Vanderwal v. Albar, Inc.

303 P.3d 175, 154 Idaho 816
CourtIdaho Supreme Court
DecidedJune 20, 2013
Docket38085-2012
StatusPublished
Cited by22 cases

This text of 303 P.3d 175 (Vanderwal v. Albar, Inc.) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vanderwal v. Albar, Inc., 303 P.3d 175, 154 Idaho 816 (Idaho 2013).

Opinion

EISMANN, Justice.

This is an appeal out of Bonner County from the district court’s finding, after a court trial, that the seller of real property had breached its contract with the buyer by failing to remediate a gasoline spill on the property within a reasonable time and the court’s award of damages to the buyer. The appeal also challenges the district court’s denial of the seller’s post-judgment motion to reduce the buyer’s damages by the amount it received from the Idaho Department of Environmental Quality after the judgment was entered because of the buyer’s completion of the remediation. We affirm the judgment of the district court.

*819 i.

Factual Background.

Albar, Inc., was the owner of a business known as Dock-N-Shop, which was a convenience store, gas station, and marina located on the Pend Oreille River. On Memorial Day weekend in May 2003, one of the business’s three underground storage tanks leaked gasoline into the surrounding soil. The three tanks were insured through the State of Idaho Petroleum. Storage Tank Fund (Fund). Albar eventually entered into a consent order dated August 22, 2003, with the Idaho Department of Environmental Quality (DEQ), which required Albar to remediate the Property and any impacted adjacent property until it met cleanup levels established by DEQ. A contractor retained by the Fund began remediation efforts.

In early 2005, Albar listed the property for sale. Albar completed a property disclosure form, which stated: “Memorial Day weekend 2003 a leak in gas tanks discovered, DEQ & State insurance fund notified immediately and tank pulled next day, suspect soil removed and replaced. DEQ continue monitoring.” That statement was false.

JLZ Enterprises, Inc., an Ohio corporation, became interested in purchasing the property. A representative of Albar told Echo VanderWal, the president of JLZ Enterprises, that the soils had been remediated and were clear and that the only task left in the remediation was two monitoring sessions, which would be completed by January 2006. The Albar representative knew or should have known that the statement was false. On June 14, 2005, JLZ Enterprises made an offer to purchase the property for $450,000. The offer included several contingencies, including the “EPA giving closure to gasoline spill on site.” Albar countered by increasing the purchase price to $539,000 and agreeing to have “all responsibility and liability for recent gasoline spill on property and adjoining property” instead of the provision regarding the EPA. Albar understood the provision to mean that it was required to continue with the remediation until the property was cleared by DEQ. JLZ Enterprises accepted the counteroffer on June 16, 2005, and the transaction closed on September 14, 2005. As payment of part of the purchase price, JLZ Enterprises executed a promissory note to Albar in the sum of $250,000, which was secured by a deed of trust on the property.

The contractor performing the remediation on behalf of Albar installed a series of vapor extraction wells which were designed to remediate the soil, as well as air sparging wells and an air stripping system to attack ground water contamination. However, it did not do any testing to determine the lateral extent of the contamination even though such testing was required by DEQ before it would clear the property.

In August 2006, there was a meeting with DEQ, JLZ Enterprises, and Albar to discuss a more expeditious and accepted way to achieve remediation of the property. During the meeting, DEQ stated that the soil beneath the Dock-N-Shop building had to be tested to see if there was contamination there. In late August 2006, JLZ Enterprises demolished the Dock-N-Shop building. The contractor performing the remediation on behalf of Albar told a representative of JLZ Enterprises that with the building removed, ground water levels would permit testing below where the building had been in mid-October and that any contaminated soil could be excavated and hauled off. However, the contractor did not test the soil then, and it abandoned any thought of excavating and hauling off any contaminated soil because the cost might exceed the limits of Albar’s insurance policy and Albar was not willing to expend any money on the remediation.

Tests conducted in December 2006 revealed contamination at various locations in the soil under the site where the building had been. During the next twelve months, the contractor performing the remediation on behalf of Albar did not take action to remediate the soil below the building site.

JLZ Enterprises wanted to remove the other two underground tanks, one of which was located between the tank that leaked and the building site where contamination had been discovered. Albar took the position that removal of the two remaining tanks was not its responsibility. DEQ would not clear *820 the property until the soils under the two remaining tanks had been tested, and by the summer of 2007 the contractor had not tested the soils beneath those tanks.

On July 16, 2007, JLZ Enterprises failed to make the payment due on the promissory note. In August 2007, it obtained approval from DEQ to remove the two tanks, and it did so. Testing revealed contamination under the tank that had been next to the one that leaked. JLZ Enterprises also removed the top fifteen feet of soil from the tank area through the building site and the easterly property line so that the contaminated soil below it could be excavated and hauled away.

By October 2007, the contractor doing the remediation on behalf of Albar had made no further progress in remediating the site. It had not even obtained approval of its amended remediation plan from DEQ. The contractor’s proposed course of action was to continue what it had been doing for the past four years.

JLZ Enterprises decided to take over the remediation itself. It applied for and was admitted to DEQ’s voluntary remediation program. Under that program, it assumed liability for the cleanup and would receive a covenant not to be sued by DEQ when the remediation was complete. It may also qualify for financial assistance for a portion of the remediation costs.

JLZ Enterprises submitted its remediation plan to DEQ in November 2007, and the plan was accepted the following month. In January 2008, JLZ Enterprises began its remediation of the entire site by removing the topsoil, excavating the contaminated soil, and hauling it away. That work was completed by the end of April 2008, and then the monitoring began. By then, JLZ Enterprises ran out of money, and its contractor left the site. Eventually, DEQ paid for the needed monitoring.

On August 29, 2007, JLZ Enterprises and its president filed an action to recover damages for fraud against the real estate agent, Albar, and its president; to recover damages against Albar and its president for breach of contract; to rescind the contract; and to recover damages for negligence against the real estate agent and the broker. On November 2, 2007, Albar filed an action to judicially foreclose the deed of trust. Both lawsuits were ordered consolidated on November 26, 2008. The parties later stipulated to dismiss the real estate agent and the broker from the lawsuit. In June 2011, JLZ Enterprises and its president stipulated to dismiss all of their claims except the breach of contract and rescission claims against Albar.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nathon A. Baughman v. Wells Fargo Bank
395 P.3d 393 (Idaho Supreme Court, 2017)
American Semiconductor, Inc. v. Sage Silicon Solutions, LLC
395 P.3d 338 (Idaho Supreme Court, 2017)
Seth Griffith v. Jumptime, Meridian
393 P.3d 573 (Idaho Supreme Court, 2017)
Robert Wolford v. Shawn Montee
Idaho Supreme Court, 2016
State v. Lannette Kay Johnson
Idaho Court of Appeals, 2016
Idaho Dep't of Health & Welfare v. John Doe
418 P.3d 1216 (Idaho Supreme Court, 2016)
Morrison v. St. Luke's Regional Medical Center, Ltd.
377 P.3d 1062 (Idaho Supreme Court, 2016)
PHH Mortgage v. Nickerson
374 P.3d 551 (Idaho Supreme Court, 2016)
State v. Marvin Gordon Crotto
Idaho Court of Appeals, 2016
Christina J. Greenfield v. Eric J. Wurmlinger
349 P.3d 1182 (Idaho Supreme Court, 2015)
Jay Brown v. Auga Greenheart
Idaho Supreme Court, 2014
Brown v. Greenheart
335 P.3d 1 (Idaho Supreme Court, 2014)
Cummings v. Stephens
336 P.3d 281 (Idaho Supreme Court, 2014)
Katie Alderson v. Gary Bonner
Idaho Court of Appeals, 2014
Cuevas v. Barraza
318 P.3d 952 (Idaho Supreme Court, 2014)
Robert Siegwarth v. Opportunity Management Co., Inc.
315 P.3d 245 (Idaho Supreme Court, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
303 P.3d 175, 154 Idaho 816, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vanderwal-v-albar-inc-idaho-2013.