USA for u v.

Court of Appeals for the First Circuit·Decided November 29, 1993·No. 93-1541·Published

Opinion

USCA1 Opinion


November 29, 1993 [NOT FOR PUBLICATION]

UNITED STATES COURT OF APPEALS
FOR THE FIRST CIRCUIT

____________________

No. 93-1541

UNITED STATES OF AMERICA, for
u/b/o LUIS A. CABRERA, S.E.
A SPECIAL PARTNERSHIP,

Plaintiff, Appellee,

v.

SUN ENGINEERING ENTERPRISES, INC.,
AND CNA CASUALTY OF PUERTO RICO,

Defendants, Appellants.

____________________

APPEAL FROM THE UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF PUERTO RICO

[Hon. Jos Antonio Fust , U.S. District Judge]
___________________

____________________

Before

Breyer, Chief Judge,
___________

Coffin, Senior Circuit Judge,
____________________

and Torruella, Circuit Judge.
_____________

_____________________

Federico Lora-L pez for appellants.
___________________
Thomas Doran-Gelabert, with whom Eduardo Castillo-Blanco was
_____________________ _______________________
on brief for appellee.

____________________

____________________

Per Curiam. This case concerns an action brought under
__________

the Miller Act, 40 U.S.C. 270a-f (1986), in the name of the

United States for the use and benefit of Luis A. Cabrera, S.E.

("Cabrera"), a subcontractor, against Sun Engineering

Enterprises, Inc. ("Sun Engineering"), a general contractor, and

its surety, CNA Casualty of Puerto Rico ("CNA"). In the

complaint, Cabrera claimed money it was due under a subcontract

with Sun Engineering. After a non-jury trial, the United States

District Court for the District of Puerto Rico awarded Cabrera

$44,769.25. Sun Engineering then filed this appeal claiming that

the district court improperly amended the pre-trial order at

trial, and that there was insufficient evidence to support the

court's findings of fact. For the reasons stated herein, we

affirm.

I. BACKGROUND
I. BACKGROUND

We review the facts in favor of the prevailing party at

trial, Cabrera. See American Title Ins. Co. v. East West
___ __________________________ __________

Financial Corp., 959 F.2d 345, 346 (1st Cir. 1992). Sun
________________

Engineering is a construction company which was the prime

contractor for a federal project involving partially renovating

the United States General Post Offices in San Juan, Puerto Rico

("the Project"). Cabrera was a subcontractor on the Project. On

December 21, l989, Mr. Luis Cabrera submitted a price quotation

to Mr. Francisco Jim nez, the president of Sun Engineering, which

detailed, item by item, the work which the Project blueprints and

specifications required with respect to supplying and installing

-2-

vinyl floors, dry wall partitions, and acoustical ceilings. The

quotation estimated the cost of the work to be $106,707.35.1

Mr. Cabrera and Mr. Jim nez then discussed the precise terms of

the quotation. On January 8, l990, Sun Engineering sent a letter

to Cabrera accepting Cabrera's December 21, l989 quotation.

Although the parties had negotiated some changes to the work

specified in the quotation, and a reduced "estimated" contract

price of $80,000, an absolute price for the contract was never

agreed upon. Rather, Cabrera and Sun Engineering informally

agreed that Sun Engineering would pay Cabrera based on the work

Cabrera actually performed.

After the contract was formed, Cabrera commenced work.

During the course of the Project, Mr. Jim nez verbally requested

that Cabrera perform additional work not encompassed by the

original contract. This work involved floor underlays. Mr.

Ismael El as, the designer of the Project who also served as the

Project inspector for the Post Office, also verbally requested

Cabrera to make changes with respect to some partitions it was

installing. Cabrera completed all work required on the Project

by June 5, l99l.

Cabrera billed Sun Engineering $105,495.39 for the work

it performed. Sun Engineering made progress payments to Cabrera

totalling $60,726.14. Sun Engineering refused to pay Cabrera the

____________________

1 At trial, there was some dispute regarding the precise dollar
figure of this initial quotation. The present appeal does not in
any way turn upon the exact figure of this initial quotation, and
for the purposes of this opinion, we will assume that $l06,707.35
was the correct figure.

-3-

balance of $44,769.25.

Cabrera then filed suit. As its defense, Sun

Engineering claimed that the contract was for a total price of

$80,000, and therefore, Sun Engineering only owed Cabrera

$l9,273.86. Sun Engineering also claimed that Cabrera

negligently performed its work, and delayed the completion of the

Project.

After trial, the district court found that the parties

entered into an informal contract. In accordance with the

contract, Cabrera was entitled to be paid $105,495.39 for the

work it had performed on the Project. The court found that

Cabrera was not responsible for any Project delays. Because Sun

Engineering had only paid Cabrera $60,726.14, the court entered

judgment in Cabrera's favor in the amount of $44,769.25.

Sun Engineering then filed this appeal. Sun

Engineering makes three arguments on appeal. Sun Engineering

Free access — add to your briefcase to read the full text and ask questions with AI

USA for u v., (1st Cir. 1993).

USA for u v. (USA for u v.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related