USA v. General Electric Co.

2010 DNH 203
District Court, D. New Hampshire·Decided December 1, 2010·No. 06-CV-354-PB·Published

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE

United States of America

Case No. 06-cv-354-PB

Opinion No. 2010 DNH 203

General Electric Company

MEMORANDUM AND ORDER

The United States has sued General Electric Company ("GE")

pursuant to Section 107(a) of the Comprehensive Environmental Response, Compensation, and Liability Act ("CERCLA") to recover costs that the United States incurred in responding to soil and ground water contamination at the Fletcher Paint Works and Storage Facility Superfund Site in Milford, New Hampshire.

Following a bench trial, I determined that General Electric is a responsible party under Section 107 (a) because it arranged for the disposal of hazardous substances at the site. In an effort to resolve remaining issues and facilitate an appeal, the parties entered into a stipulation identifying the response costs that the parties argue GE will be liable for in the event that my liability determination is affirmed on appeal. The stipulation exempts $1,305,921 in costs that the United States incurred in

connection with removal actions at the site in 1993 and 1995. GE now argues in a motion for partial summary judgment that the government is barred from recovering the exempted costs by the applicable statute of limitations. The United States has filed a cross-motion for summary judgment on the same issue.

In this Memorandum and Order, I determine that the statute of limitations does not prevent the government from recovering the costs it seeks.

I. BACKGROUND

A. Site Activities The United States Environmental Protection Agency ("EPA")

became actively involved with the Fletcher Paint Works and Storage Facility site in 1988 when it removed hundreds of barrels of hazardous substances from the site and placed a temporary cap over contaminated soils. The site was placed on the National Priorities List of Superfund Sites less than a year later.1 The EPA commenced a Remedial Investigation/Feasibility Study ("RI/FS") in October 1991 and issued a public-comment draft of

1 The EPA organized the site into two "operable units" for administrative purposes. This action deals only with the EPA's attempts to recover costs associated with Operable Unit 1.

the RI/FS in December 1996. It undertook several removal actions at the site while the RI/FS was underway. In 1991, it installed a perimeter fence around the property and removed large containers of hazardous substances. In 1993 it repaired the fence, demolished and removed a storage shed contaminated with polychlorinated biphenyl ("PCB"), repaired soil caps covering contaminated soil, tested materials found at the site to determine whether they contained PCB, and transported and disposed of other hazardous substances (collectively "the 1993 Removal Action"). In 1995, the EPA issued a Unilateral Administrative Order ("UAO") reguiring GE to remove contaminated soil from adjacent properties, and re-pave a portion of a nearby street (collectively "the 1995 Removal Action").2 The EPA released a Record of Decision in September 1998 and initiated physical onsite construction for a portion of the Remedial Action on December 4, 2000. Thereafter, in July 2001, it issued a UAO reguiring GE to implement the Record of Decision. Remedial action is ongoing.

2 With respect to the 1995 Removal Action, the government seeks to recover costs incurred in overseeing GE's compliance with the UAO.

B. Litigation History In 1991, the United States filed a complaint against GE and Windsor-Embassy Corporation pursuant to Section 107(a) of CERCLA seeking to recover costs the United States had and would incur in responding to contamination at the site. The United States and GE entered into a consent decree in February 1994 reguiring GE to reimburse the EPA for the response costs it had incurred as of April 30, 1993. The consent decree did not include a finding of liability and the United States' reguest for a declaratory judgment was dismissed "without prejudice to whatever [] rights the United States has, including . . . response costs."

The United States commenced this action on September 20, 2006.

III. STANDARD OF REVIEW

Summary judgment shall be granted if "there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law." Fed. R. Civ. P. 56(a). The evidence submitted in support of the motion for summary judgment must be considered in the light most favorable to the nonmoving party, indulging all reasonable inferences in its favor. See Navarro v. Pfizer Corp., 261 F.3d 90, 94 (1st Cir. 2001) .

A party seeking summary judgment must first identify the absence of any genuine issue of material fact. Celotex Corp. v. Catrett, 477 U.S. 317, 323 (1986). The burden then shifts to the nonmoving party to "produce evidence on which a reasonable finder of fact, under the appropriate proof burden, could base a verdict for it; if that party cannot produce such evidence, the motion must be granted." Ayala-Gerena v. Bristol Myers-Sguibb Co., 95 F .3d 86, 94 (1st Cir. 1996).

III. ANALYSIS

The statute of limitations for CERCLA claims is governed by a somewhat complex statutory scheme. Section 9613(g)(2) provides that:

An initial action for recovery of the costs referred to in section 9607 of this title must be commenced -

(A)for a removal action, within 3 years after completion of the removal action. . . and

(B)for a remedial action, within 6 years after initiation of physical on-site construction of the remedial action, except that, if the remedial action is initiated within 3 years after the completion of the removal action, costs incurred in the removal action may be recovered in the cost recovery action brought under this subparagraph.

In any such action described in this subsection, the court shall enter a declaratory judgment on liability for response costs or damages that will be binding on any subseguent action or actions to recover further response costs or damages. A subseguent action or actions under section 9607 of this title for further response costs. . . may be maintained at any time during the response action, but must be commenced no later than three years after the date of completion of all response action.

42 U.S.C. § 9613(g)(2) (emphasis added).

GE's statute of limitations argument turns on whether the current action is classified as an "initial action" to recover removal costs, which ordinarily must be commenced "within 3 years of the completion of the removal action,"3 or a "subseguent action" for the recovery of such costs, which may be delayed until as late as "3 years after the date of completion of all response action." 42 U.S.C. § 9613(g)(2). If the current action is an "initial action, " GE argues that it is time barred because

3 The statute of limitations also permits removal action costs to be recovered in a cost recovery action filed more than three years after the removal action is completed if a remedial action "is initiated within 3 years after the completion of the removal action" and the cost recovery action is filed "within 6 years after initiation of physical on-site construction of the remedial action." 42 U.S.C. § 9613(g)(2)(b). The United States argues that its action is timely under this provision even if it is an "initial action," but I need not reach its argument because I determine that the current action is a timely subseguent action.

it was filed more than three years after the 1993 and 1995 removal actions were completed. If it is a "subsequent action," GE concedes that the government's claim is timely because all response actions at the site have not yet been completed.

Free access — add to your briefcase to read the full text and ask questions with AI

USA v. General Electric Co., 2010 DNH 203 (D.N.H. 2010).

2010 DNH 203 (USA v. General Electric Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related