Venco Imtiaz Construction Company v. Symbion Power LLC

CourtDistrict Court, District of Columbia
DecidedMay 31, 2017
DocketCivil Action No. 2016-1737
StatusPublished

This text of Venco Imtiaz Construction Company v. Symbion Power LLC (Venco Imtiaz Construction Company v. Symbion Power LLC) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Venco Imtiaz Construction Company v. Symbion Power LLC, (D.D.C. 2017).

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

VENCO IMTIAZ CONSTRUCTION COMPANY, Plaintiff.

v. Civil Action No. 16-1737 (JDB)

SYMBION POWER LLC, Defendant.

MEMORANDUM OPINION

A construction company and its subcontractor are engaged in a long-running dispute over

payment for a power plant construction project in Kabul, Afghanistan, between 2008 and 2010.

The subcontractor, Venco Imitiaz Construction Company (Venco), eventually won an arbitration

award requiring the contractor, Symbion Power LLC (Symbion), to pay $ 8.5 million for the work

that Venco performed. Venco now seeks enforcement of that award. Symbion challenges that

award here, and also in a separate court proceeding in the United Kingdom. For the reasons

explained below, the Court will grant Venco’s motion for enforcement of the award, deny

Symbion’s motion for a stay, and deny as moot Venco’s motion, in the alternative, for security.

BACKGROUND

In 2008, the U.S. Agency for International Development began funding a project to build

a power plant in Kabul. The delays and disagreements began shortly thereafter. The facts that

follow are undisputed, however, unless otherwise noted.

USAID hired a U.S.-based firm, The Louis Berger Group/Black & Veatch Special Projects

Corporation (LBG/BV) to manage the project. LBG/BV then hired Symbion as is its primary

contractor. Symbion in turn hired Venco as a subcontractor responsible for certain portions of the

1 plant construction, namely for the “power blocks” that would house the electrical generators.

Resp.’s Br. [ECF No. 7] at 3. LBG/BV and Symbion had a dispute over who was responsible for

construction delays (these disputes were unrelated to Venco’s work) and, as a result, LBG/BV

withheld payment from Symbion. Id. at 3–4; Pet.’s Br. [ECF No. 1-7] at 1. Symbion, in turn,

withheld payment from Venco. Resp.’s Br. at 4; Pet.’s Br. at 1. Symbion argues that its contract

with Venco permits this, i.e., that the contract conditions payment to Venco on Symbion’s receipt

of payment from LBG/BV. Resp.’s Br. at 6. Venco takes the opposite view. Pet.’s Br. at 2–3.

According to Symbion, in 2009 LBG/BV and Symbion began arbitration proceedings

before a Tribunal of the International Court of Arbitration (ICC), as provided for in their contract.

Resp.’s Br. at 5. That tribunal concluded that LBG/BV breached its contract and was not justified

in withholding payment from Symbion, but also found that under the terms of the contract,

Symbion could not rely on the invoices that it submitted as evidence that it was entitled to full

payment. See ICC Case No. 16383/VRO, Symbion Power LLC v. LBG/BV, Final Award (Oct.

24, 2012), Ex. 4 to Resp.’s Br. [ECF Nos. 7-7–7-13] (hereinafter “Prior Award”) at 171–73.

Instead, the tribunal found that Symbion was required to separately prove the value of its work

with evidence beyond the invoices, and was only entitled to payment for the amounts it could

separately prove. Id. Venco was not a party to that arbitration proceeding nor did it participate in

it in any way.

Separately, in 2013 Venco filed a request for arbitration with the ICC against Symbion, as

required by the arbitration clause in their contract. Pet.’s Br. at 3; Resp.’s Br. at 6. A three-

arbitrator panel was empaneled pursuant to ICC rules. Pet.’s Br. at 3–4; Resp.’s Br. at 6–7. Before

the panel, Venco argued that Symbion had breached its contract by failing to make the required

payments. Pet.’s Br. at 2–3; Resp.’s Br. at 6. Symbion argued that its payments to Venco were

2 predicated on receiving payment from LBG/BV, and also raised counterclaims against Venco for

tortious interference with contract, breach of the implied covenant of good faith and fair dealing,

and malicious prosecution and abuse of process. Resp.’s Br. at 6. LBG/BV was not a party to the

Venco–Symbion arbitration. The arbitration panel reviewed briefings, received written evidence,

and held an evidentiary hearing from November 2 through November 11, 2015, where it heard

testimony from fact and expert witnesses. See ICC Case No. 19335/AGF/ZF, Venco Imtiaz

Constr. Co. v. Symbion Power LLC, Final Award (Jul. 11, 2016), Ex. 2 to Pet.’s Br. [ECF No. 1-

2] (hereinafter “Final Award”) at 22–24. The panel ultimately issued an award on July 11, 2016,

finding almost entirely in Venco’s favor. See id. at 140–42. The panel ordered Symbion to pay

all unpaid invoices that Venco had submitted, plus interest, attorney’s fees, and the cost of

arbitration. Id. It also dismissed all of Symbion’s counterclaims. Id. In total, this amounted to

$ 8,462,516.78. Id.

On August 8, 2016, Symbion filed a motion in the United Kingdom to set aside the award.

Venco, in turn, filed the instant motion in this Court to confirm and enforce the award. Petition

[ECF No. 1]. Symbion not only opposes Venco’s motion, but also filed a motion asking this Court

to stay further proceedings pending the outcome of the U.K. proceedings. Resp.’s Br. at 1–2.

Symbion’s primary argument is that the arbitration proceeding at issue here interpreted the contract

in a manner inconsistent with the prior arbitration award between Symbion and LBG/BV, and

therefore enforcement of the award in this Court would violate the public policy of issue

preclusion. Id. at 1. Venco opposes Symbion’s motion for a stay, but in the alternative, requests

that if a stay is granted, that Symbion be required to post security in the full amount of the

arbitration award. Pet.’s Reply & Opp’n [ECF No. 13] at 1. Symbion opposes the request for

security. Resp.’s Reply [ECF No. 17] at 1.

3 Since the parties completed briefing in this matter, the U.K. High Court of Justice in

London, England, has dismissed Symbion’s challenge to the arbitral award. See Symbion Power

LLC v. Venco Imtiaz Constr. Co., [2017] EWHC 348 (TCC) (March 10, 2017), Ex. 1 to Status

Report [ECF No. 22-1]. Based on the parties’ representation during a hearing before this Court on

April 18, 2017, Symbion intends to seek leave to appeal that decision. This Court has not been

advised of the time frame in which the U.K. appellate court would grant or deny leave to appeal,

or of the time frame in which that court might issue a judgment on the merits, should leave to

appeal be granted.

LEGAL STANDARD

Venco seeks enforcement of its arbitration award under the New York Convention on the

Recognition and Enforcement of Foreign Arbitral Awards. See Convention on the Recognition

and Enforcement of Foreign Arbitral Awards of June 10, 1958 (“New York Convention”), 21

U.S.T. 2517, codified at 9 U.S.C. §§ 201–08. Under the New York Convention, which is codified

as part of the Federal Arbitration Act (FAA), a “court shall confirm the award unless it finds one

of the grounds for refusal or deferral of recognition or enforcement of the award specified in the

said Convention.” Id. § 207. The FAA therefore “‘reflects an emphatic federal policy in favor of

arbitral dispute resolution.’” Marmet Health Care Ctr., Inc. v. Brown, 565 U.S. 530, 533 (2012)

(per curiam) (quoting KPMG LLP v. Cocchi, 565 U.S. 18, 21 (2011)). This emphatic federal

policy is equally true in enforcing foreign arbitration awards. See TermoRio S.A. E.S.P. v.

Electranta S.P., 487 F.3d 928, 933–34 (D.C. Cir. 2007) (citing Mitsubishi Motors Corp. v. Soler

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southern Pacific Railroad v. United States
168 U.S. 1 (Supreme Court, 1897)
Parklane Hosiery Co. v. Shore
439 U.S. 322 (Supreme Court, 1979)
Montana v. United States
440 U.S. 147 (Supreme Court, 1979)
Martin v. Wilks
490 U.S. 755 (Supreme Court, 1989)
Richards v. Jefferson County
517 U.S. 793 (Supreme Court, 1996)
New Hampshire v. Maine
532 U.S. 742 (Supreme Court, 2001)
Taylor v. Sturgell
553 U.S. 880 (Supreme Court, 2008)
Polimaster Ltd. v. RAE Systems, Inc.
623 F.3d 832 (Ninth Circuit, 2010)
Kpmg LLP v. Cocchi
132 S. Ct. 23 (Supreme Court, 2011)
Marmet Health Care Center, Inc. v. Brown
132 S. Ct. 1201 (Supreme Court, 2012)
Europcar Italia, S.P.A. v. Maiellano Tours, Inc.
156 F.3d 310 (Second Circuit, 1998)
In Re Arbitration Between Interdigital Communications Corp.
528 F. Supp. 2d 340 (S.D. New York, 2007)
G.E. Transport S.P.A. v. Republic of Albania
693 F. Supp. 2d 132 (District of Columbia, 2010)
Chevron Corporation v. Republic of Ecuador
949 F. Supp. 2d 57 (District of Columbia, 2013)
Bcb Holdings Limited v. Government of Belize
110 F. Supp. 3d 233 (District of Columbia, 2015)
Chevron Corporation v. The Republic of Ecuador
795 F.3d 200 (D.C. Circuit, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Venco Imtiaz Construction Company v. Symbion Power LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/venco-imtiaz-construction-company-v-symbion-power-llc-dcd-2017.