Valbruna Slater Steel Corp. v. Joslyn Manufacturing Co.

260 F. Supp. 3d 988
CourtDistrict Court, N.D. Indiana
DecidedMay 12, 2017
DocketCase No. 1:10-cv-44-JD
StatusPublished

This text of 260 F. Supp. 3d 988 (Valbruna Slater Steel Corp. v. Joslyn Manufacturing Co.) is published on Counsel Stack Legal Research, covering District Court, N.D. Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Valbruna Slater Steel Corp. v. Joslyn Manufacturing Co., 260 F. Supp. 3d 988 (N.D. Ind. 2017).

Opinion

OPINION AND ORDER

JON E. DEGUILIO, Judge

This case arises under the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA), 42 U.S.C. § 9601 et seq. Plaintiffs Valbruna Slater Steel Corporation and Fort Wayne Steel Corporation (collectively Valbruna) filed a cost recovery claim under § 107(a). Defendants Joslyn Manufacturing Company, Joslyn Corporation and Joslyn Manufacturing Company, LLC (collectively Joslyn) filed a contribution counterclaim under § 113(f). The parties tried Phase I of this bifurcated bench trial, on damages, from February 6, 2017 to February 7, 2017. Having considered the evidence, the Court now enters its findings of fact and conclusions of law as to that phase of trial.

BACKGROUND

This environmental litigation has endured for more than seven years. To summarize briefly, the Plaintiffs own a contaminated steel processing site, which they claim to have spent more than two million dollars to remediate. Their only cause of action (cost recovery under § 107(a)) seeks to require the Defendants, who used to own the site, to reimburse them for their cleanup costs.1 The Defendants oppose that claim. They also filed a contribution counterclaim (under § 113(f)) arguing that, to the extent they are liable for any expenses, those expenses ought to be equitably reallocated to the Plaintiffs.

While the full factual and procedural background of this matter is extensive (and set forth in prior orders), this case now boils down to two issues. First is the appropriate measure of damages. On sum[992]*992mary judgment, the Court found Joslyn jointly and severally liable for the cost of remediating the site but deferred calculating damages. [DE 124], It accordingly remains to determine which of Valbruna’s remediation costs aré necessary and consistent with the National Contingency Plan (NCP) such that they are compensable under §' 107(á). Second is the issue of contribution. Here, the Defendants argue that, even though they are technically liable under § 107(a), it is nevertheless inequitable to require them to bankroll the cleanup' effort. Phase I of this trial addressed the first of these issues (Phase II, which will address the second, is scheduled for June 12, 2017). Based upon its consideration of the testimony at trial and the other evidence submitted by the parties, the Court now enters the following conclusions of law and findings of fact as to Phase I of trial pursuant to Federal Rule of Civil Procedure 52:

FACTS

The parties stipulated to the following facts:

1. From 1928 to 1981, Joslyn owned property located at what is presently identified as 2302 and 2400 Taylor Street fik/a 1701 McKinley Avenue in Fort Wayne, Indiana (collectively, “Site”) and operated a steel manufacturing facility on the Site (“Steel Facility”) for all of those years.
2. • On February 2,1981, Joslynsold'the Site’ and Steel’ Facility to Slater Steels Corporation (“Slater”).
3. In June 2003, Slater filed a Chapter 11 bankruptcy petition in the U.S. Bankruptcy Court for the- District of Delaware (“Slater Bankruptcy”).
4; The soil and groundwater at and around the Site are contaminated with numerous hazardous substances, including chlorinated organic chemicals (e.g., TCE), semi-volatile organic chemicals, heavy metals, PCBs and radioactive elements related to historical operations at the Site.
5. Valbruna acquired the Site in April 2004 following an auction conducted as part of the Slater Bankruptcy.
6. FWSC acquired that portion of the’ Site presently identified as 2302 Taylor Street (“2302 Property”), and VSSC acquired that portion of the Site presently identified as 2400 Taylor Street (“2400 Property”).
7. In April 2004, Valbruna and the .Indiana Department, of Environmental Management (“IDEM”) entered into a Prospective Purchasers Agreement (“PPA”), which required Valbruna to spend approximately $1 million on Site investigation and remediation work in response to pre-existing contamination at and from the Site. Valbruna contributed $500,000 of the $1 million.
8. From 2005 to 2006, Valbruna conducted Electrical Resistance Heating (“ERH”) utilizing the PPA funds to address volatile organic compound impacts at a portion of the Site where, degreas-ing operations had historically occurred.
9. In June 2006, the U.S. Environmental Protection Agency (“U.S. EPA”) inspected the Site in relation to its historical contamination issues.
10. By letter dated November 1, 2007, IDEM issued ,a Risk Assessment Review outlining the Site’s remaining areas of environmental concern after the ERH work.
11. In 2008, VSSC and FWSC each entered their respective portions of the Site into IDEM’s Voluntary Remediation Program (“VRP”).
12. As part of participating in VRP, the applicants (VSSC and FWSC) and IDEM entered into separate Voluntary [993]*993Remediation Agreements (collectively, “VRA”) in March 2011.
13. Valbruna has never operated a melt shop at the Site or conducted any ihanufacturing operations at the 2302 Property.
14. Valbruna currently operates a steel rolling facility at the 2400 Property.

[DE 163 at 6-6]. The Court will set forth additional facts as they are relevant to its analysis below. Most of the evidence at trial was undisputed, though the Court also notes and explains its resolution of factual conflicts where necessary.

ANALYSIS

This phase of trial addressed which of Valbruna’s expenses meet the requirements for compensability under CERCLA. To be recoverable, expenses must be both necessary and consistent with the National Contingency Plan. Costs are “necessary” if they are incurred in response to a threat to human health or the environment and they are necessary, to address that threat. G.J. Leasing Co. v. Union Elec. Co., 854 F.Supp. 539, 562 (S.D. Ill. 1994) aff'd, 54 F.3d 379 (7th Cir. 1995). This is an objective inquiry. Carson Harbor Vill., Ltd. v. Unocal Corp., 270 F.3d 863, 872 (9th Cir. 2001) (“In determining whether response costs are ‘necessary,’ we focus not on whether a party has a business or other motive in cleaning up the property, but on whether there is a threat to human health or the environment and whether the response action is addressed to that threat.”).

A private party response action is consistent with the NCP if it is in substantial compliance with the requirements set forth in 40 C.F.R. § 300.700(c)(5) to (6) and results in a CERCLA-quality cleanup. 40 C.F.R. § 300.700(c)(3)®.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
260 F. Supp. 3d 988, Counsel Stack Legal Research, https://law.counselstack.com/opinion/valbruna-slater-steel-corp-v-joslyn-manufacturing-co-innd-2017.