RE,NDERED: MARCH 22, 2018 TO BE PUBLISHED
cSuprmut filnurl ·nf IftfFlf}ftlaj] ~ [L 2016-SC-000666-DG IQ)~11 ~'f}12/Jg ~IM ~IM"t1 ,De VANHOOK ENTERPRISES, INC. APPELLANT
ON REVIEW FROM COURT OF APPEALS v. CASE NO.- 2015-CA-001977-MR PULASKI CIRCUIT COURT NO. 1~-CI-.00922
KAY & KAY CONTRACTING, LLC APPELLEE
OPINION OF THE COURT BY JUSTICE CUNNINGHAM
REVERSING AND REINSTATIN.G
The United States Small Business Administra,tion ("SBA") regulates the
Historically Underutilized Business Zone ("HUBZone") Program. 15 U.S.C. §
657a. Through the HUBZone program, the SBA provides contracting
assistance to small businesses seeking federal government contracts. To
qualify as a HUBZone-eligible contractor, one must be a small business within
an economically distressed area. Id.
In 2010, the U.S. Army Corps of Engineers sought bids from HUBZone-
eligible contractors to replace the Cumberland Bridge Street Bridge over the
Poor Fork of the Cumberland River in Cumberland, Kentucky. The HUBZone
contract price was $1,029,394.20 .. Kay & Kay Contracting, LLC ("Kay & Kay"), a large construction firm in London, was ~nterested in the construction job, but
was not a HUBZone-:eligible business.
Accordingly, Kay & Kay negotiated with Vanhook Enterprises, Inc.
("Vanhook"), a HµBZone-eligible contractor in Somerset, and entered into a
series of agreements with Vanhook whereby Vanhook would apply for the
HUBZone: contract. Vanhook would receive th~ HUBZone contract pripe from
the federal government, which it would then split with Kay & Kay as a
subcontractor working on the HUBZone project. On July 7, 2010, this
. relationship culminated in the so-called Team Agreement between the parties,
whereby Vanhook.agreed to serve as the prime contractor for the HUBZone . ' contract. \
On January 13, 2011, Vanhook and Kay & Kay entered into the so-called
Subcontract Agreement, .which outlined services that Kay & Kay was to perform
as a ~ubcontractor under the HUBZone project. The Subcontract Agreement
stated that Vanhool,c would pay Kay & Kay $37,500 for ."Mobilization" and . a $410,000 lump sum for "All Materials, Labor, Equipment[,] and applicable
truces for the construction of the Bridge Str~et Bridge."
Later in 2011, during construction, the parties entered into a subsequent
. written agreement whereby Vanhook rented equipment and an equipment
operator from Kay & Kay for an additional $12,300. This agreement was
expressly excluded from the Subcontract Agreement. See Subcontract
}\greement, Exhibit A ("The lump-:sum item shall include all costs associated
2 with the construction of the bridge that are -not othenvise identified as being
paid separately." (emphasis added)).
After completion of the bridge, Vanhook remitted an undisputed
$459,790.04 to Kay & Kay under.the Subcontract Agreement and subsequent
written a~reement: $37,500 for "Mobilization," the $410,000 lump sum, and
$12,300 for the additional equipment rental and operator contract. On
December 8, 2011, Kay & Kay Vice President Ron Pfaff executed a writing titled
"Affidavit and Waiver of Lien, Acknowledgement of Full and Final Payment."
Therein, Pfaff swore that Kay & Kay had been fully compensated for materials
provided and ser\rices performed under the Subcontract Agreement by "full and
final payment due including any applicable retainage." However, despite its
letter, Kay & Kay continued to ·seek additional payment from Vanhook.
In the summer of 2013, Kay & Kay sued Vanhook for breach of contract
and quantum_meruit in the alternative, asserting that the parties had entered·
into a separate agreement after the Team Agreement, but before the
Subcontract Agreement-the so-called Prime Agreement ... Under that alleged - - agreement, Kay & Kay claimed that Vanhook was obligated to pay greater than
the lump-sum· price. Kay & Kay claimed it performed 76% of total work under
the 43~bid item project-$785,814.16 of the $1,029,394.20 HUBZone contract
price-and, th1:1s~ performed $~26,024.12 worth of work outside of the
Subcontract Agreement's contract price. Kay & Kay maintained that the i expenses it incurred in excess of the $410,000 lump sum were for services it
performed outside of the scope of the Subcontract Agreement, and thereby
3 \
unjustly enriched Vanhook by rendering those services without adequate
, compensation.
Vanhook responded that no such Prime Agreement existed, and, even if it
did, that the- Subcontract Agreement superseded aH prior agreements and
. negotiations be~een the parties. Therefore, Vanhook moved for judgment on
the pleadings. CR 12.03. The Pulaski Circuit Court found the Subcontract
. 1 A~eement to-be a complete integration of the dealings between Vanhook and
Kay & Kay regarding the ~ridge Street Bridge project. Accordingly, the Pulaski· (
Circuit Court held that the alleged "additional work" was included within a ,/
plain, ordinary reading of Exhibit A of the Subcontract Agreement as "any 9ther
ancillary items required to provide _a complete bridge structure."
On appeal, the Kentucky Court of Appeals affirmed the trial court's
finding that the Subcoritract Agreement was an integration. H9wever, the
Court of Appeals held that it was unclear whether Kay &·Kay's "additional
work" fell within the "any other ancillary items" language of the contract. In )
other words, it was unc_lear whether the Subcontract Agreement was a full
integration or a partial integration. The Court of Appeals declared that whether
the "additional work" Kay & Kay allegedly performed was covered by the
Subcontract Agreement was an issue of fact for the jury. Vanhook appealed to
this Court, .and we granted discretionary review.
Analysis
Interpretation of a written contract is a matter of law to be decided by the
trial court. 3D Enters. Contracting Corp. v. Louisville & Jefferson Cnty. Metro. '.
4 Sewer Dist., 174 S.W.3d 440, 448 (Ky. 2005). The Pulaski Circuit Court·
granted Vanhook's motion for judgment on the pleadings, which "should be
granted if it appears beyond doubt that the nonmoving party cannot prove any
set of facts that would entitle [that party] to relief." Schultz v. Gen. Elec.
Healthcare Fin. Svcs., Inc., 360 S.W.3d 171, 176 (Ky. 2012) (internal citation ' omitted). A motion for judgment on the pleadings is treated akin to a motion . r '
"for summary judgment[,] and [is] disposed of in that manner."· Hoke v .
.Cullinan, 914 S.W.2d 335, 338 (Ky. 1995).
_"Appellate review of a summary judgment involves only legal questions
and a ·determination of whether a disputed material issue of fact exists, So we ·
operate under a de novo standard of review with no need to defer to the trial
c~ilrt's decisiOn." Shelton v. Kentucky Easter Seals Soc'y, Inc., 413 S.W.3d 901,
905 (Ky: 20.13) Jinternal citations omitted). "The interpretation of a contract, ·
including determining whether a contract is ambiguous, is a question of law to
Free access — add to your briefcase to read the full text and ask questions with AI
RE,NDERED: MARCH 22, 2018 TO BE PUBLISHED
cSuprmut filnurl ·nf IftfFlf}ftlaj] ~ [L 2016-SC-000666-DG IQ)~11 ~'f}12/Jg ~IM ~IM"t1 ,De VANHOOK ENTERPRISES, INC. APPELLANT
ON REVIEW FROM COURT OF APPEALS v. CASE NO.- 2015-CA-001977-MR PULASKI CIRCUIT COURT NO. 1~-CI-.00922
KAY & KAY CONTRACTING, LLC APPELLEE
OPINION OF THE COURT BY JUSTICE CUNNINGHAM
REVERSING AND REINSTATIN.G
The United States Small Business Administra,tion ("SBA") regulates the
Historically Underutilized Business Zone ("HUBZone") Program. 15 U.S.C. §
657a. Through the HUBZone program, the SBA provides contracting
assistance to small businesses seeking federal government contracts. To
qualify as a HUBZone-eligible contractor, one must be a small business within
an economically distressed area. Id.
In 2010, the U.S. Army Corps of Engineers sought bids from HUBZone-
eligible contractors to replace the Cumberland Bridge Street Bridge over the
Poor Fork of the Cumberland River in Cumberland, Kentucky. The HUBZone
contract price was $1,029,394.20 .. Kay & Kay Contracting, LLC ("Kay & Kay"), a large construction firm in London, was ~nterested in the construction job, but
was not a HUBZone-:eligible business.
Accordingly, Kay & Kay negotiated with Vanhook Enterprises, Inc.
("Vanhook"), a HµBZone-eligible contractor in Somerset, and entered into a
series of agreements with Vanhook whereby Vanhook would apply for the
HUBZone: contract. Vanhook would receive th~ HUBZone contract pripe from
the federal government, which it would then split with Kay & Kay as a
subcontractor working on the HUBZone project. On July 7, 2010, this
. relationship culminated in the so-called Team Agreement between the parties,
whereby Vanhook.agreed to serve as the prime contractor for the HUBZone . ' contract. \
On January 13, 2011, Vanhook and Kay & Kay entered into the so-called
Subcontract Agreement, .which outlined services that Kay & Kay was to perform
as a ~ubcontractor under the HUBZone project. The Subcontract Agreement
stated that Vanhool,c would pay Kay & Kay $37,500 for ."Mobilization" and . a $410,000 lump sum for "All Materials, Labor, Equipment[,] and applicable
truces for the construction of the Bridge Str~et Bridge."
Later in 2011, during construction, the parties entered into a subsequent
. written agreement whereby Vanhook rented equipment and an equipment
operator from Kay & Kay for an additional $12,300. This agreement was
expressly excluded from the Subcontract Agreement. See Subcontract
}\greement, Exhibit A ("The lump-:sum item shall include all costs associated
2 with the construction of the bridge that are -not othenvise identified as being
paid separately." (emphasis added)).
After completion of the bridge, Vanhook remitted an undisputed
$459,790.04 to Kay & Kay under.the Subcontract Agreement and subsequent
written a~reement: $37,500 for "Mobilization," the $410,000 lump sum, and
$12,300 for the additional equipment rental and operator contract. On
December 8, 2011, Kay & Kay Vice President Ron Pfaff executed a writing titled
"Affidavit and Waiver of Lien, Acknowledgement of Full and Final Payment."
Therein, Pfaff swore that Kay & Kay had been fully compensated for materials
provided and ser\rices performed under the Subcontract Agreement by "full and
final payment due including any applicable retainage." However, despite its
letter, Kay & Kay continued to ·seek additional payment from Vanhook.
In the summer of 2013, Kay & Kay sued Vanhook for breach of contract
and quantum_meruit in the alternative, asserting that the parties had entered·
into a separate agreement after the Team Agreement, but before the
Subcontract Agreement-the so-called Prime Agreement ... Under that alleged - - agreement, Kay & Kay claimed that Vanhook was obligated to pay greater than
the lump-sum· price. Kay & Kay claimed it performed 76% of total work under
the 43~bid item project-$785,814.16 of the $1,029,394.20 HUBZone contract
price-and, th1:1s~ performed $~26,024.12 worth of work outside of the
Subcontract Agreement's contract price. Kay & Kay maintained that the i expenses it incurred in excess of the $410,000 lump sum were for services it
performed outside of the scope of the Subcontract Agreement, and thereby
3 \
unjustly enriched Vanhook by rendering those services without adequate
, compensation.
Vanhook responded that no such Prime Agreement existed, and, even if it
did, that the- Subcontract Agreement superseded aH prior agreements and
. negotiations be~een the parties. Therefore, Vanhook moved for judgment on
the pleadings. CR 12.03. The Pulaski Circuit Court found the Subcontract
. 1 A~eement to-be a complete integration of the dealings between Vanhook and
Kay & Kay regarding the ~ridge Street Bridge project. Accordingly, the Pulaski· (
Circuit Court held that the alleged "additional work" was included within a ,/
plain, ordinary reading of Exhibit A of the Subcontract Agreement as "any 9ther
ancillary items required to provide _a complete bridge structure."
On appeal, the Kentucky Court of Appeals affirmed the trial court's
finding that the Subcoritract Agreement was an integration. H9wever, the
Court of Appeals held that it was unclear whether Kay &·Kay's "additional
work" fell within the "any other ancillary items" language of the contract. In )
other words, it was unc_lear whether the Subcontract Agreement was a full
integration or a partial integration. The Court of Appeals declared that whether
the "additional work" Kay & Kay allegedly performed was covered by the
Subcontract Agreement was an issue of fact for the jury. Vanhook appealed to
this Court, .and we granted discretionary review.
Analysis
Interpretation of a written contract is a matter of law to be decided by the
trial court. 3D Enters. Contracting Corp. v. Louisville & Jefferson Cnty. Metro. '.
4 Sewer Dist., 174 S.W.3d 440, 448 (Ky. 2005). The Pulaski Circuit Court·
granted Vanhook's motion for judgment on the pleadings, which "should be
granted if it appears beyond doubt that the nonmoving party cannot prove any
set of facts that would entitle [that party] to relief." Schultz v. Gen. Elec.
Healthcare Fin. Svcs., Inc., 360 S.W.3d 171, 176 (Ky. 2012) (internal citation ' omitted). A motion for judgment on the pleadings is treated akin to a motion . r '
"for summary judgment[,] and [is] disposed of in that manner."· Hoke v .
.Cullinan, 914 S.W.2d 335, 338 (Ky. 1995).
_"Appellate review of a summary judgment involves only legal questions
and a ·determination of whether a disputed material issue of fact exists, So we ·
operate under a de novo standard of review with no need to defer to the trial
c~ilrt's decisiOn." Shelton v. Kentucky Easter Seals Soc'y, Inc., 413 S.W.3d 901,
905 (Ky: 20.13) Jinternal citations omitted). "The interpretation of a contract, ·
including determining whether a contract is ambiguous, is a question of law to
be determined de novo on appellate review." Kentucky Shakespeare Festival,
Inc. v. Dunaway; 490 S.W.3d 691, 695 (Ky .. 2016) (internal citation omitted).
Parol Evidence Rule
·Within contract law, the parol evidence rule is a substantive rule that
regulate.s the admissibility of written or oral evidence introduced to vary a
written contract. Under the parol evidence rule, an unambiguous writing )
intended by the parties to be a full .and final manifestation of their agreement
cannot be supplemented, contradicted, or modified by evidence of prior written
5 or oral agreements. Childers & Venters, Inc. v. SC?wards, 460 S.W-:2d 343, 345 -'
(Ky. 1970).
Initially, we must determine whether the writing constituted a final
expression. of the agreement between the parties at the time it was adopted.
First, we ask whether the contested writing was intended to be the final
manifestation of their agreement, a preliminary draft, or merely a step in
negotiations like a letter of intent? And, if a m~ifestation of intent exists, was
it a complete integration of th~ entire deal or only a partial integration?
As a matter of law, a document which on its face appears to be a
complete integration is a complete integration. See, e.g., Kentucky
Shakespeare Festival, 490 S.W.3d at 695 (quoting 3D Enters.' Contracting Corp.,
174 S.W.3d at 448) ("When no ambiguity exists in the contract, we look only as
far as the four corners of the document to determine the parties' intentions.").
Here, the merger clause at Paragraph XXV of the Subcontract Agreement
categorically states that the parties intended the Subcontract Agreement to
"represent[] the entire and integrated agreement between the Contractor and
Subcontractor and supercedes [sic] all prior negotiations, representations, or
agreements, either written or oral ..... " (emphasis added).
· Kay & Kay contends that the Subcontract Agreement was only a partial
· integration as to Mobilization and· Bridge Street Bridge Construction-bid items
1 and 10 of the 43-item bid list from the Army Corps of Engineers-and that
the other work it provided was outside of the scope of those two items.
However, contrary to Kay & Kay's argument, Paragraph III of the Subcontract Agreement states that the Su~contract includes, among other documents: the
Subcontract Agreement; the prime contract between Vanhook and the Army ' .
Corps of Engineers; and any other documents specifically incorporate.d by
reference. Thus, by its own terms, the Subcontract Agreement is a full
integration of Vanhook and Kay & Kay's contract for Kay & Kay's
subc01;1tracting work on the Bridge Street Bridge .. . . Because the merger clause states that the parties intended the
Subcontract Agreement to be a complete integration, to embody the "entire
integrated agreement" between Vanhook and Kay & Kay which supersedes all
· .prior agreements, _any evidence of a prior written or oral agreement is
inadmissible to vary its terms. Therefore, the, trial court properly found'that
any evidence of the alleged Prime Agreement was inadmissible to vary the
Subcontract Agreement's terms .
.Quantum M'eruit
Where there is no valid contract, an action for quantum meruit may
provide the aggrieved party the equitable remedy of restitution. Restitution is
intended to return the value of the benefit conferred to the aggrieved party
when the other party is unjustly enriched at the expense of the aggrieved. l . .
Hughes & Coleman, PLLC v. Chambers, 526 S..W.3d 70, 74-75 (Ky. 2017).
Here, the Subcontract Agreement incorporated the prime contract
between Vanhook and the Army Corps of Engineers by reference in Paragraph
III B. The prime contract included a list of 43 bid items for goods and services
under the HUBZone contract that Vanhook promised to provide or perform.
7 Exhibit A of the Subcontract Agreer,nent specifically addressed t:Wo of those bid
items that Vanhook subcontracted to Kay & Kay: mobiliza~ibn and co:r;istruction ' of the Bridge Street Bridge. Most notably, the bridge construction item
includes a catch-all which states that Kay & Kay is to perform "any other
ancillary items required to provide a complete bridge structure."
Kay & Kay argues it is entitled to restitution. for the costs it incurred
above the Subcontract Agreement's contract price, because Kay & Kay
performed more than just bid items 1 and 10 to provide the complete bridge
structure. However, that argument is contrary to the plain meaning of the
Subcontract Agreement. As Kay & K~.y. has stated, it seeks restitution for the
excess costs it incurred in building the bridge. Those costs fall within the
terms of the contract as "any other ancillary item [of the 43-item list] required"
. to finish the bridge, and "a written instrument will be strictly enforced
according to its terms." Mounts v. Roberts,, 388 S.W.2d 117, 119 (Ky. 1965).
· Thus, the Subcontract Agreeme~t covers the subject matter of the alleged
"additional work" performed by Kay & Kay. Consequently, the Prime
Agreement, if it existed ~t all, was merely a chain in the negotiations that led to
the final manifestation of the deal embodied in the Subcontract Agreement. A
valid written contract exists for construction of the Bridge Street Bridge, and
"there can be no implied coritract or presumed agreement where there is an
express one between the parties in reference to the same subject matter." Fruit
Growers Express Co. v. Citizens Ice & Fuel Co., 112 S.W.2d 54, 56 (Ky. 1937).
Therefore, Kay & Kay is not entitled to relief under a quantum meruit theory.
8 Conclusion
For the forgoing r~asons, we hereby reverse the Court of Appeals and
reinstate the Pulaski Circuit Court's judgment consistent with this opinion.
All sitting. Hughes, Keller, Venters, and Wright, JJ., concur. Minton,
C.J., concurs by separate opinion in which VanMeter, J.,joins.
MINTON, C.J., CONCURRING: The majorit)'.' provides a well-written
con~ract-law analysis of the issues presented in this case, with which I fully
concur. But I write separately to emphasize that this case can be decided on a
principle that this state has rec~gnized for almost 100 years, "that any conduct
or contract of an illegal, vicious, or immoral nature cannot be the basis of a
legal or equitable proceeding .... "1
As the majority recognizes, the contract between Vanhook and Kay & Kay
is subject to the rules and regulations of the HUBZone Program. Two I
regulations, 13 C.F.R. § 126~700 and 13 C.F.R. § 125.6, are of particular
relevance in this case.2
i Robenson v. Yann, 5 S.W.2d 271, 274 (Ky. 1928); see also McMullen v. Hoffman, 174 U.S. 639, 662 (1899) ("It is no part of a court of justice to aid either in carrying out an illegal contract, or in dividing the proceeds arising from an illegal contract between the ·parties to that illega!_contract. "). 2 We note that, as the majority points out, the written agreements between the parties arose between 2010 and 2011, so we located the particular versions of these regulations applicable to this case. When we refer to these regulations, we are referring to the version of 13 C.F.R. § 126. 700 promulgated on June 17, 2005, and taking effect on August 30, 2005, and of 13 C.F.R. § 125.6 promulgated on October 1, 2008, and taking effect on October 31, 2008.13 C.F.R. § 126.700, 70 FR 51243-01, 2005 WL 2071548 (August 30, 2005); 13 C.F.R. § 125.6, 73 FR 56940-01, 2008 WL. 4410591 (October 31, 2008). For the language of relevance regarding 13 C.F.R. § 125.6, see 69 FR 29411-01, 2004 WL 1143809 (June 23, 2004).
9 /
The applicable version of 13 C.F.R. § 126.700, promulgated under the
authority given by Congress to the Small Business Administration under 15 l
U.S.C. § 657a, is entitled "What are the performance of work requirements for.
HUBZone contracts?" 13 C.F.R. § 126.700(a) states, "A prime contractor .
rec:;eiving an award as a qualified HUBZone SBC must meet the performance of
work requirements set forth in§ ·12s·.6 of this chapter." 13 C.F.R. § 125.6, in ' turn; is entitled, "Prime contractor performance requirements (limitations on
subcontracting)." A list of threshold cost percentages that a subcontractor can
receive and not violate HUBZone law appears in 13 C.F.R. 125.6(c).· And 1"3
C.F.R. 126.700(b) provides a list of those threshold cost percentages.
We do rtot know exactly how the facts of this case square with these
federal rules and regulations. But both parties concede that if the parties drew .. the contract to provide Kay & Kay with the money it assert~ in its quantum
meruit claim today, it would violate federal law, i.e. the HUBZone statutes and
regulations, which provide certain· contract amounts that a non-HUBZone-
·qualifying subcontractor can contract for without violation. Even if the parties
did not concede this point, their actions speak for themselves.
Kay & Kay and Vanhook framed their relationship in this case so as ~ot
to violate federal law-their Team Agree±nent was drawn up to avoid such an \
issue. Nqw, Kay & Kay assert_s that Vanhook owes it more money, the giving of
which would fly in the face of their constructed relationship because it would
allow Kay & Kay to do the very thing federal law prevents-awarding a non-
HUBZone-qualifying entity more of the contract price than federal law allows.
10 .,
Kay & Kay attempts to justify its position by asserting its claim under a _
_quantum~meruit theory instead of a breach-of-contract theory, positing that
rec~iving money under a quantum-mer'uit theory would not violate federal law
. because receipt of this money arose from equity rather than contract ~aw. The
fact that Kay & Kay did not pursue a breach-of-contract claim essentially . . I
amounts to an admission that it cannot pursue a breach-of-contract claim in '\ this case because such claim would acknowledge that an illegal contract exists,
meaning a contract that awards Kay & Kay more money than w~at federal law
allows.
Equity cannot be a vehicle to make illegal conduct legal. Kay & Kay
cannot pursue a quantum-meruit claim to recover damages, the receipt of
which would violate the law. ·
Because Kay & Kay is attempting to recover damages, the receipt of
which would violate federal law, I would reverse the Court of Appeals and
reinstate the trial court's decision.
VanMeter, J., joins.
COUNSEL FOR APPELLANT:
Larry F. Sword SWORD & BROYLES
COUNSEL FORAPPELLEE:
Darren J. Dueyk
\