Varco Pruden Buildings v. Scott Steel Erectors Inc.

District Court, W.D. Missouri·Decided November 16, 2021·No. 4:20-cv-00438·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF MISSOURI WESTERN DIVISION

VARCO PRUDEN BUILDINGS, ) a division of BLUESCOPE BUILDINGS ) NORTH AMERICA, INC., ) ) Plaintiff, ) ) v. ) No. 4:20-CV-00438-DGK ) SCOTT STEEL ERECTORS INC, ) ) Defendant. )

ORDER ON MOTIONS TO AMEND AND MOTION TO STAY

This case involves a dispute over payment for steel building materials used in the construction of a hockey arena in Northern Canada. The Yukon Government hired Scott Design Build (“SDB”) as its general contractor to construct a hockey arena in Carmacks, Yukon. SBD in turn contracted with Defendant Scott Steel Erectors Inc. (“Scott Steel”) to erect a pre-engineered metal building as part of the arena project. Scott Steel then made a purchase order with Plaintiff Varco Buildings, a division of BlueScope Buildings North America, Inc. (“BBNA”), for the provision of engineering services and materials necessary to construct the metal building. BBNA filed a three-count lawsuit in this Court to recover the amount that Scott Steel still allegedly owes BBNA for the materials and services it provided to Scott Steel. Now before the Court are Scott Steel’s Second Motion for Leave to Amend its Answer (ECF No. 33), Motion to Stay the Case (ECF No. 34), and Motion to Amend the Scheduling Order (ECF No. 35). For the reasons stated below, the Court GRANTS the Second Motion for Leave to Amend its Answer, DENIES the Motion to Stay the Case, and DENIES AS MOOT the Motion to Amend the Scheduling Order. Scott Steel shall file its amended answer within two business days of this order. As outlined below, the Court finds that BBNA has not proven that the amendment is futile on the current record, but it should be given the opportunity to test the pleading via a motion to dismiss. Therefore, to the extent BBNA wishes to move to dismiss the counterclaim, the parties shall adhere

to the following schedule: (1) BBNA shall file any motion to dismiss on or before December 7, 2021; (2) Scott Steel shall file its opposition on or before December 21, 2021; and (3) BBNA shall file its reply, if any, by January 4, 2022. The Court will issue a revised case schedule via a separate order. Procedural Background On June 4, 2020, BBNA filed this three-count breach of contract lawsuit to recover the amounts Scott Steel allegedly owes BBNA for the building materials it constructed and provided to Scott Steel. ECF No. 1. Scott Steel answered. ECF No. 13. The Court then entered a scheduling order, which set the date to amend pleadings as November 4, 2020. ECF No. 19. On that date, Scott Steel moved for leave to amend its answer to raise a permissive counterclaim against BBNA.

ECF No. 20. The Court granted Scott Steel’s motion. ECF No. 21. On December 22, 2020, the Court amended the scheduling order at the parties’ request to extend the discovery deadline to December 2, 2021. ECF No. 26. The parties then unsuccessfully tried to resolve the dispute via a mediation in March 2021. The failed mediation led to BBNA moving to dismiss Scott Steel’s counterclaim, ECF No. 27, and moving to amend the scheduling order to specify that a party with the burden of proof had to file its expert designations by August 3, 2021, while a party without the burden of proof was required to file its expert designations by October 5, 2021, ECF No. 29. On April 14, 2021, the Court granted BBNA’s motion to amend the scheduling order. ECF No. 30. Later that same day, Scott Steel dismissed its counterclaims rather than respond to the motion to dismiss. ECF No. 31. While the case was percolating here, the underlying construction project in Canada ran into various snags that resulted in a separate lawsuit. The Yukon Government issued notices of default

to SDB in August and November 2020 and officially terminated SBD as general contractor in December 2020. On February 12, 2021, the Yukon Government filed a lawsuit (“Yukon Lawsuit”) against SBD and its insurer Echelon Financial Holdings Inc. for damages related to the failed construction project, including approximately $10 million in damages from SDB and $7 million from Echelon. Neither Scott Steel nor BBNA are a party to that lawsuit.1 On April 13, 2021, SBD filed its answer and counterclaim against the Yukon Government. In that document, SBD alleges broadly that a combination of various design issues and changes, brutally cold weather, and COVID-19 restrictions all contributed to delay the project. ECF No. 39-1. As pertinent here, SBD specifically alleges that Scott Steel is an affiliated company of SBD, that Scott Steel was the subcontractor tasked with constructing the pre-engineered arena building, that BBNA supplied the

component parts for the pre-engineered building, that BBNA discovered a flaw in the design provided to it by one of the Yukon Government’s design firms, that BBNA worked with the firm to fix the design flaw, and that the design flaw led to a delay in BBNA delivering the materials to the construction site. Id. ¶¶ 3-11. Back here in Missouri, on July 23, 2021, Scott Steel filed the instant motion to amend its answer to add a counterclaim allegedly based on the occurrences in the Yukon Lawsuit. ECF No. 33, 34. Scott Steel’s proposed amended answer includes a counterclaim for “equitable

1 Some allegations in Scott Steel’s proposed counterclaim suggests—though do not state—that it is a party in the Yukon Lawsuit and could be found directly liable therein. That does not appear to be the case based on the pleadings submitted from that lawsuit. As best the Court can tell, Scott Steel is not a party. So unless it has been added recently, the only liability it could incur appears to be derivative, downstream liability after that case concludes. indemnification” against BBNA for its alleged delay in delivering the materials to Scott Steel that in turn led to delays in the project. ECF No. 33-1. According to Scott Steel, these alleged delays contributed to the Yukon Government cancelling its contract with SBD and suing it. Id. And if SBD, Echelon, and/or Scott Steel are held liable in that action, then equity demands that BBNA

should indemnify Scott Steel. See id. at 14. Contemporaneous with this motion, Scott Steel also moved to stay this action pending the resolution of the Yukon Lawsuit, ECF No. 34, and it also moved to amend the expert designation descriptions in the scheduling order, ECF No. 35. These motions are now ripe for ruling. Standard Both Scott Steel’s motion to amend its answer as well as its motion to amend the scheduling order must satisfy Federal Rule of Civil Procedure 16(b)(4). See Sherman v. Winco Fireworks, Inc., 532 F.3d 709, 716 (8th Cir. 2008) (holding that motion to amend pleadings after the scheduling deadline to amend has passed must satisfy Rule 16(b)(4)); see also Fed. R. Civ. P. 16(b)(4). To accomplish this, Scott Steel must establish “good cause.” See Sherman, 532 F.3d at

716. As for its motion to amend its answer, Scott Steel must also establish that the proposed amendment is proper under Rule 15(a). See Fed. Trade Comm’n v. Next-Gen, Inc., No. 4:18-cv- 00128-DGK, 2018 WL 5310416, at *3 (W.D. Mo. Sept. 24, 2018). Rule 15(a)(2) broadly provides that “[t]he court should freely give leave [to amend] when justice so requires.” As for Scott Steel’s motion to stay, “the district court ha[s] the inherent power to grant [a] stay in order to control its docket, conserve judicial resources, and provide for a just determination of the case[] pending before it.” Contracting Nw, Inc. v. City of Fredericksburg, 713 F.2d 382, 387 (8th Cir. 1983).

Free access — add to your briefcase to read the full text and ask questions with AI

Varco Pruden Buildings v. Scott Steel Erectors Inc., (W.D. Mo. 2021).

Varco Pruden Buildings v. Scott Steel Erectors Inc. (Varco Pruden Buildings v. Scott Steel Erectors Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Landis v. North American Co.
299 U.S. 248 (Supreme Court, 1936)
Nken v. Holder
556 U.S. 418 (Supreme Court, 2009)
Douglas Reuter v. Jax Ltd., Inc.
711 F.3d 918 (Eighth Circuit, 2013)
Sherman v. Winco Fireworks, Inc.
532 F.3d 709 (Eighth Circuit, 2008)
Lockyer v. Mirant Corp.
398 F.3d 1098 (Ninth Circuit, 2005)
Robert Ellingsworth v. Vermeer Manufacturing Company
949 F.3d 1097 (Eighth Circuit, 2020)