Vemex Trading Corporation v. Technology Ventures

563 F. App'x 318
CourtCourt of Appeals for the Fifth Circuit
DecidedApril 16, 2014
Docket11-20723
StatusUnpublished
Cited by1 cases

This text of 563 F. App'x 318 (Vemex Trading Corporation v. Technology Ventures) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vemex Trading Corporation v. Technology Ventures, 563 F. App'x 318 (5th Cir. 2014).

Opinion

PER CURIAM: **

This appeal arises from a contract dispute between Vemex Trading Corporation (“Vemex”) and Technology Ventures, Inc. (“TVI”) relating to the construction and sale of a coiled tubing unit (the “Equipment”) for use in arctic drilling operations. Vemex, the buyer, sued TVI, the manufacturer and seller, alleging that TVI delivered defective Equipment and failed to put the Equipment into working operation at the drilling site in Siberia. After a bench trial before Judge Gilmore (the “trial judge”), the court found that TVI breached the contract and awarded $564,200 in damages. Both parties appeal.

I.

On March 18, 2004, Vemex and TVI entered into Contract No. 11351 (the “Contract”). Section 1, which sets forth *321 the “Subject of the Contract,” identifies two areas of performance for TVI. The first was to sell Vemex “one New Three Piece Design Coiled Tubing Unit High Capacity including Crane for Arctic conditions ... and spare parts.” The second area of performance, which the Contract defines as “Supervision,” was to “fulfill supervision of putting the Goods into operation ... in Russia.” Section 2 specifies the amounts Vemex was to pay TVI: $564,200.00 for the Equipment and $19,600.00 for the Supervision. At the time that the parties entered into the Contract, Vemex had already “pre-sold” the Equipment to a company called Rustek for $729,750.00. Rustek, in turn, had already sold the Equipment to a company called Vend 2000 (“Vend”).

On August 31, 2004, TVI delivered the Equipment to the Port of Houston for shipment to Russia. A number of difficulties arose with the Equipment once it arrived in Russia, although the parties dispute the causes and severity of the problems. Beginning in early 2005, representatives from TVI traveled to Siberia to fulfill the Supervision duties set forth in the Contract. The parties continued to encounter difficulties with the Equipment, and TVI ceased its Supervision efforts in August or September of 2005. TVI claims that its representatives made the Equipment operational before they left, while Vemex asserts that the Equipment never became operational. Vemex claims that it made a request to TVI to return the Equipment for a full refund; TVI denies that Vemex ever made such a request. Rustek refused to accept the Equipment from Vemex or pay the purchase price.

II.

On December 31, 2008, Vemex filed suit against TVI, asserting claims based on breach of contract, breach of express warranty, fraud, and unjust enrichment. In an April 19, 2011 order (the “Summary Judgement Order”), which was subsequently modified on May 16, 2011, the trial judge ruled on a number of the issues disputed by the parties. The court held that Vemex’s unjust enrichment, fraud, and breach of warranty claims were all barred by the statutes of limitations. Ve-mex does not contest the trial judge’s holding that it failed to bring its unjust enrichment claim within the two-year statute of limitations, but appeals the court’s holding that its fraud and breach of warranty claims were barred. With respect to Ve-mex’s breach of contract claim, the trial judge allowed the claim to go forward on the theory that, because the contract required TVI to both manufacture and install the Equipment, it might not have breached the contract until sometime between January and September of 2005, when it attempted to fulfill its Supervision obligations.

The trial judge held a bench trial from May 16, 2011 to May 19, 2011. On July 27, 2011, the trial judge issued her Findings of Fact and Conclusions of Law (the “Order”). Relevant to the instant appeal, the trial judge found the following facts:

• The Contract provided for separate payment amounts for the Equipment ($564,200.00) and TVTs Supervision services ($19,600.00). While Vemex paid the $562, 200.00 to TVI in two payments of $120, 00.00 and one payment of $324,200.00, it did not pay the $19,600.00 for the Supervision services. When TVI delivered the Equipment to the Port of Houston for shipment to Russia on August 31, 2004, the Equipment was “defective due to missing parts, poor quality parts, and parts that were not suitable for use in arctic conditions.”
*322 • Beginning in 2005, TVI spent several months supervising the installation of the Equipment in Siberia. During the installation process, Vemex discovered defects in the Equipment and notified TVI of the defects orally and in writing. TVI assured Vemex that it could cure the defects. Despite the defects, it was possible for TVI “to make the Equipment operational during the installation period.” TVI ceased its installation efforts in September of 2005, without making the Equipment operational. The reason the Equipment never became operational was that TVTs “employees lacked the knowledge and skills to cure the Equipment’s defects.”
• In the fall of 2005, Valentin Zhevlakov, the corporate representative of Ve-mex, spoke to Evgheniya Pashkevich, the director of TVTs Moscow office, and asked to return the Equipment for a refund. Pashkevich refused.
• The Equipment never became operational.

Based on these facts, the court found that Vemex’s breach of contract claim accrued in September 2005, when TVI “ended its attempts to cure the defects in the Equipment while the Equipment was being installed.” Accordingly, it held that Vemex brought its breach of contract claim within the four-year statute of limitations. The court found that TVI “breached the Contract with [Vemex] by tendering defective Equipment and failing to cure the Equipment’s defects during installation of the Equipment.” The court further found that although Vemex had initially accepted the Equipment, it had only done so on the reasonable assumption that TVI would cure the defects in the Equipment. The court also found that, after TVI ceased its efforts to fix the defects in the Equipment during the installation process, Vemex revoked its acceptance of the Equipment pursuant to Texas Business and Commercial Code § 2.608.

The court also found that although Ve-mex requested payment from Rustek, the company to which it had pre-sold the Equipment, Rustek never paid Vemex. Pursuant to Texas Business and Commercial Code § 2.711(a), which provides that a buyer who has justifiably revoked acceptance of goods may recover “so much of the price as has been paid,” the court awarded Vemex $564,200.00 in damages, the amount Vemex had paid to TVI under the Contract. The court refused Vemex’s request for an award of $729,750.00, the amount Rustek had agreed to pay Vemex, because Vemex had “not provided any evidence showing that $729,750.00 rather than $583,800.00 [the amount Vemex paid for the Equipment plus the $19,600.00 it did not pay for the Supervision] or some other price reflected the market price at the time that the buyer learned of the breach in September 2005.”

TVI appeals the trial judge’s finding that it breached the contract and the trial judge’s damages award. Vemex filed a cross-appeal, challenging the trial judge’s refusal to award incidental damages and its summary judgment holdings that Ve-mex’s fraud and breach of warranty claims were barred by the statutes of limitations. The district court had jurisdiction under 28 U.S.C. § 1332

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Minsa Corp. v. SFTC, LLC
540 S.W.3d 155 (Court of Appeals of Texas, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
563 F. App'x 318, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vemex-trading-corporation-v-technology-ventures-ca5-2014.