Victore Insurance Co. v. City of Bowie

23 S.W.3d 499, 2000 Tex. App. LEXIS 3642, 2000 WL 718809
CourtCourt of Appeals of Texas
DecidedJune 1, 2000
Docket2-99-070-CV
StatusPublished
Cited by9 cases

This text of 23 S.W.3d 499 (Victore Insurance Co. v. City of Bowie) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Victore Insurance Co. v. City of Bowie, 23 S.W.3d 499, 2000 Tex. App. LEXIS 3642, 2000 WL 718809 (Tex. Ct. App. 2000).

Opinion

OPINION ON REHEARING

CAYCE, Chief Justice.

I.Introduction

We grant Victore Insurance Company’s motion for rehearing, withdraw our opinion and judgment of March 9, 2000, and substitute this opinion and judgment.

The primary issue we must decide in this appeal is whether Diamondback Construction, Inc., a public work contractor, acquired a property interest in the final payment due under its public work contract with the City of Bowie, Texas even though Diamondback failed to pay all costs necessary to complete the contract. Because we hold Diamondback did not acquire a property interest in the remaining contract proceeds, we will reverse the trial court’s judgment in part.

II.Background Facts

In February 1992, Diamondback and the City entered into a public work contract for the construction of wastewater collection line improvements. Because of the contract amount, both performance and payment bonds were required. See Tex. Gov’t Code Ann. § 2258.021(a) (Vernon Supp.2000). 1 Victore, as surety, issued both bonds to ensure completion of and payment for the contract.

Although the contract was eventually completed in October 1992, Victore had to cover Diamondback’s payroll for two months while the project was under construction. Victore notified the City not to make any more progress payments under the contract, and the City received numerous claims from Diamondback’s subcontractors and suppliers who had not been paid. After charging $16,800 in liquidated damages against the contract balance for completion delays, in December 1992 the City notified Victore that $38,149.85 in contract proceeds had not been paid to Diamondback.

In November 1992 and February 1993, the City received notices from the Internal Revenue Service of two tax levies against Diamondback’s property. Over Victore’s objections, the City paid the $33,149.85 in remaining contract proceeds towards the IRS levies rather than holding the proceeds to satisfy the subcontractors’ and suppliers’ claims. Victore eventually paid nearly $37,000 to settle the subcontractors’ and suppliers’ claims and then sought to recover the $33,149.85 contract balance from the City, as well as $9,150 of the liquidated damages the City had charged against the contract.

After a bench trial, the trial court rendered a take-nothing judgment against Victore. Victore appeals from that judgment.

III.The City’s Liquidated Damages

In its first point, Victore complains the City improperly withheld liquidated damages from the contract balance because the project was completed on time. We hold the City was entitled to some, but not all, of the liquidated damages it withheld.

The contract allowed the City to recover $150 in liquidated damages for each day *502 Diamondback was late in completing the project. After work on the contract was completed, the City charged $16,800 in liquidated damages against the contract. The City was entitled to this amount only if Diamondback was 112 days late in completing the contract (112 x 150 = 16,800).

The parties stipulated, and the trial court found, that Diamondback had 150 days to complete the contract but took 201 days to complete it. Victore also requested a fact finding that Diamondback used 201 days to complete the contract and therefore cannot complain about this finding on appeal. See Metzger v. Sebek, 892 S.W.2d 20, 42 (Tex.App.—Houston [1st Dist.] 1994, writ denied), cert. denied, 516 U.S. 868, 116 S.Ct. 186, 133 L.Ed.2d 124 (1995).

Nonetheless, Victore can challenge the correctness of the trial court’s legal conclusions based on these facts. See Forbis v. Trinity Universal Ins. Co., 833 S.W.2d 316, 819 (Tex.App.—Fort Worth 1992, writ dism’d). Although the trial court did not make any separate conclusions of law, its take-nothing judgment against Victore on the liquidated damages issue is a legal conclusion that the City was entitled to the entire $16,800 because the project was completed 112 days late. This conclusion is incorrect, based on the trial court’s finding that the project was completed in 201 days, or only 51 days late. Accordingly, the City was only entitled to $7,650 in liquidated damages (51 x 150 = 7,650). We sustain Victore's first point as to the remaining $9,150 of the $16,800 in liquidated damages.

IV. Diamondback’s Entitlement to the Remaining Contract Proceeds

In point four, Victore complains the City improperly paid the $33,149.85 contract balance to the IRS after receiving the notices of federal tax levies against Diamondback because the contract proceeds were not Diamondback’s property. We agree.

The Internal Revenue Code provides: “If any person liable to pay any tax neglects or refuses to pay the same after demand, the amount ... shall be a lien in favor of the United States upon all property and rights to property, whether real or personal, belonging to such person.” 26 U.S.C.A. § 6321 (West 1989). The Supreme Court has construed this statutory language broadly, noting that the statute “reveals on its face that Congress meant to reach every interest in property that a taxpayer might have.” United States v. National Bank of Commerce, 472 U.S. 713, 719-20, 105 S.Ct. 2919, 2924, 86 L.Ed.2d 565 (1985); Medaris v. United States, 884 F.2d 832, 833 (5th Cir.1989). A person who receives notice of an IRS levy must surrender to the IRS any of the delinquent taxpayer’s property in the recipient’s possession or any obligations, such as income, the recipient owes the delinquent taxpayer. See 26 U.S.C.A. § 6332(a) (West Supp.1999). 2

To determine whether property is subject to the federal tax lien, courts conduct a two-step analysis. First, they look to state law to determine whether the taxpayer has an interest in the property. See National Bank of Commerce, 472 U.S. at 722, 105 S.Ct. 2919, 2925; Broday v. United States, 455 F.2d 1097, 1099 (5th Cir.1972). If the taxpayer has an interest in the property under state law, the tax consequences are dictated by federal law. National Bank of Commerce, 472 U.S. at 722, 105 S.Ct. 2919, 2925.

A lien arising under section 6321 cannot, however, extend beyond the property interests held by the delinquent taxpayer. See United States v. Rodgers, 461 U.S. 677, 690-91, 103 S.Ct. 2132, 2141, 76 L.Ed.2d 236 (1983); Gardner v. United *503 States, 34 F.3d 985, 987 (10th Cir.1994).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harris County Flood Control District v. Great American Insurance Co.
359 S.W.3d 736 (Court of Appeals of Texas, 2011)
Kemper Insurance Companies v. State
70 A.D.3d 192 (Appellate Division of the Supreme Court of New York, 2009)
Capitol Indemnity v. USA
Fifth Circuit, 2006
Gallegos v. Espinoza
2002 NMCA 011 (New Mexico Court of Appeals, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
23 S.W.3d 499, 2000 Tex. App. LEXIS 3642, 2000 WL 718809, Counsel Stack Legal Research, https://law.counselstack.com/opinion/victore-insurance-co-v-city-of-bowie-texapp-2000.