US Trinity Engy Svcs v. SE Directional Drilling

135 F.4th 303
Court of Appeals for the Fifth Circuit·Decided April 28, 2025·No. 24-10833·Published·Cited by 3 cases

Opinion

Case: 24-10833 Document: 45-1 Page: 1 Date Filed: 04/28/2025

United States Court of Appeals for the Fifth Circuit ____________ United States Court of Appeals Fifth Circuit

No. 24-10833 FILED April 28, 2025 ____________ Lyle W. Cayce United States Trinity Energy Services, L.L.C., Clerk

Plaintiff—Appellant,

versus

Southeast Directional Drilling, L.L.C.,

Defendant—Appellee. ______________________________

Appeal from the United States District Court for the Northern District of Texas USDC No. 4:23-MC-8 ______________________________

Before Stewart, Clement, and Willett, Circuit Judges. Edith Brown Clement, Circuit Judge: United States Trinity Energy Services, L.L.C. (“Trinity Energy”) and Southeast Directional Drilling, L.L.C. (“Southeast Drilling”) were parties to a subcontract for the construction of natural gas pipelines. After a dispute arose over the liability for the “stand-by costs” incurred during construction, the parties agreed to arbitration. A panel of three arbitrators concluded that Southeast Drilling was entitled to stand-by costs in the amount of $1,662,000 from Trinity Energy. The district court denied Trinity Energy’s petition to vacate the arbitration award and granted Southeast Drilling’s motion to confirm it. Trinity Energy appealed. We AFFIRM. Case: 24-10833 Document: 45-1 Page: 2 Date Filed: 04/28/2025

No. 24-10833

I. Trinity Energy contracted with Sunoco Pipeline, L.P. (“Sunoco”) to serve as the general contractor for the construction of natural gas pipelines from shale fields in western Pennsylvania, among other places, to the Delaware River for transport. In early 2020, Trinity Energy then subcontracted with Southeast Drilling for work on a special portion of the project involving horizontal directional drilling. The project encountered a series of delays. Sunoco was tasked with obtaining drilling permits for the project but procured them at a slow pace. On two occasions, Southeast Drilling experienced “loss of circulation” or “inadvertent returns” caused by mud perforating the formation. Sunoco accordingly directed Southeast Drilling to stop its work temporarily, resulting in additional delays. Later that spring, the Pennsylvania governor issued an executive order halting non-essential work throughout the state because of COVID-19, and in response, Sunoco directed Trinity Energy to stop drilling on the project yet again. Trinity Energy and Southeast Drilling agreed in their subcontract that stand-by costs—or expenses incurred when and workers are present at the drilling site but unable to perform drilling operations—would be reimbursed. Section 3.07 of the subcontract provided, In the event Contractor or Owner suspends work on the Project for any reason, other than for Subcontractor’s default under this Agreement, Subcontractor shall be entitled to and shall be paid for all stand-by costs as a result of such suspension, including all de-mobilization and re-mobilization costs, and the Project Schedule shall be extended. Because of the various delays, stand-by charges were assessed during each event where Southeast Drilling’s equipment and personnel were on-site but unable to drill.

2 Case: 24-10833 Document: 45-1 Page: 3 Date Filed: 04/28/2025

No. 24-10833

In March 2021, Sunoco and Southeast Drilling entered into an agreement where Sunoco provided “payment in full settlement of all claims against Company and the Liens” (the “Direct Pay Agreement”). 1 Shortly after executing this agreement, Sunoco separately participated in mediation with Trinity Energy where the parties agreed to a global settlement in exchange for the release of Trinity Energy’s claims against Sunoco. Neither agreement settled the dispute over stand-by costs between Trinity Energy and Southeast Drilling. To resolve this issue, the parties turned to the subcontract, which included a provision allowing them either to file suit in court or enter arbitration for “all claims, disputes, and controversies arising out of or relating to” their agreement. In May 2021, Trinity Energy initiated arbitration by seeking a declaration of non- responsibility for the stand-by costs resulting from Sunoco’s delays and the COVID-19 pandemic. Southeast Drilling counterclaimed, demanding compensation from Trinity Energy for these costs. A panel of three arbitrators—after entertaining oral argument, reviewing the parties’ written submissions, and considering the relevant provisions of the subcontract—concluded that Southeast Drilling was entitled to $1,662,000 of stand-by costs from Trinity Energy. On June 6, 2023, Trinity Energy filed a petition to vacate the arbitration award in the United States District Court for the Northern District of Texas. Relying on 9 U.S.C. § 10(a)(4), Trinity Energy sought to vacate the final award because “the arbitration panel exceeded its authority.”

_____________________ 1 Aside from arguing the subcontract contains competing provisions limiting its liability for stand-by costs, Trinity Energy also contends Southeast Drilling expressly waived and released any claim for additional payment against Sunoco for the project by executing the Direct Pay Agreement and therefore relinquished its “sole and exclusive remedy” against Trinity Energy in the form of a pass-through claim.

3 Case: 24-10833 Document: 45-1 Page: 4 Date Filed: 04/28/2025

No. 24-10833

On June 29, 2023, Southeast Drilling filed both a response in opposition to Trinity Energy’s petition and a cross-motion to confirm the arbitration award. On October 2, 2023, the district court entered an order denying the motion to vacate the award. Trinity Energy appealed the district court’s denial of its petition while Southeast Drilling’s cross-motion to confirm the arbitration award remained pending. U.S. Trinity Energy Servs., L.L.C., v. Se. Directional Drilling, No. 23-11071, 2024 WL 3738879, at *1 (5th Cir. 2024) (per curiam). A panel of this court dismissed that appeal as interlocutory by concluding it did not have jurisdiction. Id. at *2. The district court subsequently granted Southeast Drilling’s cross- motion to confirm the arbitration award on September 4, 2024. Trinity Energy timely appealed. II. We review de novo a district court’s order confirming an arbitration award. Rainier DSC 1, L.L.C. v. Rainier Cap. Mgmt., L.P., 828 F.3d 362, 364 (5th Cir. 2016). An arbitrator’s decision will be vacated “only in very unusual circumstances.” Oxford Health Plans LLC v. Sutter, 569 U.S. 564, 568 (2013) (quoting First Options of Chi., Inc. v. Kaplan, 514 U.S. 938, 942 (1995)). In our circuit, “judicial review of an arbitration award is extraordinarily narrow,” Cooper v. WestEnd Cap. Mgmt., L.L.C., 832 F.3d 534, 543–44 (5th Cir. 2016) (quoting Rain CII Carbon, LLC v. ConocoPhillips Co., 674 F.3d 469, 471–72 (5th Cir. 2012)), and our review is “exceedingly deferential” to the arbitration panel’s decision, Brabham v. A.G. Edwards & Sons, 376 F.3d 377, 380 (5th Cir. 2004). “[D]oubts or uncertainties must be resolved in favor of upholding” an arbitration award. Cooper, 832 F.3d at 544.

4 Case: 24-10833 Document: 45-1 Page: 5 Date Filed: 04/28/2025

No. 24-10833

III. Congress enacted the Federal Arbitration Act, 9 U.S.C. §§ 1–16

Free access — add to your briefcase to read the full text and ask questions with AI

US Trinity Engy Svcs v. SE Directional Drilling, 135 F.4th 303 (5th Cir. 2025).

135 F.4th 303 (US Trinity Engy Svcs v. SE Directional Drilling) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related