Valentine Lumber & Supply Co. v. Thibeault

130 N.E.2d 868, 333 Mass. 352, 1955 Mass. LEXIS 589
CourtMassachusetts Supreme Judicial Court
DecidedDecember 14, 1955
StatusPublished
Cited by4 cases

This text of 130 N.E.2d 868 (Valentine Lumber & Supply Co. v. Thibeault) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Valentine Lumber & Supply Co. v. Thibeault, 130 N.E.2d 868, 333 Mass. 352, 1955 Mass. LEXIS 589 (Mass. 1955).

Opinion

Qua, C.J.

This bill is brought by a subcontractor, hereinafter called Valentine, against the defendant principal contractor, hereinafter called Thibeault, and the defendants David R. Berg and Ethel Berg, husband and wife, the owners of real estate in Longmeadow, to establish Valentine’s lien for materials furnished to Thibeault for a house to be built by him upon the Berg land for the price of $29,000.

The lien claimed is a subcontractor’s lien under G. L. (Ter. Ed.) c. 254, § 4, and depends upon a recorded notice of a written contract for the materials between Valentine and Thibeault. No lien is claimed under §§ 1 to 3 dependent upon the recording of notice of the principal contract. In addition to the claim of lien based upon Valentine’s notice as subcontractor, the bill in a separate paragraph describes a “collateral” written agreement dated July 16, 1951, among Valentine, Thibeault, and David R. Berg and alleges that David R. Berg “personally” owes Valentine and Thibeault jointly $5,000 which, with the consent of Thibeault, *354 will be applied in reduction of Valentine’s lien against the land. In addition to prayers for the establishment of the lien there is. included a prayer for judgment on this agreement against the defendant David R. Berg in favor of the plaintiff Valentine and the defendant Thibeault.

The case was referred to a master, whose several reports were confirmed without exception or appeal, and a final decree was entered establishing a lien in favor of Valentine for an amount which is equal to the $5,000 mentioned in the so called collateral agreement plus interest. The Bergs appeal from the final decree.

For convenience we deal first with the “collateral” agreement, but without stopping to consider whether it' had a proper place in a bill of this kind, since there was no demurrer, and so far as we know no objection has been made to dealing with this agreement. The principal contract between the Bergs and Thibeault was dated January 19, 1951. The subcontract between Valentine and Thibeault was dated January 24, 1951. It is plain from findings of the master that by the latter part of May the defendant David R. Berg became apprehensive that Thibeault was not paying or would not pay Valentine for the materials furnished and in substance insisted that any further payments by the Bergs to Thibeault be used on the Valentine account in reference to the Berg house. On July 12 David R. Berg wrote Valentine that he considered that all materials furnished up to June 1 had been paid for, and that upon payment for any materials furnished after June 1 he should “expect a release and discharge of the lien which you have filed.” Thereupon Valentine stopped deliveries to Thibeault and progress of the work “slowed up” or “practically stopped.” The agreement of July 16 was made in order that the work “could be resumed and completed.” That agreement reads as follows:

“July 16, 1951

Agreement by and between David R. Berg (Owner), Robert A. Thibeault (Builder) and Valentine Lumber & Supply Company (Supplier) for valuable consideration paid *355 by each to the other, receipt of which is hereby acknowledged by each, as follows:

1. All agree that exact balance due Builder by Owner on construction of house at 152 Meadowbrook Rd., Long-meadow as of this day is Five Thousand Dollars ($5,000.00) which amount is to be paid after entire completion of construction, all in accordance with original plans and specifications. Builder to supply all labor and materials, except that Owner is to take care of all plumbing, concrete, heating, painting and electrical work.

2. Owner to make said payment of ($5,000.00) when due jointly to Builder and Supplier.

3. Supplier agrees that when said payment of $5,000.00 representing Owner’s entire balance due on construction contract is made jointly to Builder and Supplier, Supplier will release and discharge its lien on said work and materials and consider itself paid in full as far as Owner is concerned. Supplier agrees further to supply Builder with all necessary supplies and materials for the job to enable Builder to complete work.

/s/ David R. Berg

/s/ Robert A. Thibeault

Valentine Lumber & Supply Co. Inc.

/s/ By R. W. Cowles”

Duplicate Original

There are several reasons why this agreement cannot be made the foundation of a lien under c. 254, § 4, or even the basis of a recovery of a personal judgment against the Bergs jointly or against either of them. (1) Ethel Berg was not a party to the agreement. (2) The agreement fixes the balance payable to Thibeault on the general contract and provides that this balance shall “when due” be paid to Thibeault and Valentine jointly, and that when such payment is made Valentine shall release its lien. But the agreement does not even purport to relieve Valentine in any way from the necessity of following in all particulars the procedure provided by statute if it should seek to estab *356 lish a lien. (3) The payment of $5,000 is to be made only "after entire completion of construction, all in accordance with original plans and specifications.” Entire completion was an express condition of the agreement. On November 1, the approximate date fixed for completion of the principal contract, work and materials remaining within Thibeault’s contract and amounting to about $2,100 bad not been performed or furnished by Thibeault and so far as appears he never completed the work.

Therefore nothing ever became due under the agreement of July 16. Accordingly the decree in so far as based upon that agreement cannot stand.

It remains to be considered whether upon the findings of the master Valentine has established a lien for any amount according to the provisions of the statute. The result of the- detailed and elaborate findings of the master appears to us to be that he found a lien was proved in the amount of $2,729.80, which by adding interest from the filing of the bill, October 1, 1952, to the filing of the master’s first report, August 10, 1953, became $2,870.39. The process by which this result is reached is too complicated to be restated here. We can best proceed by dealing with the several contentions made by the parties in attacking the master’s conclusions.

1. We cannot accept the Bergs’ contention that because the principal contract had an indefinite completion date, to wit, "shall be substantially completed on or about November 1, 1951,” no lien can be established under the subcontract the completion date of which was definitely fixed as November 1, 1951. The subcontractor’s hen under § 4 depends upon the subcontract and the notices given. It is not affected by an indefinite date in the principal contract. There is nothing to the contrary in Pratt & Forrest Co. v. Strand Realty Co. of Lowell, 233 Mass. 314, or Adams & Powers Co. v. Seder, 257 Mass. 453. It must be remembered that a lien is here sought under § 4 and not under §§ 2 or 3.

2. Section 4 requires "actual notice to the owner” of *357 the recording of the notice of contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JP Smith Co. Inc. v. Wexler Construction Co. Inc.
233 N.E.2d 723 (Massachusetts Supreme Judicial Court, 1968)
Carroll Hunnewell, Inc. v. Southboro Construction Corp.
180 N.E.2d 343 (Massachusetts Supreme Judicial Court, 1962)
Forte v. Caruso
146 N.E.2d 501 (Massachusetts Supreme Judicial Court, 1957)
Valentine Lumber & Supply Co. v. Thibeault
146 N.E.2d 349 (Massachusetts Supreme Judicial Court, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
130 N.E.2d 868, 333 Mass. 352, 1955 Mass. LEXIS 589, Counsel Stack Legal Research, https://law.counselstack.com/opinion/valentine-lumber-supply-co-v-thibeault-mass-1955.