Dreyer v. Portland General Electric Co.

142 P.3d 1010, 341 Or. 262, 2006 Ore. LEXIS 819
CourtOregon Supreme Court
DecidedAugust 31, 2006
DocketCC 03 C10639; SC S52217; CC 03 C10640; SC S52284
StatusPublished
Cited by12 cases

This text of 142 P.3d 1010 (Dreyer v. Portland General Electric Co.) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dreyer v. Portland General Electric Co., 142 P.3d 1010, 341 Or. 262, 2006 Ore. LEXIS 819 (Or. 2006).

Opinion

*265 GILLETTE, J.

In these consolidated actions against defendant Portland General Electric Company (PGE) brought by current and former customers of that utility, PGE asks this court to issue writs of mandamus ordering the Marion County Circuit Court to dismiss plaintiffs’ actions and to vacate an order certifying plaintiffs as a class. PGE contends, among other things, that the circuit court lacks jurisdiction to hear the actions because the cases necessarily involve rate-setting, a function that the legislature has delegated exclusively to the Oregon Public Utility Commission (the PUC). Although we reject PGE’s contention that the actions must be dismissed, we conclude that they should be abated, at least until the PUC responds to certain remands from the Marion County Circuit Court in related cases, because the PUC’s disposition of those remanded cases may negate some of or all the damages that plaintiffs now claim. We issue a writ of mandamus accordingly.

The actions arose out of a longstanding controversy over one of PGE’s former generating facilities, the Trojan nuclear power plant. When Trojan first went into service in 1976, the PUC set PGE’s rates in a way that allowed it to recover its investment in Trojan over a 35-year period. However, the plant was plagued with technical problems and breakdowns, and PGE finally closed it in 1993 — long before PGE had recouped its investment.

By the time that Trojan was shut down, the legislature had enacted a statute that allowed utilities to charge rates that included their “undepreciated investment” in a retired plant — if the PUC found the closure to be in the public interest. 1 PGE sought to take advantage of that provision and *266 therefore argued to the PUC that closing Trojan (and replacing it with power purchased from outside sources) was in the public interest because it was the “least cost” alternative for providing power to PGE’s customers.

In 1993, the PUC issued an order finding that PGE’s decision to close Trojan under a ‘least cost” theory was “reasonable.” PUC Order No. 93-804. However, it reserved for a later proceeding the question of how to adjust PGE’s rates to deal with the closure. Shortly thereafter, PGE filed a request with the PUC pursuant to ORS 756.450 (1993), 2 asking that body to issue a declaratory ruling as to the propriety of charging the undepreciated portion of its Trojan investment to PGE’s ratepayers. The PUC opened a proceeding to consider that question, and two public interest groups — the Citizens’ Utility Board of Oregon (CUB) and the Utility Reform Project (URP) — intervened. Relying on ORS 757.355 (1993), a statute that Oregon voters had approved in 1978 as a ballot initiative, 3 CUB argued that PGE could not include a return on its Trojan investment in its rate base, even if ORS 757.140(2) permitted it to recover its undepreciated investment in the plant in its rates. URP argued further that ORS 757.355 (1993) barred PGE from including any aspect of its Trojan investment in its rates.

*267 At the end of that proceeding, the PUC issued PUC Order No. 93-1117. The order rejected both CUB’s and URP’s arguments and declared that, ¿/PGE met certain conditions and could show certain “assumed facts” to be true in a rate case or similar forum, 4 then PGE could set rates to obtain both a “return of’ and a “return on” its Trojan investment. 5 The PUC also announced that it considered its decision to be binding and that, in any future PGE rate case, it would consider only whether PGE had proven the “assumed facts” that it had identified. CUB and URP unsuccessfully sought reconsideration of the ruling and then sought review in the Marion County Circuit Court. After the circuit court summarily affirmed, CUB and URP appealed.

Shortly thereafter, the PUC conducted a rate case in which PGE submitted evidence to prove the “assumed facts” that the PUC had identified and to show that it had met the required conditions. CUB and URP both intervened in that case, arguing, respectively, that PGE could not include a return on its investment in its rate base and that PGE could not include any aspect of its Trojan investment in its rate base. After a hearing, the PUC issued PUC Order No. 95-322, which generally allowed PGE to include in its rate base (and amortize, through its rates, over the next 16 years) the amount that it had identified as the unrecovered portion of its original Trojan investment. 6 The PUC also allowed PGE to include a return on that investment in its new rates. Consistent with its comments in PUC Order No. 93-1117, the PUC refused to consider any argument that ORS 757.355 (1993) barred “return of’ or “return on” investments in a retired plant.

The rates approved in PUC Order No. 95-322 went into effect immediately — even as CUB and URP filed an *268 action against the PUC in Marion County Circuit Court, seeking to “modify, vacate or set aside” the order pursuant to former ORS 756.580 (1993). 7 After hearing the evidence and arguments, the circuit court adopted CUB’s position that PGE was not entitled to include a “return on” its Trojan investment in its rates, and reversed. This time the PUC appealed, and that appeal was consolidated with CUB’s and URP’s earlier appeal from PUC Order No. 93-1117, which raised similar, if not identical, issues. 8

In Citizens’ Utility Board v. PUC, 154 Or App 702, 962 P2d 744 (1998), the Court of Appeals affirmed the circuit court’s decision against the PUC in the rate case and reversed the circuit court’s decision affirming the PUC in the declaratory ruling case. The court rejected the theory advanced by PGE and the PUC — that ORS 757.355 (1993) is inapplicable to retired plants and therefore has no relevance to the issue of the rate treatment of Trojan. The court also rejected PUC’s and PGE’s position that ORS 757.140(2) supersedes the earlier statute. Id. at 708-13.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mouktabis v. Oregon City Police Dept.
323 Or. App. 114 (Court of Appeals of Oregon, 2022)
Dreyer v. PGE
453 P.3d 580 (Court of Appeals of Oregon, 2019)
Gearhart v. Public Utility Commission
356 P.3d 216 (Oregon Supreme Court, 2014)
Gearhart v. PUC
Oregon Supreme Court, 2014
Bates v. Bankers Life & Casualty Co.
993 F. Supp. 2d 1318 (D. Oregon, 2014)
Gearhart v. Public Utility Commission
299 P.3d 533 (Court of Appeals of Oregon, 2013)
Wallace v. STATE EX REL. PERB
263 P.3d 1020 (Court of Appeals of Oregon, 2011)
Laing v. Psychiatric Security Review Board
222 P.3d 748 (Court of Appeals of Oregon, 2009)
Utility Reform Project v. Oregon Public Utility Commission
170 P.3d 1074 (Court of Appeals of Oregon, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
142 P.3d 1010, 341 Or. 262, 2006 Ore. LEXIS 819, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dreyer-v-portland-general-electric-co-or-2006.