Varco Pruden Buildings v. Scott Steel Erectors Inc.

CourtDistrict Court, W.D. Missouri
DecidedApril 19, 2022
Docket4:20-cv-00438
StatusUnknown

This text of Varco Pruden Buildings v. Scott Steel Erectors Inc. (Varco Pruden Buildings v. Scott Steel Erectors Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Varco Pruden Buildings v. Scott Steel Erectors Inc., (W.D. Mo. 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF MISSOURI WESTERN DIVISION

VARCO PRUDEN BUILDINGS, ) a division of BLUESCOPE BUILDINGS ) NORTH AMERICA, INC., ) ) Plaintiff, ) ) v. ) No. 4:20-CV-00438-DGK ) SCOTT STEEL ERECTORS INC, ) ) Defendant. )

ORDER GRANTING PLAINTIFF’S MOTION TO DISMISS DEFENDANT’S AMENDED COUNTERCLAIM

This case involves a dispute over payment for steel building materials used to construct an arena in Northern Canada. The Government of Yukon, Canada (“Yukon Government”) hired Scott Design Build (“SDB”) as its general contractor to construct an arena in Carmacks, Yukon. SDB in turn contracted with Defendant Scott Steel Erectors Inc. (“Scott Steel”) to erect a pre-engineered metal building as part of the arena project. Scott Steel then made a purchase order with Plaintiff Varco Buildings, a division of BlueScope Buildings North America, Inc. (“BBNA”), for the provision of engineering services and materials necessary to construct the metal building. BBNA filed a three-count lawsuit in this Court to recover the amount that Scott Steel still allegedly owes BBNA for the materials and services it provided to Scott Steel. After being granted leave to amend its answer, ECF No. 42, Scott Steel filed a counterclaim against BBNA for equitable indemnification. Now before the Court is BBNA’s motion to dismiss Scott Steel’s counterclaim. ECF No. 46. Because Scott Steel’s counterclaim fails both the ripeness and standing tests, the motion is GRANTED and the claim is DISMISSED WITHOUT PREJUDICE. Procedural History The Court starts with the procedural history as it lays the foundation for the counterclaim. On June 4, 2020, BBNA filed this three-count breach of contract lawsuit in this Court. Compl., ECF No. 1. Scott Steel answered. Answer, ECF No. 13.

While the case was percolating here, the underlying construction project hit roadblocks that eventually resulted in a separate lawsuit in Canada. On February 12, 2021, in a Yukon provincial court, the Yukon Government filed a lawsuit (“Yukon Lawsuit”) against SDB and its insurer Echelon Financial Holdings Inc. (“Echelon”) for damages related to the failed construction project, including approximately $10 million in damages from SDB and $7 million from Echelon. Neither Scott Steel nor BBNA are a party to that lawsuit.1 On April 13, 2021, SDB filed its answer and counterclaim against the Yukon Government. In that document, SDB alleges broadly that a combination of various design issues and changes, brutally cold weather, and COVID-19 restrictions all contributed to delay the project. SDB Counterclaim, ECF No. 39-1. As pertinent here, SDB specifically alleges that Scott Steel is an affiliated company of SDB, that Scott Steel

was the subcontractor tasked with constructing the pre-engineered arena building, that BBNA supplied the component parts for the pre-engineered building, that BBNA discovered a flaw in the design provided to it by one of the Yukon Government’s design firms, that BBNA worked with the firm to fix the design flaw, and that the design flaw led to a delay in BBNA delivering the materials to the construction site. Id. ¶¶ 3-11. Back here in Missouri, on July 23, 2021, Scott Steel moved to amend its answer to add the instant counterclaim for equitable indemnification and to stay the case pending the Yukon Lawsuit

1 Some allegations in Scott Steel’s counterclaim suggests—though do not state—that it is a party in the Yukon Lawsuit and could be found directly liable therein. That is not the case based on the Yukon Lawsuit pleadings attached to counterclaim; Scott Steel is not a party according to those documents. outcome. ECF No. 33, 34. The Court denied the motion to stay, but it granted the motion to amend. Order, ECF No. 42. The Court granted the motion to amend in part because BBNA had failed to show that amendment was futile. But the Court noted that the equitable indemnification claim “may not sufficiently state a claim under the governing law, may not be ripe for adjudication,

or may not even pass the Article III standing test.” Order at 8. In that same order, the Court allowed BBNA to file a motion to dismiss the counterclaim. Id. at 9. That motion is now ripe. Factual Background The following facts are from Scott Steel’s counterclaim as well as the documents embraced by it. Scott Steel is an authorized supplier and erector of pre-engineered buildings, while BBNA is a supplier of steel components for buildings. In October 2018, the Yukon Government contracted with SDB to construct an arena in Carmacks, Yukon. SDB then subcontracted with Scott Steel to build the arena’s steel shell, and Scott Steel in turn engaged BBNA to supply the primary and secondary steel components for the shell. BBNA told Scott Steel that the engineering, fabrication, and delivery of the steel components should be completed by early July 2019.

Scott Steel advised BBNA that delivery by July 2019 was critical because it needed to erect the shell before the beginning of the harsh Yukon winter. Despite BBNA’s representations that it could meet the deadline, the components did not begin to arrive until October 1–3, 2019. It took another two weeks for all the critical components to arrive and, even then, Scott Steel had to source several steel components that BBNA had failed to provide or mis-fabricated. Scott Steel did not begin building the shell until October 19, 2019. Due to BBNA’s delays and errors, Scott Steel was not able to construct the arena’s shell, enclose it, and apply heat before the beginning of winter. Temperatures plunged to -50 degrees Celsius in January 2020, putting all the worksite equipment out of commission and halting all work on the project until the weather improved. But work did not resume until August 2020 due in part to the COVID-19 pandemic. In August 2020, the Yukon Government issued a notice of default to SDB and then, in December 2020, the Yukon Government terminated its contract with SDB. In the count pleading section, Scott Steel clearly defines the nature of its claim. In relevant

part, Scott Steel alleges: 20. As set forth above, SDB and Scott Steel deny that the Government of Yukon is entitled to the relief it seeks in its action filed with the Supreme Court of Yukon (SC No. 20- A0129). However, if it is ultimately determined that the Government of Yukon is entitled to damages against SDB, Echelon Financial Holdings Inc., and/or Scott Steel, any award of damages entered in favor of the Government of Yukon constitutes a payment obligation due by BBNA to the Government of Yukon. 21. An award of damages entered against and paid by SDB, Echelon Financial Holdings Inc., and/or Scott Steel constitutes a discharge of that payment obligation of BBNA to the Government of Yukon. 22. BBNA would be unjustly enriched if SDB, Echelon Financial Holdings Inc, and/or Scott Steel discharged a payment obligation of BBNA to the Government of Yukon. 23. BBNA has improperly denied and is refusing its responsibility to indemnify Scott Steel for any amounts that may be required to be paid by Scott Steel. 24. Because BBNA is refusing to hold harmless and indemnify Scott Steel for any judgment that may be ultimately entered in Scott Steel’s favor in this case, Scott Steel has had to incur attorneys’ fees and costs in defending against the Government of Yukon’s claims and in bringing this action for indemnity.

First Amended Counterclaim ¶¶ 20-24, ECF No. 43 (emphasis added). Its prayer for relief makes clear that Scott Steel is entitled to relief “in the event that an award or judgment in favor of the Government is Yukon is entered against Scott Design Build Inc., or if Scott Design Build Inc., Echelon Financial Holdings, Inc., and/or Scott Steel Erectors Inc. is otherwise required to pay moneys to the Government of Yukon.” Id. (emphasis added).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Texas v. United States
523 U.S. 296 (Supreme Court, 1998)
Mills v. City of Grand Forks
614 F.3d 495 (Eighth Circuit, 2010)
OUTDOOR CENTRAL, INC. v. GreatLodge. Com, Inc.
643 F.3d 1115 (Eighth Circuit, 2011)
Kennedy v. Ferguson
679 F.3d 998 (Eighth Circuit, 2012)
Giandinoto v. CHEMIR ANALYTICAL SERVICES
545 F. Supp. 2d 952 (E.D. Missouri, 2007)
Beeler v. Martin
306 S.W.3d 108 (Missouri Court of Appeals, 2010)
Hartford Acc. and Indem. v. Doe Run Resources
663 F. Supp. 2d 771 (E.D. Missouri, 2009)
Jennifer Parrish v. Governor Mark Dayton
761 F.3d 873 (Eighth Circuit, 2014)
Melissa Alleruzzo v. SuperValu, Inc.
870 F.3d 763 (Eighth Circuit, 2017)
United States v. Lashone Gates
915 F.3d 561 (Eighth Circuit, 2019)
Janice Duffner v. City of St. Peters, Missouri
930 F.3d 973 (Eighth Circuit, 2019)
Dwight Mitchell v. Dakota County Social Services
959 F.3d 887 (Eighth Circuit, 2020)
Tom Yeransian v. B. Riley & Co., LLC
984 F.3d 633 (Eighth Circuit, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
Varco Pruden Buildings v. Scott Steel Erectors Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/varco-pruden-buildings-v-scott-steel-erectors-inc-mowd-2022.