Utility Reform Project v. Oregon Public Utility Commission

372 P.3d 517, 277 Or. App. 325, 2016 Ore. App. LEXIS 405
CourtCourt of Appeals of Oregon
DecidedApril 6, 2016
DocketUM1402; A150814
StatusPublished
Cited by1 cases

This text of 372 P.3d 517 (Utility Reform Project v. Oregon Public Utility Commission) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Utility Reform Project v. Oregon Public Utility Commission, 372 P.3d 517, 277 Or. App. 325, 2016 Ore. App. LEXIS 405 (Or. Ct. App. 2016).

Opinion

GARRETT, J.

In another installment of a long-running dispute related to the closure of the Trojan nuclear power plant, petitioner seeks judicial review of an order of the Public Utility Commission (PUC) that granted respondent Portland General Electric’s (PGE) request to amortize in its rates certain costs of issuing a refund to ratepayers.

Petitioner challenges the PUC’s order on several grounds, asserting that the order is unlawful because (1) charging ratepayers for administering the refund violates ORS 757.355, (2) the PUC prevented petitioner from challenging the refund mechanism used by PGE, (3) the rate treatment approved by the PUC does not result in rates that are “fair, just, and reasonable,” (4) the PUC failed to order PGE to “forfeit the amount it retained for uncashed refund checks,” (5) the PUC, in approving PGE’s application to amortize the refund costs, applied an incorrect “earnings test,” and, (6) the PUC’s order was not supported by substantial evidence. We reject petitioner’s arguments for the reasons expressed below, and affirm the PUC’s order.

I. BACKGROUND

The precise issue on review is whether the PUC permissibly allowed PGE to recover the administrative costs of issuing a PUC-ordered refund to ratepayers. To place that question in context, however, some extensive factual and procedural background is required.

PGE began commercial operation of the Trojan nuclear power plant in 1976. At that time, the PUC authorized PGE to recover its capital investment in Trojan and a return on its investment in rates over a 35-year period. In 1993, after problems arose at Trojan, PGE retired the facility, at least in part, because it was cheaper for PGE to replace Trojan’s power output with purchased power than to continue operating the facility.

A. Order Nos. 93-1117 and 95-322, and Trojan I

PGE wished to recover the remaining balance of its capital investment in Trojan. In response, the PUC issued Order Nos. 93-1117 and 95-322, which, together, allowed [328]*328PGE’s rate base to include both a return of and a return on PGE’s Trojan investment. Those orders were appealed. In Citizens’ Utility Board v. PUC, 154 Or App 702, 716-17, 962 P2d 744 (1998), rev dismissed, 335 Or 91 (2002) (Trojan I), we concluded that ORS 757.140(2) and ORS 757.355 (1993)1 authorized a return of PGE’s principal investment in the retired facility, but not a return on its investment in the retired facility. We therefore remanded the orders to the PUC for reconsideration. Id. at 717.

B. Settlement, Order Nos. 00-601 and 02-227, and Dreyer

The Supreme Court allowed review of our decision in Trojan I, but then held the case in abeyance “when certain events occurred that appeared to have some potential for resolving the controversy without the court’s participation.” Dreyer v. PGE, 341 Or 262, 269, 142 P3d 1010 (2006). One of those events was a settlement between PGE and Citizens’ Utility Board, in which PGE agreed to offset its remaining Trojan investment balance and certain tax liabilities against certain existing credits in favor of PGE’s ratepayers. Id. That is, the settlement removed PGE’s remaining undepreciated investment in Trojan from prospective rates.

PGE applied to the PUC for an accounting order and revised rate schedules implementing the terms of the settlement; the PUC approved the request, effective October 1, 2000, in Order No. 00-601. Id. Petitioner, which was not a party to the settlement, challenged Order No. 00-601 in a proceeding before the PUC, arguing, in part, that the revised rates improperly allowed PGE to retain the return on investment that it had collected from ratepayers between 1995 and 2000. Id. at 270. That is, petitioner contended that the PUC merely provided prospective relief to ratepayers without providing a mechanism for returning ratepayers’ money that PGE had collected unlawfully between 1995 and 2000. Id.

[329]*329The PUC rejected petitioner’s challenge to Order No. 00-601 in Order No. 02-227, concluding that, under the “filed-rate doctrine,” it lacked authority to order PGE to refund the “return on investment” money that PGE had collected between 1995 and 2000. Petitioner sought review of that order in Marion County Circuit Court, which agreed with petitioner, reversed and remanded Order No. 02-227, and instructed the PUC to order PGE to immediately issue refunds for the full amount of all “excessive and unlawful charges” collected by PGE for its return on investment. Id. at 271-72. The PUC appealed that ruling, which ultimately resulted in our decision in Utility Reform Project v. PUC, 215 Or App 360, 170 P3d 1074 (2007) (Trojan II). Notably, however, the circuit court’s judgment was not stayed pending our review in Trojan II.

While the PUC’s appeal in Trojan II was pending before us, certain ratepayers, based on our decision in Trojan I, brought civil actions against PGE seeking refunds of the amounts that they had paid between 1995 and 2000 that were attributable to a return on investment. Dreyer, 341 Or at 273. Those plaintiffs each sought relief in four separate claims and sought certification as a class. PGE moved for dismissal of the civil suits, arguing, in part, that jurisdiction lay with the PUC. Id. at 275. The circuit court denied PGE’s motion to dismiss and certified the ratepayers as a class. PGE then petitioned the Supreme Court for alternative writs of mandamus, asking the court to dismiss the plaintiffs’ complaints and to vacate the circuit court’s class-certification order. Id. at 276.

In Dreyer, the Supreme Court initially concluded that, at the very least, the plaintiffs’ first claim was legally tenable. Id. at 280. In that claim, the plaintiffs had alleged that PGE had violated ORS 757.355 (1993) by charging and receiving rates that included a return on investment, and that, under ORS 756.185(1), PGE was liable to the plaintiffs for damages that they had sustained in consequence of that violation. Id. at 273-74. Because at least one of the plaintiffs’ claims was viable, the court concluded that it could not grant the relief requested by PGE—i.e., the dismissal of the plaintiffs’ complaint on the theory that none of the claims had [330]*330any basis in the law. Id. at 279-80. The court also rejected PGE’s argument that, under ORS 756.225, the circuit court lacked jurisdiction because the plaintiffs’ claims necessarily involved ratemaking or pertained to utility regulation. Id. at 282-83.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Calpine Energy Solutions LLC v. Pub. Util. Comm'n of Or.
445 P.3d 308 (Court of Appeals of Oregon, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
372 P.3d 517, 277 Or. App. 325, 2016 Ore. App. LEXIS 405, Counsel Stack Legal Research, https://law.counselstack.com/opinion/utility-reform-project-v-oregon-public-utility-commission-orctapp-2016.