Utah Construction Co. v. McIlwee

266 P. 1094, 45 Idaho 707, 1928 Ida. LEXIS 32
CourtIdaho Supreme Court
DecidedMarch 5, 1928
DocketNo. 4854.
StatusPublished
Cited by6 cases

This text of 266 P. 1094 (Utah Construction Co. v. McIlwee) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Utah Construction Co. v. McIlwee, 266 P. 1094, 45 Idaho 707, 1928 Ida. LEXIS 32 (Idaho 1928).

Opinion

TAYLOR, J.

In October, 1919, plaintiff-appellant, entered into a contract to construct for defendants, for the sum of $100,000, a railway about 3.6 miles in length, from Paris, Idaho, to the Western Phosphate Mine, according to plans and specifications of the Oregon Short Line Railroad Company made a part of the contract, the road when completed to be accepted and approved by an engineer of the railway company. Plaintiff’s action is to enforce a lien for the value of material, work and services, alleged to be in addition to those required under the contract. Its right to recover is primarily based upon an interpretation of this contract, and the sufficiency of evidence to sustain a contract or contracts alleged to have been made in addition to this one. It contained this clause:

“The work is to be pushed with all possible speed to completion and completed on or before February 1st, 1920, in a way that trains may operate over it in safety, the final *712 completion of the road may be done by them any time before July 1st, 1920.”

The $100,000 was paid in advance. The road was not completed until some time after February 1st, in a way that trains might operate over it in safety, or at least without causing the settling and sinking of the track, but was finally completed and accepted in August, 1920.

Plaintiff’s lien and complaint claimed a number of items of extras. Defendants, by cross-complaint, claimed $4,604.45 for ties furnished to plaintiff. To this cross-complaint, plaintiff filed what it termed an answer and counterclaim and cross-complaint. After admitting receipt of the ties, and denying any indebtedness therefor, it alleged, by way of counterclaim and cross-complaint, a claim of $4,090.20 under a subsequent agreement with defendants, paid by plaintiff, subsequent to filing its lien and complaint, to certain farmers in settlement of damages suffered by them by obstruction of a canal.

The court disallowed all the claims of plaintiff except one undisputed one of $654.31, and allowed defendants under their cross-complaint for the ties furnished, and entered judgment for defendants for the difference, $3,410.39. Plaintiff appeals from this judgment.

Plaintiff assigns error as to the disallowance of only three of these claims: (1) $20,100, for hauling 402 cars of ore at $1 per ton, alleged hauled at defendants’ special instance and request; (2) $13,743.63, alleged extra work necessitated to repair and restore the track due to hauling ore thereover at defendants’ request before the roadbed was completed; and (3) the claim of $4,090.20 for settling with farmers for damages to the canal; and in the refusal of certain offered evidence.

To support a recovery for repairing and restoring the roadbed due to settling thereof caused by hauling cars of ore thereover after February 1st, and before final completion, plaintiff alleged and offered to prove that “With respect to the operating of trains over the road before final completion, it was orally understood and agreed between *713 plaintiff and defendants as a part of said contract that the trains to be operated over said road, before the final completion thereof, might be so operated during the winter and early spring months while the ground was frozen, but that after the spring thaws when the roadbed became soft such trains could not be operated without injuring the roadbed, and that the provisions with respect to the operating of trains applied only to such time as the said ground remained frozen and hard until the road was finally completed”; and that in March the railroad was so far constructed that trains might safely run over it; that in April, May and June, at a time when the roadbed had become soft and yielding, and this condition known to defendants, they requested and plaintiff at this request operated these trains, resulting in the sinking and settling of the railway, necessitating the expense claimed in restoring it, and thus more material and labor to be performed and furnished than contracted for; that in doing so, plaintiff at defendants’ request used shale and rock from sources outside of those contemplated by the contract, all of which was extra work not within the contract.

The court did not err in excluding the evidence of the understanding and agreement prior to or at the making of the contract. The contract was not uncertain or am. biguous. By the provision for completion of the road for safe operation of trains, such operation after February 1st, and the necessary maintenance and completion by plaintiff, were contemplated by the contract; and to permit this evidence of prior or contemporaneous oral agreements, in effect to vary it, would be contrary to rules of evidence or interpretation. (Milner v. Earl Fruit Co., 40 Ida. 339, 232 Pac. 581.)

Plaintiff’s contention that, if the contract required it to maintain and restore the road after the hauling of ore and until final completion, then the plans were defective in that the road could not be maintained and restored during hauling by surfacing taken from the cuts, as the contract required, is not well grounded, for no allegation of *714 fraud, accident or mistake is made, nor any allegation that the plans were defective.

The mere statement of plaintiff’s manager to a defendant that there would be damage, and they would be expected to pay for it, could not render defendants liable for that which the contract contemplated, operation of cars over the track after February 1st. For the same reason, evidence of augmented sinking or settling, or the added cost of such restoration, was immaterial.

Plaintiff’s claim for added expense of securing shale and rock from sources outside of the “cuts” contemplated by the contract and specifications depended upon proof of Horst’s agency for defendants in ordering this to be done. The court’s finding against plaintiff as to this agency is supported by and not contrary to the evidence, and cannot be disturbed.

Plaintiff’s claim for compensation of $20,100 for hauling ore depends upon proof of a contract, express or implied. Error is assigned as to the finding that no agreement (request) for this hauling was made by defendants. Plaintiff contends that its evidence of specific request to haul the ore, and compliance therewith, although at no fixed price, entitles it to the reasonable value of the services.

Plaintiff seeks to make two uses of its contention that the evidence shows that this hauling was to defendants-’ interest and benefit. First, that it so strongly supports plaintiff’s evidence of an express request and agreement for the hauling as to overthrow the finding of no express request and contract. Secondly, that nevertheless this hauling was to defendants’ interest and benefit, done with their knowledge and consent, and thus plaintiff is entitled to reasonable compensation as upon an implied contract.

To support each of these contentions plaintiff argues that defendants were receiving a bonus of $1 per ton for hauling tlris ore. Plaintiff is in error in this contention. They were receiving $1.50 per ton for ore delivered at the mine end of the railway, and the Western Phosphate Company *715

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Haener v. Ada County Highway District
697 P.2d 1184 (Idaho Supreme Court, 1985)
Vance v. Connell
529 P.2d 1289 (Idaho Supreme Court, 1974)
Tapper Chevrolet Company v. Hansen
510 P.2d 1091 (Idaho Supreme Court, 1973)
Morgan v. Firestone Tire & Rubber Co.
201 P.2d 976 (Idaho Supreme Court, 1948)
Gramkow v. Farmers Cooperative Irrigation Co.
277 P. 431 (Idaho Supreme Court, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
266 P. 1094, 45 Idaho 707, 1928 Ida. LEXIS 32, Counsel Stack Legal Research, https://law.counselstack.com/opinion/utah-construction-co-v-mcilwee-idaho-1928.