Van Iderstine Co., Inc. v. Barnet L. Co., Inc.

152 N.E. 250, 242 N.Y. 425, 46 A.L.R. 858, 1926 N.Y. LEXIS 1001
CourtNew York Court of Appeals
DecidedMay 4, 1926
StatusPublished
Cited by20 cases

This text of 152 N.E. 250 (Van Iderstine Co., Inc. v. Barnet L. Co., Inc.) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Van Iderstine Co., Inc. v. Barnet L. Co., Inc., 152 N.E. 250, 242 N.Y. 425, 46 A.L.R. 858, 1926 N.Y. LEXIS 1001 (N.Y. 1926).

Opinion

Lehman, J.

On or about August 12th, 1920, the plaintiff and the defendant entered into a contract for the sale of 15,000 vealskins, delivery thereof to be ma de beginning week oí August 16th.” The contract was *429 made upon condition that the skins were “to be received by Jules Star & Co.’s representative subject to their approval.” On September 10th, 1920, the parties entered into another contract for the sale of 6,000 vealskins, delivery to be made in September, “to be received by Jules Star & Co. subject to their approval.” On or about August 16th a representative of Jules Star & Co. examined 15,000 vealskins tendered by the plaintiff in performance of its contract of sale of August 12th, and rejected 3,500 of such skins. It is not disputed that such rejection was justified. In October the plaintiff notified the defendant that it was ready to deliver 3,500 skins in substitution for those previously rejected. The defendant refused to accept or even examine the same on the ground that the time for delivery had expired. About the same time, Jules Star & Co. rejected the entire quantity of 6,000 skins which the plaintiff tendered in attempted performance of its contract of September 10th, 1920, and defendant refused to accept them.

The plaintiff has brought this action to recover damages suffered because of the defendant’s refusal to accept the skins which plaintiff offered to deliver. In the first cause of action for failure to accept the 3,500 skins under the contract of August 12th, 1920, the plaintiff alleges that at or about the time of the delivery to defendant of 11,500 skins in August “ it was mutually agreed between the plaintiff and defendant that the time for delivery of the remaining 3,500 vealskins called for by said Exhibit A should be extended until such time as plaintiff, in the usual course of its business, should have collected that number of its skins.” In the second cause of action as amended at the trial the plaintiff alleged that any condition for approval by a representative of Jules Star & Co. of the skins to be delivered under the contract of September 10th was waived and excused because the approval was unreasonably withheld, and because defendant prevented Jules Star & Co. from giving such approval *430 and “because defendant and said Jules Star & Co. wrongfully and knowingly colluded to withhold that approval, with intent to avoid defendant’s having to accept the said skins.” The issues raised by the denial to these allegations were submitted to the jury and decided in favor of the plaintiff.

The alleged agreement set forth in the first cause of action to extend the time for the delivery of 3,500 skins in substitution for those rejected under the first cause of action was not in writing, and it is urged that consequently it was unenforcible under the Statute of Frauds. The alleged conversation could not result in the substitution of a different time for delivery of the vealskins from that which had been agreed upon in writing. The Statute of Frauds would render an oral agreement changing any term of the written contract ineffectual. (Imperator Realty Co. v. Tull, 228 N. Y. 447; Davison Coal Co. v. Weston, Dodson & Co., 209 App. Div. 514, 517; affd., 240 N. Y. 705.) Nevertheless such conversation may not be entirely disregarded. The written contract provided for deliveries “ beginning week of August 16th.” The conversation at least evidences that the parties understood that under the provision of the contract that deliveries should be made “ beginning week of August 16th,” the plaintiff should have a reasonable time to complete delivery of sldns which Jules Star & Co. would accept, though approval had been withheld from some sldns previously tendered. In that aspect the conversation might have the effect of placing a Emit upon what would constitute reasonable time as understood by the parties. (Eppens, Smith & Wiemann Co. v. Littlejohn, 164 N. Y. 187.)

The intention of the parties as set forth in the written contract as to whether or not the seller should have reasonable time to substitute other sldns for those rejected seems under the circumstances of the case to present a question of fact. Even if that question is resolved *431 against the seller, it does not follow that the buyer could not waive, or elect not to take advantage of a partial breach resulting from failure to tender the full quantity of satisfactory skins or that the conversation could not be proven to show such election. If the seller under the contract was obligated to deliver 15,000 skins subject to the approval of Jules Star & Co. without right of substitution for rejected skins, the buyer, of course, had the right to refuse to accept skins tendered after the original tender of 15,000 skins. He was not bound to do so. He might still choose to keep the contract alive in order to enable the seller to make delivery of the full stipulated number of approved skins. If the conversation was had as alleged, it shows that the buyer did elect to keep the contract alive in spite of known excuse justifying refusal to proceed further. The seller concurred in that election, and thereafter the buyer could not assert that excuse as reason for rejection. (Williston on Contracts, sections 687 and 688.) We have recently pointed out that sometimes distinction between a waiver of default, or an extension of the time for performance, and acts which enlarge definition of a ‘ reasonable time ’ as contemplated by the parties beyond the limits which might otherwise be set, is tenuous.” (Murray Co. v. Lidgerwood Mfg. Co., 241 N. Y. 455.) Here the conversation may not result in .extension of time for delivery; it may result in waiver of right to regard the contract as no longer in force after partial failure to perform by the seller, and thereafter the seller could not be again placed in default until reasonable opportunity is afforded for performance.

Even though evidence was properly admitted as to the alleged conversation in regard to the delivery of the 3,500 skins which constitute* the subject-matter of the first cause of action, there must be a new trial because in other respects error has crept into the record. We have pointed out that under both contracts sued upon, the *432 seller agreed to make delivery subject to the approval of Jules Star & Co. The parties chose to stipulate that such approval must be given. It constitutes a condition which unless waived or excused must be fulfilled before the buyer can be compelled to accept skins that are tendered. Concededly approval of Jules Star & Co. has not been given. The condition was as matter of law waived by the buyer in regard to the 3,500 skins referred to in the first cause of action, when the buyer refused to accept any skins even if approved by Jules Star & Co. Of course, the condition was waived also in regard to the contract which forms the basis of the second cause of action if refusal of approval by Jules Star & Co. was the result of bad faith on the part of Jules Star & Co. in which the defendant had some share.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Matter of Liberty Mut. Fire Ins. Co. v. Wilson
2025 NY Slip Op 51076(U) (New York Supreme Court, Kings County, 2025)
Green v. William Penn Life Insurance
74 A.D.3d 570 (Appellate Division of the Supreme Court of New York, 2010)
A.B. Medical Services, PLLC v. State Farm Mutual Automobile Insurance
7 Misc. 3d 822 (Civil Court of the City of New York, 2005)
Oppenheimer & Co. v. Oppenheim, Appel, Dixon & Co.
660 N.E.2d 415 (New York Court of Appeals, 1995)
Ber v. Johnson
163 A.D.2d 817 (Appellate Division of the Supreme Court of New York, 1990)
Cities Service Co., Inc. v. Derby & Co., Inc.
654 F. Supp. 492 (S.D. New York, 1987)
McKenna v. Case
123 A.D.2d 517 (Appellate Division of the Supreme Court of New York, 1986)
Hadden v. Consolidated Edison Co.
312 N.E.2d 445 (New York Court of Appeals, 1974)
Gee v. Nieberg
501 S.W.2d 542 (Missouri Court of Appeals, 1973)
All-Year Golf, Inc. v. Products Investors Corp.
34 A.D.2d 246 (Appellate Division of the Supreme Court of New York, 1970)
In re the Town of Oyster Bay
50 Misc. 2d 91 (New York Supreme Court, 1966)
Russell & Axon v. Handshoe
176 So. 2d 909 (District Court of Appeal of Florida, 1965)
Jones v. Burton
9 Misc. 2d 354 (New York Supreme Court, 1957)
Tichenor v. Peoples Savings Bank
282 A.D. 1053 (Appellate Division of the Supreme Court of New York, 1953)
Gillette v. Kelling Nut Co.
185 F.2d 294 (Fourth Circuit, 1950)
McCutcheon v. Kimball
135 Misc. 299 (City of New York Municipal Court, 1929)
Jungmann Co., Inc. v. Atterbury Bros., Inc.
163 N.E. 123 (New York Court of Appeals, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
152 N.E. 250, 242 N.Y. 425, 46 A.L.R. 858, 1926 N.Y. LEXIS 1001, Counsel Stack Legal Research, https://law.counselstack.com/opinion/van-iderstine-co-inc-v-barnet-l-co-inc-ny-1926.