Vanhook Enterprises, Inc. v. Kay & Kay Contracting, LLC

CourtKentucky Supreme Court
DecidedApril 11, 2018
Docket2016-SC-0666
StatusPublished

This text of Vanhook Enterprises, Inc. v. Kay & Kay Contracting, LLC (Vanhook Enterprises, Inc. v. Kay & Kay Contracting, LLC) is published on Counsel Stack Legal Research, covering Kentucky Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vanhook Enterprises, Inc. v. Kay & Kay Contracting, LLC, (Ky. 2018).

Opinion

RE,NDERED: MARCH 22, 2018 TO BE PUBLISHED

cSuprmut filnurl ·nf IftfFlf}ftlaj] ~ [L 2016-SC-000666-DG IQ)~11 ~'f}12/Jg ~IM ~IM"t1 ,De VANHOOK ENTERPRISES, INC. APPELLANT

ON REVIEW FROM COURT OF APPEALS v. CASE NO.- 2015-CA-001977-MR PULASKI CIRCUIT COURT NO. 1~-CI-.00922

KAY & KAY CONTRACTING, LLC APPELLEE

OPINION OF THE COURT BY JUSTICE CUNNINGHAM

REVERSING AND REINSTATIN.G

The United States Small Business Administra,tion ("SBA") regulates the

Historically Underutilized Business Zone ("HUBZone") Program. 15 U.S.C. §

657a. Through the HUBZone program, the SBA provides contracting

assistance to small businesses seeking federal government contracts. To

qualify as a HUBZone-eligible contractor, one must be a small business within

an economically distressed area. Id.

In 2010, the U.S. Army Corps of Engineers sought bids from HUBZone-

eligible contractors to replace the Cumberland Bridge Street Bridge over the

Poor Fork of the Cumberland River in Cumberland, Kentucky. The HUBZone

contract price was $1,029,394.20 .. Kay & Kay Contracting, LLC ("Kay & Kay"), a large construction firm in London, was ~nterested in the construction job, but

was not a HUBZone-:eligible business.

Accordingly, Kay & Kay negotiated with Vanhook Enterprises, Inc.

("Vanhook"), a HµBZone-eligible contractor in Somerset, and entered into a

series of agreements with Vanhook whereby Vanhook would apply for the

HUBZone: contract. Vanhook would receive th~ HUBZone contract pripe from

the federal government, which it would then split with Kay & Kay as a

subcontractor working on the HUBZone project. On July 7, 2010, this

. relationship culminated in the so-called Team Agreement between the parties,

whereby Vanhook.agreed to serve as the prime contractor for the HUBZone . ' contract. \

On January 13, 2011, Vanhook and Kay & Kay entered into the so-called

Subcontract Agreement, .which outlined services that Kay & Kay was to perform

as a ~ubcontractor under the HUBZone project. The Subcontract Agreement

stated that Vanhool,c would pay Kay & Kay $37,500 for ."Mobilization" and . a $410,000 lump sum for "All Materials, Labor, Equipment[,] and applicable

truces for the construction of the Bridge Str~et Bridge."

Later in 2011, during construction, the parties entered into a subsequent

. written agreement whereby Vanhook rented equipment and an equipment

operator from Kay & Kay for an additional $12,300. This agreement was

expressly excluded from the Subcontract Agreement. See Subcontract

}\greement, Exhibit A ("The lump-:sum item shall include all costs associated

2 with the construction of the bridge that are -not othenvise identified as being

paid separately." (emphasis added)).

After completion of the bridge, Vanhook remitted an undisputed

$459,790.04 to Kay & Kay under.the Subcontract Agreement and subsequent

written a~reement: $37,500 for "Mobilization," the $410,000 lump sum, and

$12,300 for the additional equipment rental and operator contract. On

December 8, 2011, Kay & Kay Vice President Ron Pfaff executed a writing titled

"Affidavit and Waiver of Lien, Acknowledgement of Full and Final Payment."

Therein, Pfaff swore that Kay & Kay had been fully compensated for materials

provided and ser\rices performed under the Subcontract Agreement by "full and

final payment due including any applicable retainage." However, despite its

letter, Kay & Kay continued to ·seek additional payment from Vanhook.

In the summer of 2013, Kay & Kay sued Vanhook for breach of contract

and quantum_meruit in the alternative, asserting that the parties had entered·

into a separate agreement after the Team Agreement, but before the

Subcontract Agreement-the so-called Prime Agreement ... Under that alleged - - agreement, Kay & Kay claimed that Vanhook was obligated to pay greater than

the lump-sum· price. Kay & Kay claimed it performed 76% of total work under

the 43~bid item project-$785,814.16 of the $1,029,394.20 HUBZone contract

price-and, th1:1s~ performed $~26,024.12 worth of work outside of the

Subcontract Agreement's contract price. Kay & Kay maintained that the i expenses it incurred in excess of the $410,000 lump sum were for services it

performed outside of the scope of the Subcontract Agreement, and thereby

3 \

unjustly enriched Vanhook by rendering those services without adequate

, compensation.

Vanhook responded that no such Prime Agreement existed, and, even if it

did, that the- Subcontract Agreement superseded aH prior agreements and

. negotiations be~een the parties. Therefore, Vanhook moved for judgment on

the pleadings. CR 12.03. The Pulaski Circuit Court found the Subcontract

. 1 A~eement to-be a complete integration of the dealings between Vanhook and

Kay & Kay regarding the ~ridge Street Bridge project. Accordingly, the Pulaski· (

Circuit Court held that the alleged "additional work" was included within a ,/

plain, ordinary reading of Exhibit A of the Subcontract Agreement as "any 9ther

ancillary items required to provide _a complete bridge structure."

On appeal, the Kentucky Court of Appeals affirmed the trial court's

finding that the Subcoritract Agreement was an integration. H9wever, the

Court of Appeals held that it was unclear whether Kay &·Kay's "additional

work" fell within the "any other ancillary items" language of the contract. In )

other words, it was unc_lear whether the Subcontract Agreement was a full

integration or a partial integration. The Court of Appeals declared that whether

the "additional work" Kay & Kay allegedly performed was covered by the

Subcontract Agreement was an issue of fact for the jury. Vanhook appealed to

this Court, .and we granted discretionary review.

Analysis

Interpretation of a written contract is a matter of law to be decided by the

trial court. 3D Enters. Contracting Corp. v. Louisville & Jefferson Cnty. Metro. '.

4 Sewer Dist., 174 S.W.3d 440, 448 (Ky. 2005). The Pulaski Circuit Court·

granted Vanhook's motion for judgment on the pleadings, which "should be

granted if it appears beyond doubt that the nonmoving party cannot prove any

set of facts that would entitle [that party] to relief." Schultz v. Gen. Elec.

Healthcare Fin. Svcs., Inc., 360 S.W.3d 171, 176 (Ky. 2012) (internal citation ' omitted). A motion for judgment on the pleadings is treated akin to a motion . r '

"for summary judgment[,] and [is] disposed of in that manner."· Hoke v .

.Cullinan, 914 S.W.2d 335, 338 (Ky. 1995).

_"Appellate review of a summary judgment involves only legal questions

and a ·determination of whether a disputed material issue of fact exists, So we ·

operate under a de novo standard of review with no need to defer to the trial

c~ilrt's decisiOn." Shelton v. Kentucky Easter Seals Soc'y, Inc., 413 S.W.3d 901,

905 (Ky: 20.13) Jinternal citations omitted). "The interpretation of a contract, ·

including determining whether a contract is ambiguous, is a question of law to

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McMullen v. Hoffman
174 U.S. 639 (Supreme Court, 1899)
Hoke v. Cullinan
914 S.W.2d 335 (Kentucky Supreme Court, 1995)
Mounts v. Roberts
388 S.W.2d 117 (Court of Appeals of Kentucky (pre-1976), 1965)
The Kentucky Shakespeare Festival, Inc. v. Brantley Dunaway
490 S.W.3d 691 (Kentucky Supreme Court, 2016)
Fruit Growers Express Co. v. Citizens Ice & Fuel Co.
112 S.W.2d 54 (Court of Appeals of Kentucky (pre-1976), 1937)
Robenson v. Yann
5 S.W.2d 271 (Court of Appeals of Kentucky (pre-1976), 1928)
Schultz v. General Electric Healthcare Financial Services Inc.
360 S.W.3d 171 (Kentucky Supreme Court, 2012)
Shelton v. Kentucky Easter Seals Society, Inc.
413 S.W.3d 901 (Kentucky Supreme Court, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Vanhook Enterprises, Inc. v. Kay & Kay Contracting, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vanhook-enterprises-inc-v-kay-kay-contracting-llc-ky-2018.