USA for u v.
Opinion
USCA1 Opinion
November 29, 1993 [NOT FOR PUBLICATION]
UNITED STATES COURT OF APPEALS
FOR THE FIRST CIRCUIT
____________________
No. 93-1541
UNITED STATES OF AMERICA, for
u/b/o LUIS A. CABRERA, S.E.
A SPECIAL PARTNERSHIP,
Plaintiff, Appellee,
v.
SUN ENGINEERING ENTERPRISES, INC.,
AND CNA CASUALTY OF PUERTO RICO,
Defendants, Appellants.
____________________
APPEAL FROM THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF PUERTO RICO
[Hon. Jos Antonio Fust , U.S. District Judge]
___________________
____________________
Before
Breyer, Chief Judge,
___________
Coffin, Senior Circuit Judge,
____________________
and Torruella, Circuit Judge.
_____________
_____________________
Federico Lora-L pez for appellants.
___________________
Thomas Doran-Gelabert, with whom Eduardo Castillo-Blanco was
_____________________ _______________________
on brief for appellee.
____________________
____________________
Per Curiam. This case concerns an action brought under
__________
the Miller Act, 40 U.S.C. 270a-f (1986), in the name of the
United States for the use and benefit of Luis A. Cabrera, S.E.
("Cabrera"), a subcontractor, against Sun Engineering
Enterprises, Inc. ("Sun Engineering"), a general contractor, and
its surety, CNA Casualty of Puerto Rico ("CNA"). In the
complaint, Cabrera claimed money it was due under a subcontract
with Sun Engineering. After a non-jury trial, the United States
District Court for the District of Puerto Rico awarded Cabrera
$44,769.25. Sun Engineering then filed this appeal claiming that
the district court improperly amended the pre-trial order at
trial, and that there was insufficient evidence to support the
court's findings of fact. For the reasons stated herein, we
affirm.
I. BACKGROUND
I. BACKGROUND
We review the facts in favor of the prevailing party at
trial, Cabrera. See American Title Ins. Co. v. East West
___ __________________________ __________
Financial Corp., 959 F.2d 345, 346 (1st Cir. 1992). Sun
________________
Engineering is a construction company which was the prime
contractor for a federal project involving partially renovating
the United States General Post Offices in San Juan, Puerto Rico
("the Project"). Cabrera was a subcontractor on the Project. On
December 21, l989, Mr. Luis Cabrera submitted a price quotation
to Mr. Francisco Jim nez, the president of Sun Engineering, which
detailed, item by item, the work which the Project blueprints and
specifications required with respect to supplying and installing
-2-
vinyl floors, dry wall partitions, and acoustical ceilings. The
quotation estimated the cost of the work to be $106,707.35.1
Mr. Cabrera and Mr. Jim nez then discussed the precise terms of
the quotation. On January 8, l990, Sun Engineering sent a letter
to Cabrera accepting Cabrera's December 21, l989 quotation.
Although the parties had negotiated some changes to the work
specified in the quotation, and a reduced "estimated" contract
price of $80,000, an absolute price for the contract was never
agreed upon. Rather, Cabrera and Sun Engineering informally
agreed that Sun Engineering would pay Cabrera based on the work
Cabrera actually performed.
After the contract was formed, Cabrera commenced work.
During the course of the Project, Mr. Jim nez verbally requested
that Cabrera perform additional work not encompassed by the
original contract. This work involved floor underlays. Mr.
Ismael El as, the designer of the Project who also served as the
Project inspector for the Post Office, also verbally requested
Cabrera to make changes with respect to some partitions it was
installing. Cabrera completed all work required on the Project
by June 5, l99l.
Cabrera billed Sun Engineering $105,495.39 for the work
it performed. Sun Engineering made progress payments to Cabrera
totalling $60,726.14. Sun Engineering refused to pay Cabrera the
____________________
1 At trial, there was some dispute regarding the precise dollar
figure of this initial quotation. The present appeal does not in
any way turn upon the exact figure of this initial quotation, and
for the purposes of this opinion, we will assume that $l06,707.35
was the correct figure.
-3-
balance of $44,769.25.
Cabrera then filed suit. As its defense, Sun
Engineering claimed that the contract was for a total price of
$80,000, and therefore, Sun Engineering only owed Cabrera
$l9,273.86. Sun Engineering also claimed that Cabrera
negligently performed its work, and delayed the completion of the
Project.
After trial, the district court found that the parties
entered into an informal contract. In accordance with the
contract, Cabrera was entitled to be paid $105,495.39 for the
work it had performed on the Project. The court found that
Cabrera was not responsible for any Project delays. Because Sun
Engineering had only paid Cabrera $60,726.14, the court entered
judgment in Cabrera's favor in the amount of $44,769.25.
Sun Engineering then filed this appeal. Sun
Engineering makes three arguments on appeal. Sun Engineering
Free access — add to your briefcase to read the full text and ask questions with AI
USA for u v., (1st Cir. 1993).
USA for u v. (USA for u v.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Related
Joseph Rodrigues v. Ripley Industries, Inc., Joseph Rodrigues v. Ripley Industries, Inc.
507 F.2d 782 (First Circuit, 1974)
United States of America for the Use and Benefit of Control Systems, Inc. v. Arundel Corporation, Defendants-Cross Cross-Appellees v. Lar Electric, Inc., Defendant-Cross Cross-Appellant
814 F.2d 193 (Fifth Circuit, 1987)
Awilda Ramirez Pomales v. Becton Dickinson & Co., S.A.
839 F.2d 1 (First Circuit, 1988)
Cindy Nickerson v. G.D. Searle & Company and Ortho Pharmaceutical Corporation
900 F.2d 412 (First Circuit, 1990)
E.H. Ashley & Co., Inc. And Willow Associates v. Wells Fargo Alarm Services, Etc.
907 F.2d 1274 (First Circuit, 1990)
Roland M. And Miriam M. v. The Concord School Committee
910 F.2d 983 (First Circuit, 1990)
American Title Insurance Company v. East West Financial Corporation, American Title Insurance Company v. East West Financial Corporation, Bay Loan & Investment Bank
959 F.2d 345 (First Circuit, 1992)
Dedham Water Co., Inc. v. Cumberland Farms Dairy, Inc.
972 F.2d 453 (First Circuit, 1992)
Westcott Construction Corp. v. Firemen's Fund of New Jersey
996 F.2d 14 (First Circuit, 1993)