Veolia Water North America Operating Services, LLC v. City of Atlanta

546 F. App'x 820
CourtCourt of Appeals for the Eleventh Circuit
DecidedOctober 18, 2013
Docket19-90011
StatusUnpublished
Cited by2 cases

This text of 546 F. App'x 820 (Veolia Water North America Operating Services, LLC v. City of Atlanta) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Veolia Water North America Operating Services, LLC v. City of Atlanta, 546 F. App'x 820 (11th Cir. 2013).

Opinion

PER CURIAM:

This case arises from a contract dispute between the City of Atlanta and Veolia Water North America Operating Services, LLC regarding the improvement, operation, and maintenance of four City-owned wastewater treatment facilities. Both parties claimed breach, and, after an 11-day bench trial, the district court awarded Veo-lia $21 million in damages and the City $11 million in damages. Both parties have now appealed that judgment.

Veolia appeals the award to the City of over $9 million for the lease and operating expenses of replacement belt presses, $302,333 for two damaged digester lids, and $948,608 in prejudgment interest. The City appeals the award to Veolia of approximately $3.8 million in prejudgment interest and the denial of its request for attorney’s fees. After review and with the benefit of oral argument, we affirm in part, reverse in part, and remand for further proceedings.

I. Background & Facts

Because we write only for the parties, we assume their familiarity with the extensive record in this case, and only restate those facts necessary for our decision.

In April of 2001, the City of Atlanta released a request for proposal for an alternative method of waste disposal at its wastewater treatment facilities. The City eventually awarded Veolia the contract, and the two parties executed a service agreement in August of 2002. The agreement called for Veolia to operate and maintain part of the facilities for ten years *823 on condition that Veolia accept the facilities “as is.” It also required Veolia to provide a letter of credit that the City could draw upon if Veolia defaulted on the agreement.

In December of 2002, Veolia took over the facilities’ dry side operations under the terms of the agreement. Over time, the four digester tanks at the RM Clayton facility — which had not been cleaned in years — began to fall into disrepair. 1 Although another company had been awarded a contract to clean the digester lids at RM Clayton, the City delayed that work until after Veolia had installed new centrifuges that were expected to improve the digester conditions and lower costs. As a result, digester tank cleaning at RM Clayton did not begin until October of 2004.

In March of 2005, the digester tanks at RM Clayton began to operate near or above their maximum capacity. By April 8, 2005, the lid for one of the digester tanks collapsed under the weight of the excess waste. Another digester lid suffered the same fate on December 81, 2005. After the digester lids collapsed, the City had to lease out belt presses from Synagro Technologies, Inc. The belt presses provided a substitute method for processing waste until the digester lids could be replaced. 2 The City used the belt presses at RM Clayton for approximately two years.

On July 10, 2006, the City served Veolia with a notice of termination for purported breaches of the service agreement. The City also drew upon Veolia’s letter of credit in full for $9,525,304. Veolia, in turn, sued the City to recover on unpaid invoices and various operating expense increases. The City answered and asserted its own breach of contract claims against Veolia. The case proceeded to a bench trial.

After the trial, the district court concluded that both parties had breached the agreement. As to Veolia, the district court found that it had caused the digester lids to collapse, and was liable for the remaining value of the digester lids and the expenses the City incurred from leasing the belt presses. As to the City, the district court found that it owed Veolia for unpaid work and had to return the full amount of the letter of credit because the City had •wrongfully drawn on the letter.

Both parties filed motions to alter or amend the judgment. Veolia argued that the City’s recovery for belt press expenses was improper because the City had not proven avoidance costs or, alternatively, the award was subject to a $2 million cap under the agreement; the digester lids had no remaining monetary value; and it was owed prejudgment interest. The City, for its part, sought to recover its attorney’s fees. The district court denied all of the requested relief except for Veo-lia’s claim for prejudgment interest. This appeal followed, and the parties presented oral argument to the panel.

II. Discussion

“After a bench trial, we review the district court’s conclusions of law de novo and ... factual findings for clear error.” Proudfoot Consulting Co. v. Gordon, 576 F.3d 1223, 1230 (11th Cir.2009) (citation omitted). Because this is a diversity case, we “look[ ] to state law as to substantive *824 matters but procedural matters are governed by federal law.” Helmich v. Kennedy, 796 F.2d 1441, 1443 (11th Cir.1986) (citing to Hanna v. Plumer, 380 U.S. 460, 469-74, 85 S.Ct. 1136, 14 L.Ed.2d 8 (1965)).

On appeal, both parties raise the arguments made in their respective Rule 59(e) motions. They also raise separate issues relating to the district court’s award of prejudgment interest. Veolia argues that its award should not have been reduced by the amount of prejudgment interest that the City would have been entitled to. And the City argues that Veolia should not have been awarded prejudgment interest on the letter of credit. We turn to all of these issues below.

A. The Belt Presses

In its order, the district court concluded that the City was entitled to recover $9,032,469.19 in expenses that it had incurred for the replacement belt presses. That award represented the full amount that the City had paid Synagro. The district court did not offset the award in any way because it also found that Veolia had failed to provide any evidence that damages could have been mitigated or that the City had avoided significant operating expenses.

First, we address Veolia’s argument that the City’s belt press damages were consequential damages and, therefore, subject to a $2 million cap under the terms of the agreement. The district court found that Veolia had waived this argument because “it never invoked the [$2 million cap provision] at any time during the trial ... [and] [i]t never referred to [the provision] in its proposed findings of fact and conclusions of law.” D.E. 392 at 9. 3

“We review a district court’s procedural ruling on waiver of an affirmative defense for abuse of discretion.” Proctor v. Fluor Enters., Inc., 494 F.3d 1337, 1350 n. 9 (11th Cir.2007) (citation omitted). Veolia argues that it did not waive this argument because it asserted the consequential damages limitation in the pretrial order and one of the City’s witnesses testified that the belt press expenses were “an alleged consequence” of the digester lid collapses.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
546 F. App'x 820, Counsel Stack Legal Research, https://law.counselstack.com/opinion/veolia-water-north-america-operating-services-llc-v-city-of-atlanta-ca11-2013.