Vaughan v. Ford

127 N.W. 280, 162 Mich. 37, 1910 Mich. LEXIS 987
CourtMichigan Supreme Court
DecidedJuly 14, 1910
DocketDocket No. 7
StatusPublished
Cited by6 cases

This text of 127 N.W. 280 (Vaughan v. Ford) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vaughan v. Ford, 127 N.W. 280, 162 Mich. 37, 1910 Mich. LEXIS 987 (Mich. 1910).

Opinion

Blair, J.

Complainants filed the bill of complaint in this case to enforce a mechanic’s lien against the defendant Ford as owner, and the defendant Goddard as masonry contractor, for the erection of a certain office building known as the “Ford Building,” on the northwest corner of Congress and Griswold streets in the city of Detroit.

On the 18th day of September, 1906, Vaughan & Dumont and Goddard entered into a contract, portions of which we quote, as follows:

“Whereas, F. H. Goddard has taken a contract for the erection of a building on the northwest corner of Gris-wold aná. Congress streets, in the city of Detroit, Michigan, which contract includes the construction of forty-seven caissons according to plans and specifications of D. H. Burnham & Company, architects of said building; and,
“Whereas, J. C. Dumont and J. W. Vaughan have agreed to construct said caissons as subcontractors under said Goddard.
“ Now, therefore, it is agreed between said J. C. Dumont and J. W. Vaughan, as parties of the first part, and said F. H. Goddard, as party of the second part, as follows:
“ 1. Said J. C. Dumont and J. W. Vaughan shall construct said forty-seven caissons ready to receive the columns according to said plans and specifications within sixty days from the date of delivery of the rings hereinafter mentioned for the sum of sixty-nine thousand, eight hundred and sixty-seven dollars ($69,867). * * *
[39]*39“ 10, The foregoing agreement contemplates excavation to depth of one hundred and twenty feet. If the excavation is less than one hundred and twenty feet then there shall be a rebate to Goddard of the amount of such shortage at the rate of 36 -jVo- cents per cubic foot. If it becomes necessary to excavate below one hundred and twenty feet then for such extra excavation up to one hundred and thirty feet said Dumont and Vaughan shall be paid at the rate of 36 cents per cubic foot. For all work below one hundred and thirty feet the price shall-hereafter be agreed upon, which price shall not exceed exact cost.”

The specifications for foundations and masonry provided, among other things:

“The caissons are to be excavated to bedrock, for which purpose this contractor shall provide all necessary wood lagging, steel rings, bracings, etc. The bedrock exists on an average one hundred and twenty (120) feet beneath grade line. This contractor shall estimate on a basis of 120 feet below grade, and shall give a price per foot for additions to or deductions from this depth. * * *
“Caisson construction: This contractor shall build -caisson foundations as shown on both the engineering and architect’s drawings, digging to be thoroughly braced and protected until concrete piers are complete; jacks and drums to be used where necessary. Shafts to be kept straight and plumb and carried down to bedrock. This •contractor shall estimate on a basis of depth of 120 feet below grade line to bedrock and shall give a price per foot for additions to or deductions from this depth.”

Complainants entered upon and proceeded with the work of excavating the caissons, or wells, for the cement piers until October 20, 1906, when water and gas burst into one of the wells, which had reached a depth of over 120 feet, and the work was stopped by mutual consent. By mutual consent, a new plan was substituted for the original plan. By the new plan, which was satisfactorily executed by complainants, the concrete piers were to go down 95 feet instead of 120 feet, and were to be belled with three or four bells in each well.

October 9,1908, the owners of the Moffat building com[40]*40menced suit against all of the parties to this suit to recover damages for their alleged removal of lateral support. A lien is claimed in the claim of lien and in the bill for a balance of $39,879.01, with interest from February 18, 1907. The circuit court entered a decree granting a lien for the sum of $19,581.50, with interest, and appeals have been taken by both defendants. Complainants have not appealed.

Defendant Ford appeals upon the grounds:

“(1) Because the amount allowed is excessive; and
“(2) Because the claim as presented was excessive;
“(3) Because with the Moffat block suit pending, the court cannot determine whether or not there is any balance due from the owner to the principal contractor, Goddard.”

Defendant Goddard appeals upon the following grounds:

“1. The trial court erred in his findings in disallowing defendant Goddard’s claims against complainants.
“ 2. The court erred in allowing complainants’ claims for extras.”

With reference to the contract determining the rights, of the parties, the court determined that upon the happening of the accident—

“Both architects, contractor and subcontractor at that time felt that some changes under the existing circumstances would be desirable. At the end of the four or five days, the exact time matters not, the architects had brought forth the plans, which were subsequently followed in this case, whereby the support of the building was to rest upon piers in which there were three or more bells, I think, to each pier, or caisson, as it may be called, of concrete, and this plan was adopted in lieu, I think, of the original design which contemplated going through to solid rock. I am very certain that all parties at that, time recognized the impossibility for the contract price, or anything like the contract price, of the putting through of the caissons, if you may call them such, to the bedrock, and I am satisfied from the evidence that it was agreed between the parties at that time that the plan of belling, I think, as it is called, should be substituted in place of the original design of going through to bedrock. Now [41]*41under these circumstances there can he no question in my mind but what the basis of the payment for this contract should be the contract price. It is testified, I think, on behalf of both parties, of all parties, in fact, that it was represented, I think, to Vaughan and Dumont, at that time, that the contents of the bells and the concrete work to be done under the new plan was substantially the same a3 under the old, and I think they are entitled for any excess there may exist to claim as an extra the difference between the actual — what would have been required under the original plans — and the actual volume which they put into the piers or caissons and bells as completed.”

It is conceded that there was due from Goddard to complainants a balance of $15,685, and the controversy as to the amount of complainants’ claim concerns the following items, which defendants contend were either improperly allowed to complainants, or improperly charged against defendant Goddard, viz.:

(a) Extra concrete............................. $692 45
(b) Pumping water............................ 200 00
(c) Cantilevers................................ 1,010 94
(d) Melchers’ salary........................... 969 90
(e) Hughes’salary............................. 44 75

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vorrath v. Garrelts
192 N.W.2d 547 (Michigan Court of Appeals, 1971)
Clark v. City of Humansville, Missouri
348 S.W.2d 369 (Missouri Court of Appeals, 1961)
Rustuen v. Apro
243 P.2d 479 (Washington Supreme Court, 1952)
Hartsman v. Mueller
218 N.W. 854 (Wisconsin Supreme Court, 1928)
Ross v. Keaton Tire & Rubber Co.
206 P. 645 (California Court of Appeal, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
127 N.W. 280, 162 Mich. 37, 1910 Mich. LEXIS 987, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vaughan-v-ford-mich-1910.