Chapman v. Meiling

147 Ill. App. 411, 1909 Ill. App. LEXIS 108
CourtAppellate Court of Illinois
DecidedMarch 9, 1909
DocketGen. No. 14,456
StatusPublished
Cited by1 cases

This text of 147 Ill. App. 411 (Chapman v. Meiling) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chapman v. Meiling, 147 Ill. App. 411, 1909 Ill. App. LEXIS 108 (Ill. Ct. App. 1909).

Opinion

Me. Pbesiding Justice Smith

delivered the opinion of the court.

Appellee, Charles Chapman, brought this action in the Municipal Court of Chicago, against appellants, Gustave Meiling and Frederick W. Walthier, to recover a balance due on several different building subcontracts between them and for extra work and materials, amounting in all to $1,504.26. A trial was had before the court without a jury and the court found the issues for the plaintiff and assessed his damages at $1,015. After overruling a motion for new trial and a motion in arrest of judgment, the court rendered judgment on its finding, from which this appeal is prosecuted.

The assignments of error and the arguments of counsel present three items of controversy, the first of which is a charge of $27 for a bill of Furst & Fanning paid by appellants and charged by them to appellee on the ground that appellee ought to have, paid it, and that he agreed with appellants that it was properly chargeable to him. This amount was for recutting some old stone on what is called in the record the Ebart contract.

Appellant Walthier testified to a conversation with appellee in regard to this item in which he says he told appellee that Furst & Fanning had presented a bill for the item and that it belonged to appellee’s contract; that he asked appellee if he, the witness, was to pay the bill and Chapman replied, “I suppose so”, and that the witness then paid the bill. The witness further testified that the first he knew that Chapman objected to its being a proper charge against Mm was at the time they came together to make a final settlement and he objected to it and said it was not in the specifications, or in Ms contract. The contract between the parties was not offered in evidence, but reliance was had on the trial on the promise of appellee, Chapman, to pay the bill.

Appellee, Chapman, denied the conversation testified to by Walthier and denied that he ever agreed or consented to pay the claim or that it was a part of his contract.

Inasmuch as appellants were seeking to obtain credit for this item in their accounts with appellee, a statement of which was offered in evidence, the burden of proof was upon them under the state of the evidence in the record. We are of the opinion upon the evidence that appellants failed to sustain this item or claim by a preponderance of the evidence. The trial court therefore correctly disallowed this item to appellants.

The second item in controversy here is for $218.95 which appellants have retained and held out of the contract price between appellants and appellee for the masonry work on the Ward building on Lake avenue and Forty-seventh street, Chicago.

Appellee offered in evidence on the trial a statement rendered by appellants to appellee some time prior to the trial, showing a credit to appellee of $4,475, the entire contract price on the Ward building. It was agreed between the parties at the trial that this statement was correct with the exception of the three or four items in dispute. The item now under consideration appears in that statement as a charge against appellee as follows: “In abeyance amount of deduction claimed by Richard E. Schmidt, Arch’t., on account for masonry for A. Montgomery Ward’s Bldg., $218.95.”

Appellee contends that appellants are not entitled to retain this amount from the contract price for two reasons: (1) because it was not a part of appellee’s contract to support the wall of the adjoining building, and (2) admitting it was a part of appellants’ contract, the expense of sustaining the wall was voluntarily paid by Mr. Ward and the adjoining owner, and was not charged against appellants, hut that this amount was alleged to have been paid by Mr. Ward for damages done to the adjoining building in the course of the construction of the Ward building, and not for supporting the wall, and therefore is a matter with which appellee has nothing to do.

The record shows that two sets of specifications were offered in evidence, both issued by the architect Schmitt. Appellee offered in evidence the set on which he figured when the contract with appellants was made and which was used in doing the work. In this set it is provided in reference to the adjoining wall, “Notify the neighbors to protect their foundation walls, footings, etc., and do not allow water or sand to run from under their foundations.” Appellants offered in evidence the office copy of the specifications of Mr. Schmitt which had been in his office all the time until a few weeks before the trial, when appellants obtained it. This copy contained a provision as follows: “If the neighbor to the south does not support his house promptly the contractor shall do so, so as not to delay the progress of the work.”

The evidence does not show and it is not contended that appellee had this set of specifications before him when he figured on the work and the contract was made. The evidence shows that it always remained in the architect’s office; that there were several sets of specifications out and that appellee made his estimates on the work in appellants’ office. The evidence shows further that the set of specifications offered in-evidence by appellee was used by both parties on the work while it was in progress. The architect, Schmitt, testified that the set used by appellee was prepared by him, and that some one in his office must have given it out; that the sets of specifications were made up at different times; the first specifications were made up about two years before the building was erected and later quite a number of corrections and additions were made.

If the architect permitted Sets of specifications to go out from his office and to be used for the purpose of making estimates and in the actual construction of the building which differed in their provisions from his office copy, we think the responsibility for any mistakes or omissions in them cannot be placed upon appellee. He cannot be held to the provisions of specifications which he never saw or used. It would be an imposition and a fraud upon him to furnish him with one set of specifications on which to base his figures and make his contract, and then hold him bound by another set which contained provisions not to be found in the specifications furnished him. We are compelled'to hold on the evidence that appellee’s contract did not require him to support and sustain the wall of the adjoining building, and that appellee was right in declining to do what his contract did not require him to do.

Assuming, however, that it was the duty of appellee, under his contract, to support the wall of the adjoining building, the evidence in the record fails to show, in our opinion, that the $218.95 was necessarily expended by appellants in supporting the wall, or that said amount was actually paid for that purpose alone. Nor does the evidence show that it was reasonably worth that amount to support the wall. We conclude therefore that the judgment of the trial court in allowing to appellee this item was correct.

The third item in controversy between the parties arises upon the cross-errors of appellee. It is contended by appellee that the trial court erred in refusing to allow to him the claim or item of $157 for extra work done on the Saddle & Cycle Club contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Utah Construction Co. v. McIlwee
266 P. 1094 (Idaho Supreme Court, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
147 Ill. App. 411, 1909 Ill. App. LEXIS 108, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chapman-v-meiling-illappct-1909.