Vigliarolo Bros. v. Lanza Contracting Corp.

127 Misc. 2d 965, 487 N.Y.S.2d 979, 1985 N.Y. Misc. LEXIS 2765
CourtCivil Court of the City of New York
DecidedMarch 29, 1985
StatusPublished
Cited by1 cases

This text of 127 Misc. 2d 965 (Vigliarolo Bros. v. Lanza Contracting Corp.) is published on Counsel Stack Legal Research, covering Civil Court of the City of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vigliarolo Bros. v. Lanza Contracting Corp., 127 Misc. 2d 965, 487 N.Y.S.2d 979, 1985 N.Y. Misc. LEXIS 2765 (N.Y. Super. Ct. 1985).

Opinion

OPINION OF THE COURT

Joseph Slavin, J.

The motion by all defendants other than the defendant Lanza Contracting Corp. to dismiss pursuant to CPLR 3211 (a) (5) and (7) or for summary judgment pursuant to CPLR 3212 is denied.

Plaintiff is evidently in the business of either acting as a hauler of demolition debris or leasing trucks and equipment to others for such purpose.

From the pleadings and the affidavits, it appears that there is no dispute that between ¡June 17, 1983 and October 27, 1983 [966]*966plaintiff leased such equipment to the defendant Lanza. Lanza was a subcontractor for the defendant Clark-Fitzpatrick, Inc. (hereafter Clark). Clark was the prime contractor for extensive road renovation work on a section of what is commonly known as the Belt Parkway here in Brooklyn. The total (and undisputed) amount charged to Lanza was $47,902.38. Of this amount all but $3,605 was paid either directly by Lanza or through a check issued by Clark jointly to Lanza and plaintiff. This net amount is now sought against Clark and the two sureties (Federal and Aetna) on its labor and material bond.

At issue in the motion is the applicability of State Finance Law § 137 (3) and (4) (b) as amended by the Laws of 1980 (ch 360).

The moving defendants’ first prong of attack is based upon subdivision 3. This attack is twofold. Clark initially argues that it cannot be a direct defendant (absent their being a necessary party in an action on the bond), in that plaintiff had “no contractual relationship express or implied with such contractor.” As to this point, I find from all of the documents annexed to the papers submitted that no implied contractual relationship was established by reason of the payment of $23,750 by Clark’s check issued jointly on September 1, 1983, to plaintiff and Lanza. Likewise the request for waiver of lien prepared by Clark on November 16, 1983 and sent to plaintiff does not create a contractual relationship.

In that I agree with Clark that there was no contractual relationship between it and plaintiff, we now turn to Clark’s second prong of attack, not only in its own behalf but also on behalf of the sureties. As to this point the section reads in pertinent part that: “3. Every person who has .furnished * * * material * * * to a subcontractor of the contractor, in the prosecution of work provided for in the contract and who has not been paid in full therefor before the expiration of a period of ninety days after the day on which the last of the * * * material was furnished by him for which the claim is made, shall have the right to sue on such payment bond in his own name for the amount, or the balance thereof, unpaid at the time of commencement of the action; provided, however, that a person having a direct contractual relationship with a subcontractor of the contractor furnishing the payment bond but no contractual relationship express or implied with such contractor shall not have a right of action upon the bond unless he shall have given written notice to such contractor within one hundred twenty days from the date on which the last of the labor was performed or the last [967]*967of the material was furnished, for which his claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or for whom the labor was performed.”

Looking at the cited portion of the section, and keeping in mind the purposes of the State of New York in requiring these payment surety bonds, which is to protect suppliers of labor and materials by guaranteeing them payment of their proper charges HNC Realty Co. v Bay View Towers Apts. (92 Misc 2d 151, mod 64 AD2d 417), we must determine if there is no factual issue as to whether plaintiff gave “written notice to such contractor * * * with substantial accuracy the amount claimed”.

Clark maintains that it did not receive “within one hundred twenty days from the date on which the last * * * of the material was furnished” a formal document setting forth the claim. Plaintiff urges, that while no such formal document was sent, by reason of the dealings between them and Clark (including the oral discussions of continual withholding of moneys paid by Clark to Lanza by Lanza which gave rise to the September 1, 1983 payment discussed above) and a November 16,1983 letter and waiver of lien sent to it by Clark, that the spirit, if not the letter, of the claim was timely presented to Clark.

On November 16, 1983 (which is within the 120-day period) Clark, through its accounts payable supervisor, sent plaintiff a letter, with reference to the job on which Lanza had been working, which in pertinent part reads: “Attached you will find a waiver of lien form for the above-referenced project. In order to produce joint checks for monies of owed to you by Lanza Contracting Corp. for this project, it is necessary for us to receive this form with the appropriate dollar amounts filled in.”

An examination of the waiver of lien form, bearing Clark’s name at the top thereof, including looking at the typewritten portions, I find that Clark inserted the date (Nov. 16, 1983), plaintiff’s and Lanza’s names, that it included work performed “to and including October 14, 1983.” The dollar amounts, both written out and in figures (total billed $47,922.38, balance due $3,605) and “unpaid as of November 16, 1983” as well as the signing date of November 28, 1983 were typed or handwritten by plaintiff. The preprinted waiver form included specific reference to Clark’s master contract, having the contract number, job number and other identification.

I find, for the purpose of this motion, that this waiver of lien is sufficient in form to satisfy the requirements that the “written notice * * * (states) with substantial accuracy the [968]*968amount claimed, and the name of the party to whom the material was furnished”. In connection with this determination I have considered Ulster Elec. Supply Co. v Maryland Cas. Co. (30 NY2d 712) cited by defendants. Their reliance on such case as it relates to the form of the statement is not well taken, merely by referring to the language of the letter written in Ulster. The Court of Appeals affirmed the Appellate Division reversal of the denial of a dismissal solely on the question of the mode of service of the statement. At 30 NY2d, page 713, the court specifically wrote “[w]e pass on no other question.” Looking at the Ulster case at the Appellate Division, we find, in the dissent, Mr. Justice Herlihy, wrote “[t]he majority do not reach the question of the sufficiency of the alleged notice to meet the requirements of * * * section 137, but it appears” that even the skimpy letter sent in Ulster was sufficient (35 AD2d 309, 312). A fair reading of both court’s decisions would indicate that the issue of the sufficiency of a notice was never fully determined, although the Court of Appeals had before it the dissent which specifically mentioned such problem.

As stated, I find that the waiver form, in this case is a proper notice since it meets the criteria for such a notice so properly stating the purpose of these bonds as set forth in paragraph 10 of the reply affirmation of Mr. Jonathan R. Morris, the defendants’ attorney: “The reason for the notice requirement is to afford protection to the contractor by fixing a date beyond which the contractor will not be liable for the subcontractor’s debts and to apprise the contractor of the fact the supplier is looking to it for payment of the subcontractor’s obligation. See e.g.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Riluc Co. v. Reliance Insurance
181 A.D.2d 1048 (Appellate Division of the Supreme Court of New York, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
127 Misc. 2d 965, 487 N.Y.S.2d 979, 1985 N.Y. Misc. LEXIS 2765, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vigliarolo-bros-v-lanza-contracting-corp-nycivct-1985.