts of the cases show, and includes such performance as was in this case shown to have been rendered down to. the time when the defendant elected to treat the contract as at an end.

Counsel for the defendant cite Lawrence v. Davey, 28 Vt. 264, as a case analogous to this. There the plaintiff contracted to- deliver certain quantities of hard wood coal to- the defendant, but failed to deliver the quantities he had agreed to. The plaintiff recovered on the ground of a waiver by the [317]*317defendant, and in the opinion it is said that probably recovery could not have been had if the defendant had insisted upon, strict performance of the contract. But that case states the things which the evidence of the plaintiff therein tended to show, and it did not tend to> show that the plaintiff endeavored in good faith to' comply with the terms of the contract.

Eddy v. Clement, 38 Vt. 486; is cited by the defendant as a case favorable to: its contention. The plaintiff therein failed to furnish the defendants with the quantity of lumber which he had contracted to» furnish them, and it was held that, though he was prevented from fulfilling on account of a severe drouth which stopped the lumber mills on which he was dependent, nevertheless, he broke his contract. But the effect given to the plaintiff’s breach of contract was simply to permit the defendant to recoup his damages, and judgment went for the defendant solely because the damages recouped by the defendant equalled the sum to which at the contract price the lumber delivered and unpaid for would come.

Kettle v. Harvey, 21 Vt.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vance v. Forty-Eight Star Mill
215 P.2d 1016 (New Mexico Supreme Court, 1949)
Schwasnick v. Blandin
65 F.2d 354 (Second Circuit, 1933)
Ronan v. J. G. Turnbull Co.
131 A. 788 (Supreme Court of Vermont, 1926)
Capital Garage Co. v. Powell
127 A. 375 (Supreme Court of Vermont, 1925)
Burlington Grocery Co. v. Heaphy's Estate
126 A. 525 (Supreme Court of Vermont, 1924)
Pacific-Wyoming Oil Co. v. Carter Oil Co.
226 P. 193 (Wyoming Supreme Court, 1924)
Wilbur v. Town of Calais
98 A. 913 (Supreme Court of Vermont, 1916)
Douglass & Varnum v. Village of Morrisville
95 A. 810 (Supreme Court of Vermont, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
65 A. 104, 79 Vt. 311, 1906 Vt. LEXIS 129, Counsel Stack Legal Research, https://law.counselstack.com/opinion/viles-v-barre-montpelier-traction-power-co-vt-1906.