US Pollution Control, Inc. v. NAT. AMERICAN INS.
This text of 663 So. 2d 119 (US Pollution Control, Inc. v. NAT. AMERICAN INS.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
UNITED STATES POLLUTION CONTROL, INC., Plaintiff-Appellee,
v.
NATIONAL AMERICAN INSURANCE COMPANY, Defendant-Appellant.
Court of Appeal of Louisiana, Third Circuit.
*120 Allen Dale Darden, Michael David Ferachi, Baton Rouge, for U.S. Pollution Control, Inc.
Paul Joseph McMahon III, Lafayette, for National American Ins. Co.
William Littlejohn Goode, Paul Albert Landry, Lafayette, for City of Lafayette.
Before KNOLL, SULLIVAN, and BROUILLETTE[*], Judges.
KNOLL, Judge.
The primary issue on appeal is whether plaintiff, United States Pollution Control, Inc. (USPCI), qualifies as a "claimant" under the Louisiana Public Works Act, La.R.S. 38:2241 et seq.
Finding that USPCI was a claimant, the trial court granted partial summary judgment in favor of USPCI, entitling it to recover the full amount of a performance and payment bond issued by the defendant, National American Insurance Company (National American). The trial court denied USPCI's request for attorney's fees pursuant to La.R.S. 38:2246 and dismissed with prejudice USPCI's claims for contractual interest, attorney's fees, and penalties.[1]
National American appeals, contending that the trial court improperly granted summary judgment on the performance and payment bond because USPCI is not a "claimant" under the Louisiana Public Works Act. USPCI answered the appeal, contending that the trial court improperly denied its motion for summary judgment on the issue of statutory attorney's fees.[2]
FACTS
The City of Lafayette and Martech USA, Inc. (Martech) entered into a "PCB Site Remediation" agreement to clean up a hazardous waste site. Martech provided a performance and payment bond of $222,525 issued by National American as the surety. Martech subcontracted with USPCI to haul and dispose of the hazardous waste at a facility owned by USPCI in the state of Utah. Although the City issued two change orders which increased the base contract *121 price to $425,500, the performance and payment bond was not increased.
USPCI invoiced Martech $342,108.27, representing work done, labor performed, and materials and supplies furnished by USPCI. Martech made a single payment of $93,075. Martech disputed some of USPCI's invoices and claimed the correct total owed was $318,563.92. USPCI agreed to reduce its total charges, which left a balance owed of $225,488.92. Despite amicable demand by USPCI, Martech and National American failed to pay. Subsequently, Martech filed for bankruptcy protection in federal district court for the District of Alaska.
USPCI preserved its claim against National American by recording a sworn statement of claim and privilege in the mortgage records of Lafayette Parish for $225,488.92, together with interest, attorney's fees, and costs.
CLAIMANT UNDER THE PUBLIC WORKS ACT
Appellate courts review summary judgments de novo using the same criteria that govern the trial court's consideration of whether summary judgment is appropriate. Schroeder v. Board of Supervisors, 591 So.2d 342 (La.1991). La.Code Civ.P. art. 966 provides for the granting of summary judgment if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to material fact, and that mover is entitled to summary judgment as a matter of law.
Determining whether USPCI is entitled to summary judgment as a matter of law depends upon the resolution of two issues: (1) whether USPCI is a "claimant" as that term is defined in the Louisiana Public Works Act; and (2) if USPCI is a "claimant," is USPCI entitled to attorney's fees pursuant to La. R.S. 38:2246?
The Public Works Act was passed to protect laborers and materialmen involved in public works projects by offering them a vehicle by which they could recover monies owed to them for material or labor spent on behalf of the public works project. See Wilkin v. Dev Con Builders, Inc., 561 So.2d 66 (La.1990). Because laborers and materialmen are prohibited from placing a lien against the actual property which is the subject of the public works project, the Act allows them to assert their claims against the unexpended funds financing the public work or the surety required by the Act. Id. This process has been succinctly summarized by the Louisiana Supreme Court in Construction Materials, Inc. v. American Fidelity Fire Ins. Co., 388 So.2d 365 (La.1980):
The Public Works Act was enacted for the purpose of protecting persons doing work, performing labor or furnishing material for the construction, alteration or repair of public buildings, roads or works of any character. The statute accomplishes this by providing (1) the governing authority must require of the contractor a bond, with solvent surety, for the faithful performance of the contract and payment by the contractor and his sub-contractors for labor or material furnished in the construction, alteration or repair of public works; and (2) generally, a person due money for labor or materials furnished for the construction, alteration or repair of any public works may file a sworn statement of the amount due him with the governing authority and in the mortgage records, which, when timely recorded, makes the governing authority liable for his claim if it is not deducted from payments made to the contractor.
Id. at 366-67 (citations omitted).
La.R.S. 38:2241 requires that a contractor furnish a surety for the faithful performance of the public works contract. Under La.R.S. 38:2241, those who do not enjoy contractual privity with the general contractor on a public work are given a cause of action against the general contractor and his surety as provided for in the statute. However, this cause of action is limited to only those persons who meet the definition of a claimant as defined by the Act. La.R.S. 38:2241; 38:2242. La. R.S. 38:2242 provides in pertinent part as follows:
A. (1) "Claimant", as used in this Chapter, means any person to whom money is due pursuant to a contract with the owner *122 or a contractor or subcontractor for doing work, performing labor, or furnishing materials or supplies for the construction, alteration, or repair of any public works, or for transporting and delivering such materials or supplies to the site of the job by a for-hire carrier, or for furnishing oil, gas, electricity, or other materials or supplies for use in machines used in the construction, alteration, or repair of any public works,....
The Public Works Act is sui generis and provides exclusive remedies to parties in public construction work. Metro Builders Hardware, Inc. v. Burko Const., Inc., 93-1970 (La.App. 4 Cir. 2/25/94); 633 So.2d 838; writ denied, 94-727 (La. 5/6/94); 637 So.2d 1049; Martinolich v. Albert, 143 So.2d 745 (La.App. 1 Cir.1962). Because the Public Works Act is in derogation of common rights, it is stricti juris and the liability of a surety may not be expanded beyond the statute. Rester v. Moody & Stewart, 172 La. 510, 134 So. 690 (1931); National Sur. Corp. v. Highland Park Country Club, Inc., 111 So.2d 811 (La.App. 2 Cir.1959).
In an affidavit submitted in support of its motion for summary judgment, USPCI contends that it performed the following work:
USPCI provided the transportation, processing, treatment, and disposal of the waste material in accordance with the terms of the Waste Disposal Agreement.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
663 So. 2d 119, 95 La.App. 3 Cir. 153, 1995 La. App. LEXIS 2423, 1995 WL 515732, Counsel Stack Legal Research, https://law.counselstack.com/opinion/us-pollution-control-inc-v-nat-american-ins-lactapp-1995.